H. C. Lindsly & Son v. Kansas City Viaduct & Terminal Co.

133 S.W. 389, 152 Mo. App. 221, 1911 Mo. App. LEXIS 85
CourtMissouri Court of Appeals
DecidedJanuary 2, 1911
StatusPublished
Cited by4 cases

This text of 133 S.W. 389 (H. C. Lindsly & Son v. Kansas City Viaduct & Terminal Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H. C. Lindsly & Son v. Kansas City Viaduct & Terminal Co., 133 S.W. 389, 152 Mo. App. 221, 1911 Mo. App. LEXIS 85 (Mo. Ct. App. 1911).

Opinion

JOHNSON, J.

This is an action on contract to recover the reasonable value of work and labor performed by plaintiffs in the construction of the Inter[222]*222City Viaduct connecting the cities of Kansas City, Missouri, and Kansas City, Kansas. The answer is a general denial and a plea of no considerátion. A trial to a jury resulted in a verdict and judgment for plaintiff for $3011.05, the amount claimed in the petition, and the cause is here on the'appeal- of defendant.

In April, 1905, the defendant, the Kansas City Viaduct and Terminal Railway Company (hereinafter referred to as the Viaduct Company) entered into a contract with the Kansas Construction and Equipment Company (hereinafter called the Construction Company), by the terms of which the Construction Company, for a stated consideration, agreed to build the viaduct according to certain plans and ■ specifications and to deliver the completed structure to the Viaduct Company on or before July 1, 1907. The viaduct is an elevated structure of steel and concrete over eight thousand feet long, and its main features are a wide, paved roadway for vehicles and on the north side of that roadway, railway tracks for the accommodation of street car traffic.

On July 10, 1906, the Construction Company entered into a written contract with plaintiffs whereby plaintiffs, in consideration of certain payments of money, agreed to furnish all labor and perform all work “necessary to place, frame, and bolt in position all of the timber ties and guard rails and to lay, splice and full spike all of the steel rails for the two street railway tracks on the steel portion of the viaduct, all in accordance with the plans and specifications . . . and will fully finish and complete the same within five days form the date the last of the steel work is ready for the tracks, unless in the opinion of the engineer, the party of the second part (plaintiffs) be delayed or prevented by circumstances that are absolutely beyond its control.” The materials for the track laying and other work were to be [223]*223provided by tbe Construction Company and placed on tbe ground along and under tbe structure and the work of hoisting the material and putting it in place was to be done by plaintiffs. The specifications contained the stipulation: "The entire work herein outlined is to be completed within five days from the date the last of the steel work is ready for the tracks, and for each day of delay in so completing the work, the company' shall withhold permanently from the contractor’s total compensation the sum of fifteen and no one-hundredthsl dollars, unless in the opinion of the engineers the contractor be delayed by circumstances and conditions absolutely beyond his control. The amounts thus withheld shall not be considered as a penalty but as liquidated damages, fixed and agreed to in advance by the contracting parties.”

The contract contained, among others, the following provisions:

‘ ‘ In case the party of the first part, notwithstanding the failure of the party of the second part to complete its work within the time specified, shall permit the said second party to proceed, and continue, and complete the same, as if such time had not elapsed, such permission shall not be deemed a waiver in any respect, by the first party, of any forfeiture or liability for damages thereby incurred, arising from such non-completion of said work within the time specified, and covered by the "liquidated damages” clause of the specifications ; but such liability shall continue in full force against the said second party, as if such permission had not been granted.
"In the event of any delay in completing the work embraced in this contract, the party of the second part shall be entitled to no extra compensation on account of such delay; as it is hereby assumed that in submitting its tender it took its chances for the occurrence of such delay.”

[224]*224Plaintiffs began work immediately under this contract and prosecuted it as vigorously as the Construction Company would permit until November 1st, following, when the engineers of the Construction Company stopped plaintiffs’ work entirely and kept them idle during the ensuing two months. It is, 'and all along has been the contention of plaintiffs that they ¡were materially and unreasonably delayed by the Construction Company to such an extent that great loss was entailed in doing the first half of the work which was completed by November 1st, and that they would have suffered still greater loss from the wrongful conduct of the Construction Company had they gone ahead under the contract with the last half of the work in the dead of winter. It appears from the evidence of plaintiffs that the Construction Company used the framework for the railway tracks as a place for the beds used in mixing concrete for the wagon roadway and that the materials for plaintiffs’ work which had been assembled on the ground under the structure had been displaced and much of it had been sunk and frozen into the marshy ground. On January 3, 1907, one of the consulting engineers of the Construction Company requested the senior member of plaintiffs ’ firm to proceed with the work. Plaintiffs’ version of what was said and done pursuant to that request appears in the following quotations from the testimony of Mr. Lindsly :

‘ ‘ Q. Give that conversation, Mr. Lindsly. A. Mr. Hedrick came into the office to consult with me and take up the question of going ahead with the work.
“Q. What did he say to you about that? A. He said it was .time to go ahead with the work of decking again and wanted to know if I would, go ahead — probably not in just those terms, but that was the substance of it. And I told him very plainly that I would not think of going ahead, resuming that work under [225]*225the original contract — that wasn’t to be thought of for a moment. He smiled and said, £I don’t blame you.’
“Q. What followed after that in the further discussion of this matter with respect to your resuming work and laying rails and ties on this structure? A. Later on, I was requested to come up to-Mr. Harmon’s ■office in the Keith & Perry building, and Mr. Hedrick, I think, had his office there at the same time.
“Q. What time did you reach Mr. Harmon’s office in response to this request? A. On the third of January, 1907.
“Q. Mr. H. L. Harmon? A. Mr. H. L. Harmon.
“Q. He at that time was what? A. President of the viaduct company.
“Q. Whom did you meet there at that time at Mr. Harmon’s office? A. I met Mr. Hedrick first and Mr. Harmon and Mr. Howard, a resident engineer on the work, was also present.
“Q. What was said by you, why you would not resume work under the old contract? A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thompson v. Baltimore & OR Co.
59 F. Supp. 21 (E.D. Missouri, 1945)
Great Lakes Const. Co. v. Republic Creosoting Co.
139 F.2d 456 (Eighth Circuit, 1943)
Schaefer v. Brunswick Laundry, Inc.
183 A. 175 (Supreme Court of New Jersey, 1936)
Lebrecht v. New State Bank
205 S.W. 273 (Missouri Court of Appeals, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
133 S.W. 389, 152 Mo. App. 221, 1911 Mo. App. LEXIS 85, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-c-lindsly-son-v-kansas-city-viaduct-terminal-co-moctapp-1911.