H. D. Timmons & Co. v. Casey

47 S.W. 805, 19 Tex. Civ. App. 476, 1898 Tex. App. LEXIS 285
CourtCourt of Appeals of Texas
DecidedOctober 15, 1898
StatusPublished
Cited by2 cases

This text of 47 S.W. 805 (H. D. Timmons & Co. v. Casey) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H. D. Timmons & Co. v. Casey, 47 S.W. 805, 19 Tex. Civ. App. 476, 1898 Tex. App. LEXIS 285 (Tex. Ct. App. 1898).

Opinion

FINLEY, Chief Justice.

This is a suit by appellants against the appellee to establish and foreclose a lumber dealer’s lien on a certain lot and improvements belonging to appellee, described in appellants’ petition. The cause was tried at the fall term, 1897, in the District Court of Hill County, before the Hon. J. M. Hall, judge, without a jury, and the court rendered a judgment on the law and facts in favor of the appellee.

The plaintiffs, H. D. Timmons & Co., have appealed from the judgment rendered. The trial judge filed the following conclusions: “The *477 court finds as a fact that the defendant John S. Casey entered into a written contract with one John Bolinger, on the 24th day of September, A. D. 1895, to erect for him a dwelling house on lot No.-, in the city of Hillsboro, Texas; that the said John Bolinger was to furnish all material and perform all the work sufficient to complete and finish the said building, and that said Casey was to pay him therefor the sum of $3870. I further find that on November 19, 1895, said John Bolinger quit said work and abandoned his contract, and at that time said dwelling-house had fairly begun; I find that up to said November 19, 1895, that the said Casey had paid said Bolinger, under said contract for material furnished and work performed, $2740.20; and at the time he left, to wit, November 19, 1895, the said Casey was not due the said John Bolinger, the contractor, any sum under the contract, and I find that on November 17, 1895, the plaintiff herein served notice on said Casey, accompanied by bill of particulars of the amount of Bolinger’s indebtedness to plaintiff, and that said Casey did not, after receiving said notice of bill of particulars, pay to Bolinger any sum of money under the contract, and never did thereafter pay to said Bolinger any sum of money, and neither did said Bolinger earn any. I find that on November 23, 1895, after Bolinger had quit the work and threw up his contract, that B. H. Silven, an architect in the employ of the defendant, took charge of the work under the written contract and under the directions of the defendant and the sureties of the contractor’s building bond, all of which was in accordance with the contract, and completed the work according to the contract as entered into between said John Bolinger and John S. Casey, the defendant. I find that the said dwelling-house cost the defendant $6000, and I further find that after the completion of the said dwelling-house the said Casey was not due Bolinger anything under the contract. I further find that on the 24th day of October, 1895, the defendant herein entered into a contract with one John Bolinger to erect for him, Casey, and finish and deliver in a good, workmanlike manner, the brick work, carpenter work, tin and galvanized work, glazing, etc., and all work required in the erection of a one and one-half story barn and coalhouse, two water closets, cesspool, and all fences required to fence the entire lot No.-of the Craig addition to the city of Hillsboro; also to put down cement walks in accordance with the said contract. I further find that the said Casey was to pay him, Bolinger, for the above named work, completed and delivered, the sum of $1161.40; I find that on the 19th day of November, 1895, said Bolinger quit said work under this contract and abandoned the same, and that the erection of said barn had fairly begun, and that the other improvements mentioned in said contract had not been commenced. I find that it would take $1500 to complete the improvements mentioned in said contract of date October 24, 1895, and I find at the time said Bolinger quit work that the value of the work done and material furnished on said barn was $700, and it would have required $300 more to have completed the barn alone, and would have required $500 to have completed the other im *478 provements mentioned in said contract, dated October 24, 1895; I further find the value of the material furnished by Bolinger to build the barn, up to the time he quit the work, to be the sum of $400. I further find that after the said Bolinger threw up the contract and quit the work, the architect took charge of the same under the terms of this contract and completed the improvements named in said contract in accordance with the agreements and stipulations mentioned in said contracts. I find that the improvements mentioned in the said contracts completed in accordance with the terms of the said contracts, cost the defendant the sum of $8030.04 in excess of the amount named in the contracts, for which Bolinger was to erect, finish, and complete the said improvements; that after completing the improvements mentioned in both of said contracts the said Oasey was not indebted to Bolinger in any sum, but that said Casey had expended $2999.04 in excess of the sum named in the contracts, and that he, Casey, had instituted a suit on the builder’s bond for the sum of $1000, the amount of said bond, in Dallas County, Texas.

“Conclusions of Law.—I find as a conclusion of law, that as Casey was. due the contractor Bolinger nothing at the date Bolinger quit the work, and that at the date plaintiff served the defendant with notice of Bolinger’s indebtedness to them, attaching thereto a bill of particulars, that said Casey was not indebted to the said Bolinger, and did not thereafter pay to said Bolinger any sum of money under the contracts, and that Bolinger having contracted to furnish all material and all work necessary to complete the improvements mentioned in said contracts, that the said Casey would not be liable to the plaintiff for the material furnished, unless at the time Bolinger quit the work and at the time defendant was. served with notice of plaintiff’s claim against Bolinger, that he was indebted to Bolinger, and paid him money after the notice was so served upon him. The facts show that after said improvements were completed in accordance with the contracts, that the defendant was not due Bolinger any sum of money on the contracts; therefore the plaintiffs could not recover from the defendant Casey for an account made with the contractor Bolinger, unless after the said work was completed, in accordance with the contract, the defendant Casey was due the said Bolinger something under the contracts for the erection and completion of said improvements.

“I conclude as a matter of law that the plaintiff had taken proper steps to fix a lien against the lot and improvements, but that said lien never attached, because as a matter of fact the defendant was never at any time after the service of a notice of plaintiff’s claim against the contractor, or at the time notice of plaintiff’s claim was served, indebted tc said contractor in any sum, and never paid out in any manner any sum of money which was due the contractor.”

Opinion.—1. The first assignment of error is directed at the refusal of the court to require the attorney of appellee to deliver over to the attorneys of appellant a statement or memoranda of expenditures pre *479 pared by the architect, showing the money expended in completing the work after it was abandoned by the contractor. The contention is that this paper was used by appellee while being examined by his attorney to refresh his memory, and that opposing counsel had the right to cross-examine him npon this paper.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bova v. St. Louis Public Service Company
316 S.W.2d 140 (Missouri Court of Appeals, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
47 S.W. 805, 19 Tex. Civ. App. 476, 1898 Tex. App. LEXIS 285, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-d-timmons-co-v-casey-texapp-1898.