H & J Ditching & Excavating, Inc. v. Cornerstone Community Bank

CourtCourt of Appeals of Tennessee
DecidedFebruary 19, 2016
DocketE2015-01060-COA-R3-CV
StatusPublished

This text of H & J Ditching & Excavating, Inc. v. Cornerstone Community Bank (H & J Ditching & Excavating, Inc. v. Cornerstone Community Bank) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H & J Ditching & Excavating, Inc. v. Cornerstone Community Bank, (Tenn. Ct. App. 2016).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE October 27, 2015 Session

H & J DITCHING & EXCAVATING, INC. V. CORNERSTONE COMMUNITY BANK

Appeal from the Circuit Court for Knox County No. 2-560-13 Jon Kerry Blackwood, Judge1

No. E2015-01060-COA-R3-CV-FILED-FEBRUARY 19, 2016

Plaintiff H & J Ditching & Excavating, Inc. (Contractor) was hired by JRSF, LLC (Developer) to perform excavating and grading work on a subdivision construction project (the project) in West Knox County. Defendant Cornerstone Community Bank (Lender) provided financing for the project with a $2,512,500 construction loan. Complications arose, including the bankruptcy of one of Developer‟s primary members. Developer defaulted on the construction loan. Lender foreclosed and took possession by bidding on the property at the foreclosure sale. Contractor alleges that it completed the grading and infrastructure work but that it only received 90% of the contract price. Contractor brought this tort action against Lender, alleging intentional and negligent misrepresentation to-wit, by assuring Contractor that the construction loan to Developer was “fully funded” and that Contractor would be paid for its work. The trial court granted Lender summary judgment, finding that (1) Lender made no false or misleading statements and (2) the proximate cause of Contractor‟s alleged injury in not receiving its final 10% payment was Contractor‟s failure to request and obtain an engineer‟s certificate of final completion, a condition precedent to payment under its contract with Developer. We affirm.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court Affirmed; Case Remanded

CHARLES D. SUSANO, JR., J., delivered the opinion of the court, in which D. MICHAEL SWINEY, C.J., and JOHN W. MCCLARTY, J., joined.

Arthur F. Knight, III, and Jonathan Swann Taylor, Knoxville, Tennessee, for appellant, H & J Ditching & Excavating, Inc. 1 Sitting by designation. 1 P. Edward Pratt, Knoxville, Tennessee, for appellee, Cornerstone Community Bank.

OPINION

I.

On December 18, 2007, Contractor excuted agreements with Developer to perform excavation, grading, and other work for the project, a residential subdivision known as Terra Vista. In a one-sentence letter dated December 31, 2007, Lender notified Contractor that “[f]inancing is in place for [Developer] for the residential subdivision named „Terra Vista.‟ ” The contract between Developer and Contractor provided for periodic payments, prior to substantial completion of the project. Upon substantial completion, Contractor was to receive the balance due on its contract less a 10% retainage. Contractor commenced work on the project and received periodic payments for 90% of the total work completed and approved.

In November 2008, Derek Keck, Knox County Stormwater Department‟s primary inspector for the project, inspected the Terra Vista property and found it in violation of environmental regulations requiring stablization and erosion control of the newly excavated and graded soils. Keck stated in his affidavit:

on November 18, 2008, Knox County Stormwater issued a Notice of Violation to the owner of the Project . . . [I]t was noted that all grading of the Project was final but that no stabilization as is required by environmental regulations had been performed. It was my understanding that [Contractor] was the contractor on the Project responsible for stabilization of the exposed and graded portions of the Project.

* * *

On November 21, 2008, [Contractor] gave Notice of Termination - Storm Water Discharges Construction Activity to TDEC [Tennessee Department of Environment and Conservation] for the Project with the explanation: “Due to financial decline in the economy we are no longer working at the job site. . . .”

2 The Project was not substantially complete at this time. My understanding is that [Contractor] pulled off the Project because it was not being paid.

Following a change in ownership, on March 19, 2010, I prepared and my supervisor forwarded a Notice of Violation to [Lender] documenting that: “An inspection of your site on March 17 found your site to be deficient in this area. Approximately 75% of this property is not adequately stabilized. All raw areas should be stabilized. Prior to applying stabilization measures, any rills and ruts should be regraded.”

On or about March 17, 2010, I took numerous photographs documenting the lack of stabilization and incomplete condition of the Project. . . . [T]hey document the lack of stabilization on the Project through March 17, 2010, but this lack of stabilization on the Project existed at least from November 2008.

[Lender] undertook stabilization through a contractor other than [Contractor] which was not completed and signed off on by Knox County Stormwater, and the Knox County Law Director‟s Office, until November 1, 2010.

(Paragraph numbering in original omitted.)

According to the affidavits of Contractor‟s shareholders, Contractor “substantially completed the project on February 11, 2009.” They further stated as follows:

Essentially, [Contractor] cleared, excavated and graded the entire Terra Vista development. We cut all the roads of the subdivision into the land, built ponds, implemented the drainage plan designed by the engineers, and installed all utilities, including sewer, water and electric into the subdivision. It was a turn-key job, and we did everything but lay the asphalt.

* * * 3 Back in late November 2008, [Lender] suddenly and abruptly told us that the bank would no longer fund the project. We inquired about the retainage that [Lender] was holding and whether that would be disbursed to us. We were told it would not be so disbursed. Nevertheless, we substantially completed the project and upheld our version of the Contracts. [Lender] was well aware that we completed our work, and that they were withholding the retainage that was fully owed under the Contracts.

The contract between Developer and Contractor required the issuance of a certificate of substantial completion before final payment to Contractor would become due. No certificate was ever issued, and there is no proof in the record that Contractor ever requested the project engineer to issue one.

As previously noted, following Developer‟s default under its agreements with Lender, Lender foreclosed in early December 2009 and took possession of the property as high bidder at the foreclosure sale. Lender hired another contractor to complete the Terra Vista project, expending an additional $410,556.60 above the roughly $2.5 million construction loan proceeds.

Contractor brought this action alleging intentional and negligent misrepresentation by Lender. Contractor argues that Lender “made multiple false statements . . . that [Developer] was financially sound, that [Lender‟s] loan to [Developer] was „fully funded‟ and that [Contractor] would be paid for the work it completed on the Terra Vista project.” Lender moved for summary judgment and filed, among other things, the affidavit of Lynn Vandergriff, special assets officer for Lender, which states:

[Lender] foreclosed its deed of trust on the Project in December 2009. The Project was far from complete, so much so, that in March 2010, [Lender] received a Notice of Violation from Knox County Stormwater that 75% of the stabilization measures for the raw grading had never been implemented and that [Lender] would receive substantial daily fines if not immediately remedied.

4 [Lender] funded $2,511,927.76 of the Loan to [Developer], which was in the initial amount of $2,515,500.00.2 In addition, [Lender] made payments toward completion of the Project . . . of $410,556.60, for total payments related to the Project of $2,922,484.36.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robin Lee Stanfill v. John T. Mountain
301 S.W.3d 179 (Tennessee Supreme Court, 2009)
Tennie Martin, et.al. v. Southern Railway Company, et.al.
271 S.W.3d 76 (Tennessee Supreme Court, 2008)
Walker v. Sunrise Pontiac-GMC Truck, Inc.
249 S.W.3d 301 (Tennessee Supreme Court, 2008)
Cumulus Broadcasting, Inc. v. Shim
226 S.W.3d 366 (Tennessee Supreme Court, 2007)
White Ex Rel. Estate of White v. Lawrence
975 S.W.2d 525 (Tennessee Supreme Court, 1998)
Muhlheim v. Knox County Board of Education
2 S.W.3d 927 (Tennessee Supreme Court, 1999)
Harris v. St. Mary's Medical Center, Inc.
726 S.W.2d 902 (Tennessee Supreme Court, 1987)
Gardiner v. Word
731 S.W.2d 889 (Tennessee Supreme Court, 1987)
Merriman v. Smith
599 S.W.2d 548 (Court of Appeals of Tennessee, 1979)
Henderson v. Bush Bros. & Co.
868 S.W.2d 236 (Tennessee Supreme Court, 1993)
Branch v. Warren
527 S.W.2d 89 (Tennessee Supreme Court, 1975)
Luther v. Compton
5 S.W.3d 635 (Tennessee Supreme Court, 1999)
McCall v. Wilder
913 S.W.2d 150 (Tennessee Supreme Court, 1995)
Welch v. Thuan
882 S.W.2d 792 (Court of Appeals of Tennessee, 1994)
Michelle RYE Et Al. v. WOMEN’S CARE CENTER OF MEMPHIS, MPLLC Et Al.
477 S.W.3d 235 (Tennessee Supreme Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
H & J Ditching & Excavating, Inc. v. Cornerstone Community Bank, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-j-ditching-excavating-inc-v-cornerstone-community-bank-tennctapp-2016.