H. W. Bond & Bro. v. City of New Orleans

171 So. 572, 186 La. 60, 1936 La. LEXIS 1269
CourtSupreme Court of Louisiana
DecidedMarch 30, 1936
DocketNo. 33439.
StatusPublished
Cited by1 cases

This text of 171 So. 572 (H. W. Bond & Bro. v. City of New Orleans) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H. W. Bond & Bro. v. City of New Orleans, 171 So. 572, 186 La. 60, 1936 La. LEXIS 1269 (La. 1936).

Opinions

HIGGINS, Justice.

Caldwell Bros, and H. W. Bond & Bro., partnerships engaged in business as general contractors, brought this action against the City of New Orleans to recover the sum of $29,892.61, representing alleged extras consisting of brass strippings placed in the terrazzo pavement on the sidewalks and the neutral ground of Canal street, which were paved under a written contract between the parties.

The defense was twofold: (1) That under the agreement, the city engineer’s decision would be final and binding on both parties and that this official had ruled that *63 the brass strippings were not to be considered as extra in accordance with the plans and specifications under which the paving was installed. (2) That the brass strip-pings were provided for in the plans and •specifications and therefore not extra.

The city also called the New Orleans Public Service, Inc., in warranty, alleging that under a contract with that corporation its pro rata would be $17,646.17, in the event the city would be held liable.

The New Orleans Public Service, Inc., filed an exception of no cause or right of action to the call in warranty on the grounds: (1) That the pleadings affirmatively showed that the city, without the consent or authorization of the New Orleans Public Service,'Inc., had waived the provision of the contract which made the decision of the city engineer final in any dispute between the contractor, and the city and had done so after the city engineer had ruled that the claim for the brass strip-pings was not extra. (2) That the city was without authority or right to waive the above provision of the contract.

The exception was overruled, and the New Orleans Public Service, Inc., answered, reiterating these defenses, and on the merits pleaded the same defense as the city.

There was judgment in favor of the plaintiff as prayed for, there being a stipulation entered into between the parties that there was no dispute as to the amount, and further judgment dismissing the call in warranty of the City of New Orleans.

The .city appealed.

The officials of the City of New Orleans decided to pave the sidewalks and the neutral ground of Canal street with terrazzo pavement. Advertisement for bids was published during March, 1929, and the bids received in the early part of April, 1929. The lowest bid by H. W. Bond & Bro. was published on April 15, 19, and 22, 1929, and formally accepted on July 16, 1929. Shortly thereafter, H. W. Bond & Bro. assigned part of the contract to Caldwell Bros.

There was some discussion between H. W. Bond and the city engineer as to how the work was to be executed, since there was not to be any interference with the pedestrian traffic on Canal street during the laying of the pavement. The specifications provided that half of the pavement of each of the sidewalks would be laid at a time, in order to permit pedestrians to have ingress and egress to the stores and buildings on the street during the time that the work was being performed. In June, 1929, there appears to have been further discussion between these parties, but the tenor of the conversation is doubtful, except that it pertained to brass strippings. On August 1, 1929, the contractor definitely informed the city engineer that brass strippings in .anything but construction joints were to be considered extra. The city engineer ruled against the contractor, who threatened to refuse to go forward with the agreement. After some negotiation between the city engineer, the city attorney, ' and the attorney for the contractor, the matter in controversy was placed before the Commission Council, resulting in an understanding that the contractor would proceed with the formal signing of the written contract and *65 the work, under protest, with reservation of his right to litigate the matter. It appears that this action was taken by the Commission Council, in order to prevent a delay of the work and apparently because of the advantage of the low bid. The formal contract in authentic or notarial form was entered into on November 18, 1929.

The Commission Council on January 7, 1930, in accordance with the negotiations and understanding between the parties, adopted a resolution reading, in part, as follows:

“Therefore, be it resolved by the Commission Council of the City of New Orleans, that it takes cognizance of the controversy between H. W. Bond & Brother, and' Honorable Bryson Vallas, City Engineer, as evidenced by the communication aforesaid, and approves the action of the City Engineer, as to his authority and interpretation of the plans and specifications aforesaid; and further ratifies the action of Bertrand I. Cahn, City Attorney, to the extent that H. W. Bond & Brothers be, and they are hereby permitted to reserve their rights to litigate their asserted claim under their interpretation of' the contract aforesaid, and the Commission Council approves and ratifies the figure $.628 per square yard, for furnishing and installing brass joint strips, as aforesaid, as the basis for any extra compensation that may be due and payable to H. W. Bond & Brother, if the Court determines their interpretation to be correct.”

The terrazzo pavement was laid with the brass strippings, under the supervision of the city engineer, and the work was formally and finally accepted by the city. This suit then followed.

The argument of the City of New Orleans under its exceptions of no right or catise of action, that the city engineer’s ruling under the contract, plans, and specifications was to be final in any dispute between the parties, is plainly without merit, because the resolution above quoted clearly shows' that the parties agreed to submit the question to the court. The city, therefore, modified the contract to the extent of agreeing that the decision of the court would be final, instead of the decision of the city engineer. To place any other construction on the resolution would lead to the absurd conclusion that, although the city engineer had already ruled against the contractor, he agreed that after actually placing the brass strippings in the pavement, the contractor would again submit the question to the engineer for his decision. The city’s exception of no right or cause of action was correctly overruled.

The decision on the merits resolves itself into a question of the correct interpretation of the plans and specifications under which the bids were made, the contract entered into, and the work performed.

In the general specifications and standard plans for street paving and temporary sub-surfacing, adopted by the Commission Council ón September 7, 1927, by Ordinance 9986 C.C.S., we find subparagraph H, section 96, at page 59, reading, as follows :

"Artificial stone footwalks shall .be divided into, blocks of such dimensions as the City Engineer may designate by means of a, jointer or groover'in such manner as to *67 completely separate the wearing or top course of adjacent blocks. Transverse expansion joints shall be made at intervals of about thirty (30) feet so as to separate the footwalk into slabs or sections.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bank of Baton Rouge v. Hendrix
193 So. 713 (Supreme Court of Louisiana, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
171 So. 572, 186 La. 60, 1936 La. LEXIS 1269, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-w-bond-bro-v-city-of-new-orleans-la-1936.