H & H Concrete, Inc. v. Civicon, Inc.

533 So. 2d 1294, 1988 La. App. LEXIS 2298, 1988 WL 118984
CourtLouisiana Court of Appeal
DecidedNovember 9, 1988
DocketNo. 87-875
StatusPublished
Cited by1 cases

This text of 533 So. 2d 1294 (H & H Concrete, Inc. v. Civicon, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H & H Concrete, Inc. v. Civicon, Inc., 533 So. 2d 1294, 1988 La. App. LEXIS 2298, 1988 WL 118984 (La. Ct. App. 1988).

Opinion

FORET, Judge.

H & H Concrete, Inc. (H & H) filed suit against Civicon, Inc. (Civicon) and Consola-ta Cemetery for recovery of money owed in connection with a contract to supply concrete and other material. Civicon filed a reconventional demand for damages, alleging that H & H had breached the contract in question. The trial court rendered judgment in favor of H & H and against Civicon in the sum of $15,707.61, together with interest and attorney fees1 and dismissed all claims asserted by Civicon in its recon-ventional demand. Civicon has appealed.

FACTS

Civicon was retained by a general contractor known as The Chelsea Group to do concrete work at the Consolata Cemetery located in the Lake Charles area. By agreement dated January 7, 1986, H & H agreed to supply to Civicon concrete and backfill grout to be used in connection with this project. Delivery of concrete pursuant to this agreement continued without incident until the early part of April of 1986, at which time Howard Delahoussaye, who was then an employee of H & H, advised John White, President of Civicon, that H & H would be closing its operations at the end of the month due to its inability to obtain sufficient liability insurance coverage on its trucks. The last delivery of concrete took place on April 17, 1986 and, on April 30, 1986, H & H shut down its operations entirely.

In May of 1986, Soil Testing Engineers, Inc., who was retained to conduct strength tests on all concrete used on the subject job, conducted 28-day strength compression tests on the concrete poured on April 8, 1986, and it was discovered that a total of 113 cubic yards of concrete poured on this date did not meet the required strength of 3500 psi (pounds per square inch) provided for in the job specifications, as well as in the agreement entered into between Civicon and H & H. Accordingly, [1296]*1296Doug McGee, the project engineer retained by Consolata, reduced the amount due the general contractor by 15% or $1,445.85, and the general contractor, in turn, imposed a similar reduction on Civicon. Considering this, Civicon, who at the time owed H & H a total of $17,153.46 for concrete delivered, offered to pay to H & H the full amount due, less the sum of $1,445.85, being the amount of the reduction imposed on Civi-con by the general contractor. H & H refused this offer of settlement, and this litigation ensued.

ISSUES

The following issues are presented for our consideration on appeal:

1. Should Civicon’s liability be limited to the discounted price of $40 per cubic yard provided for in the subject contract?
2. Should Civicon be liable for attorney’s fees provided for in the contract?
3. Did H & H breach the contract in question by failing to supply any additional concrete after the April 17, 1986 delivery?
4. Did the concrete in question contain redhibitory defects and, if so, is H & H the maker of the concrete sold, thus entitling Civicon to damages and attorney’s fees in accordance with C.C. art. 2545?
5. Did the trial court err in recognizing and maintaining the materialman’s lien filed by H & H?

1. SHOULD CIVICON’S LIABILITY BE LIMITED TO THE DISCOUNTED PRICE OF $40.00 PER CUBIC YARD PROVIDED FOR IN THE SUBJECT CONTRACT?

The contract in question provides that Civicon shall pay for concrete having a strength of 3500 psi at the rate of $43 per cubic yard, subject to a discount of $3 per cubic yard if payment is made “on or before the tenth day of the month following the month in which purchase is made.” (General terms and conditions of sale — Section 2) As noted in our recitation of the facts, Civicon offered to pay to H & H the full amount due, less the amount of the price reduction imposed by the general contractor. Civicon maintains that this offer was made while the discounted price was still available and thus Civicon should only be held liable for the discounted price of $40 per cubic yard. We disagree. It is well established that in order to be accorded the legal effect of payment, a tender must be absolute and unconditional. Riv-erland Oil Mill v. Underwriters for Lloyd’s, 368 So.2d 156 (La.App. 2 Cir.1979), writ denied, 369 So.2d 1365 (La.1979). Thus, an offer to pay a stated sum in full settlement is not considered an unconditional tender. O’Brian v. Allstate Ins. Co., 420 So.2d 1222 (La.App. 3 Cir.1982). See also, Walker v. Investment Properties, Ltd., 507 So.2d 850 (La.App. 5 Cir.1987), writ denied, 513 So.2d 293 (La.1987). In the instant case, John White of Civicon clearly did not make an unconditional tender. His letter of June 11, 1986, as well as the testimony of the witnesses at trial, reveals that White offered to pay the undisputed sum of $15,707.61 in full settlement of this dispute, whereas the total amount claimed by H & H was $17,153.46. As such, this offer is not considered an unconditional tender. Consequently, Civi-con is liable for the nondiscounted price of $43 per cubic yard for 3500 psi concrete as no payment or unconditional tender has been made on this account.

2. SHOULD CIVICON BE LIABLE FOR ATTORNEY’S FEES PROVIDED FOR IN THE CONTRACT?

Civicon maintains that it should not be held liable for attorney’s fees provided for in Section 5 of the contract (in the event the account is placed into the hands of an attorney for collection) in view of the fact that it did offer to pay the undisputed amount before it was necessary for H & H to retain counsel in this matter. However, we have already determined that the offer tendered by Civicon did not constitute an unconditional tender and therefore, this argument is without merit. Civicon also contends that it was not made aware of the fact that the contract in question provided for attorney’s fees and consequently, it should not be held liable for attorney’s fees [1297]*1297on this basis. Civicon cites Lambert Redi-Mioc v. Charles Carter & Co., 486 So.2d 932 (La.App. 1 Cir.1986), and Concrete Control Div. v. Cement Products Ser., 457 So.2d 769 (La.App. 1 Cir.1984), in support of its argument. These cases are clearly distinguishable from the instant case as they simply state the well established principle that a delivery receipt cannot support a claim for attorney’s fees absent a showing that its provisions (providing for attorney’s fees) were agreed to by the parties. In this case, the claim for attorney’s fees is founded upon a bilateral, written agreement signed by representatives of both H & H and Civicon. Section 5 of the contract clearly provides for attorney’s fees in the event that the account is placed in the hands of an attorney for collection. The fact that Civicon may not have been aware of provisions of the contract providing for attorney’s fees does not, in and of itself, render such provisions unenforceable. One who signs a contract is presumed to know its terms and cannot avoid its provisions, absent fraud or error, simply because he fails to read or understand it. Allen v. Royale 16, Inc., 449 So.2d 1365 (La.App. 4 Cir.1984). There is no showing of fraud or error; therefore, attorney’s fees are recoverable in accordance with the contract in question.

3. DID H & H BREACH THE CONTRACT IN QUESTION BY FAILING TO SUPPLY ANY ADDITIONAL CONCRETE AFTER THE APRIL 17, 1986 DELIVERY?

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
533 So. 2d 1294, 1988 La. App. LEXIS 2298, 1988 WL 118984, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-h-concrete-inc-v-civicon-inc-lactapp-1988.