H. G. Hastings Co. v. Southern Natural Gas Corp.

166 S.E. 56, 45 Ga. App. 774, 1932 Ga. App. LEXIS 701
CourtCourt of Appeals of Georgia
DecidedSeptember 26, 1932
Docket21775
StatusPublished
Cited by14 cases

This text of 166 S.E. 56 (H. G. Hastings Co. v. Southern Natural Gas Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H. G. Hastings Co. v. Southern Natural Gas Corp., 166 S.E. 56, 45 Ga. App. 774, 1932 Ga. App. LEXIS 701 (Ga. Ct. App. 1932).

Opinion

Sutton, J.

Southern Natural Gas Corporation instituted proceedings to condemn a right of way through lands of H. G. Hastings Company Inc. for a “pipe line or pipe lines” for the transportation and distribution of natural gas, the right of way to extend through the farm of the Hastings Company in Clayton county and to be 401 rods in length and 30 feet in width. The notice of the gas company’s intention to condemn stipulated that the condemnor “is to bury said pipes below plow depth on all of the lands on which [776]*776said pipes are laid.” The assessors made an award fixing the value of the land at $910 and assessing the consequential damages at $6,-590, making a total of $7,500 as the compensation to be paid to the owner by the gas company. From this award each of the. parties took an appeal to the superior court, and upon a trial in that court the jury returned a lump-sum verdict of $2,750. The gas company having paid and the owner having accepted the amount allowed by the award of the assessors, the court gave judgment in favor of the gas company for $4,750, this being the difference in the condemnor’s favor between the amount of the verdict and the sum advanced by the condemnor under the award. The case was brought to this court by the Hastings Company upon exceptions to the overruling of its motion for new trial.

The trial judge in outlining the case to the jury made the following statement: “From that award of the appraisers Southern Natural Gas Corporation has brought this appeal which is now on trial before you.” It is averred that the defendant, the condemnee, also appealed from the award and that the failure of the court to mention this fact had the effect of impressing the jury that the condemnor alone was dissatisfied with the award, all three of the appraisers having testified, “and the jury having deduced from their testimony their ideas on the issue.” There is no merit in this ground. The appeal of either party resulted in a de novo investigation, and it was the function and duty of the jury to pass upon the issues independently of the award made by the assessors, and they were expressly instructed to this effect in another portion of the court’s charge. It follows that the defendant could not have been prejudiced by the court’s failure to inform the jury that the defendant had also entered an appeal. See, in this connection, Central Georgia Power Co. v. Cornwell, 139 Ga. 1 (3) (76 S. E. 387, Ann. Cas. 1914A, 880); Atlanta, Birmingham & Atlantic R. Co. v. Smith, 132 Ga. 725 (64 S. E. 1073).

It is averred that the court erred “in charging the jury upon the question of consequential benefits,” there being no evidence, “as movant contends, which would support a finding of any consequential benefits” to offset the consequential damages. A ground of a motion for a new trial must be complete within itself, and this ground is defective as failing to show what the court did charge upon the subject. The assignment of error is directed only to an [777]*777alleged error in the charge of the court, and, the charge complained of .not having been stated either literally or in substance, this ground of the motion presents no question for decision by this court. Brock v. Brock, 140 Ga. 590 (4) (79 S. E. 473); Elliott v. Gary, 153 Ga. 665 (2, 9) (112 S. E. 900). Moreover, it would seem to be a question for the jury whether the bringing of this public utility into the locality of these lands would result in any consequential benefit to the property.

It is alleged that the court erred “in failing to charge the jury . . that the consequential benefits assessed shall in no case exceed the consequential damages assessed.” It appears that the right of way occupies less than five acres of'the land, and the highest value to be placed by any witness upon the land taken was $200 per acre, so that if the jury allowed the highest valuation for the land, this item could not have exceeded the sum of $1,000. The verdict, however, was in the sum of $2,750, and it thus appears that the jury actually allowed a substantial sum as consequential damages ; and this is true even if the verdict included a sum as the value of crops destroyed, the proven value of which was less than $1,750. It is therefore clear from the record that the defendant was not harmed by the court’s failure to instruct the jury that the consequential benefits shall in no case exceed the consequential damages.

Defendant assigns error upon the following charge to the jury: “If the defendant company, H. G. Hastings Co. Inc., desired to establish an irrigation system, it could lay its pipes under or over the plaintiff’s gas-pipe lines if such laying of pipes under or over the gas-pipe lines would not interfere with the transmission of gas. If you believe such to be the case, you could not consider any irrigation system as having any effect on the value of the land.” The only criticisms made of this charge were: (1) that it was a conclusion by the court and amounted to an expression of an opinion on the part of the court “that said gas line would not interfere with any proposed irrigation system,” and (2) that the excerpt was also a “specific instruction to the jury to disregard the irrigation project as an item of damages if the irrigation pipes could be laid over or under the gas-pipes, and was an erroneous direct instruction by the court that the gas line could in no other way interfere with an irrigation system, although there are numerous other ways in which said proposed easement would interfere with an irrigation system.”

[778]*778We do not think the chárge was subject to the exception that it contained an expression of opinion that the gas line would not interfere with any proposed irrigation system. On the other hand, it stated merely that the defendant could lay its irrigation pipes under or over the plaintiff’s gas-pipe lines if to do so would not interfere with the transmission of gas. As to the second exception, it is true that the juiy were instructed in effect that the gas line would not interfere with the establishment of the proposed irrigation system unless as an obstruction to the laying of supply water-pipes, but there was no evidence to authorize an inference of any other or further interference therewith. The nearest approach to an issue of this kind was made by a witness who testified that he had heard Mr. Hastings of the defendant company speak of “putting a pond there,” and that he, the witness, had been informed “of where these pipe lines broke,” and that, in his opinion, “jeopardizing that pond by having a pipe line under it would depreciate its value.” The witness evidently referred to some possible improper or negligent condition of the gas-pipes, from which he apprehended an explosion with resulting injury to the proposed pond or lake from which water would be supplied to the irrigation system.

In a case of this kind the consequential damages must be determined upon the theory that the public utility will be maintained and operated in a proper and lawful manner. It can not rightly be assumed “that there will be negligent construction or operation so as to cause damages in excess of that which would naturally and proximately arise from proper construction and operation. If the company be negligent in such matters, causing damages beyond those naturally arising from such construction and operation, this might give rise to a subsequent cause of action.” Central Georgia Power Co. v. Mays, 137 Ga. 120, 124 (72 S. E. 900).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Holding v. Indiana & Michigan Electric Co.
400 N.E.2d 1154 (Indiana Court of Appeals, 1980)
DeKalb County v. Queen
217 S.E.2d 624 (Court of Appeals of Georgia, 1975)
Hill v. Dixie Pipeline Co.
169 S.E.2d 656 (Court of Appeals of Georgia, 1969)
B. & W. Hen Farm, Inc. v. Georgia Power Co.
152 S.E.2d 841 (Supreme Court of Georgia, 1966)
Clemones v. Alabama Power Co.
130 S.E.2d 600 (Court of Appeals of Georgia, 1963)
Chandler v. Alabama Power Company
122 S.E.2d 317 (Court of Appeals of Georgia, 1961)
Tuggle v. DeKalb County
115 S.E.2d 751 (Court of Appeals of Georgia, 1960)
Georgia Power Co. v. Hendricks
103 S.E.2d 601 (Court of Appeals of Georgia, 1958)
Georgia Power Company v. Pittman
89 S.E.2d 577 (Court of Appeals of Georgia, 1955)
Gill v. State
69 S.E.2d 804 (Court of Appeals of Georgia, 1952)
Carolina Power & Light Co. v. Bowman
51 S.E.2d 191 (Supreme Court of North Carolina, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
166 S.E. 56, 45 Ga. App. 774, 1932 Ga. App. LEXIS 701, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-g-hastings-co-v-southern-natural-gas-corp-gactapp-1932.