H. B. "Buster" Hughes, Inc. v. Bernard

355 So. 2d 1027, 1978 La. App. LEXIS 3964
CourtLouisiana Court of Appeal
DecidedFebruary 14, 1978
DocketNo. 8748
StatusPublished
Cited by2 cases

This text of 355 So. 2d 1027 (H. B. "Buster" Hughes, Inc. v. Bernard) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H. B. "Buster" Hughes, Inc. v. Bernard, 355 So. 2d 1027, 1978 La. App. LEXIS 3964 (La. Ct. App. 1978).

Opinion

BEER, Judge.

This case was previously heard by us and remanded. See: H. B. “Buster” Hughes, Inc. v. Bernard, 306 So.2d 785 (La.App. 4th Cir. 1975), writ revoked with reasons, 318 So.2d 9 (Supreme Court of La., 1975).

The facts giving rise to this litigation are set forth in detail in our previous opinion. In summary, this litigation now involves only (1) the resolution of a claim by Hughes against Bernard, et al, for rental due for the sublease of the barge “ORLEANS,” and (2) the resolution of a claim against Bernard’s corporation (assigned to Hughes) for the cost of repair necessitated by erroneous excavation of a channel.

In fulfillment of a contract between Bernard’s corporation and Plaquemines Parish for removal of nine “camps” located too close to a hurricane levee right-of-way, Bernard’s acknowledged borrowed servant erroneously excavated a flotation channel from the campsites on Bay Adams, across approximately two-thirds to three-fourths of the marshland between the Bay and the relocation sites. The channel was unintentionally yet improperly cut across an area which was to form the base of a hurricane levee right-of-way. Excavation was eventually halted by the Corps of Engineers, upon their • discovery of what was taking place, but was later allowed to resume because “the damage had already been done” and completion of the channel would expedite the already delayed removal of the camps.

Subsequently, the Corps of Engineers required that the levee base be repaired by filling the channel that had been improvidently cut. Because of the urgency of this repair, appellee Hughes was persuaded by Chalin 0. Perez, President of the Plaque-mines Parish Commission Council, to contract for the needed repairs, pay $25,490.97 therefor, and accept an assignment of all claims the Parish had against Bernard’s corporation for same.

In its own right, appellee Hughes also asserts claim due from Bernard or his corporation for rental of the barge “ORLEANS” in the amount of $6,850.00.

In our previous opinion, we noted:

“ . . .As the record now stands, it does not reflect if the'9,685.11 cubic yards of shell furnished to plaintiff were used exclusively to fill the 322-foot segment of the excavation as required by the Corps of Engineers. Should part of this material have been used to backfill any portion of the flotation channel beyond the limits of the Corps of Engineers requirements, rather than backfill with the excavated soil, the defendant may well be entitled to an adjustment of plaintiff’s claim for its assignor’s failure to minimize the cost of repairs. Further it is relevant to establish at what point in the excavation the Parish officials ordered the canal continued to facilitate the camp-moving contract for this too can adversely affect the amount of plaintiff’s claim.”

We also determined that the repair claim could only be asserted against Bernard’s corporation, not Bernard personally, because the assigned claim arose from a contract with the corporation. In revoking writs, the Supreme Court affirmed this determination.

With regard to the barge rental claim, we determined that the hourly rental rate was $42.50 but were unsure of the number of hours worked by the barge. Thus, on remand, the following issues were to be addressed:

1. if Bernard had, as an individual rather than a corporate officer, contract[1029]*1029ed for the barge rental, and was therefore individually liable for the rental due;
2. if the barge had operated for time periods as reflected by Jordan’s (its owner) records, as reflected by plaintiff’s invoice to Bernard, or less, because of repairs, as alleged by Bernard;
3. whether all of the shells that were used to fill the channel were needed as a result of the original improper cutting of same; and
4. whether the cutting had caused the total damages claimed.

The trial court held that Bernard had failed to identify himself in his corporate capacity, was therefore personally liable for the barge rental and denied credit for repair time on the ground that the contract provided for a 10 hour per day minimum which entitled plaintiff to be paid for ten hours even if the barge was not working because of being in need of repair. The court also awarded approximately two-thirds of plaintiff’s claim against Bernard’s corporation for channel cut refilling, in the net amount of $16,992.28.

Bernard now contends the trial court erred in holding him personally responsible for the barge rental since the requirements of La.Civil Code art. 2277 were not met. He avers that no documentary proof or corroborating circumstances confirm the contention that he failed to identify himself in his corporate capacity, and also disputes the trial court’s denial of credit for repair time. Bernard’s corporation now contends that the record does not support the award against it in the amount of $16,992.28. Ap-pellee did not answer the appeal.

We find that the record supports a conclusion that all or almost all of the proposed levee base had been cut when the channel was improvidently dug (which is not contradictory to the essentially irrelevant evidence that two-thirds of the channel had been excavated). Bernard’s own testimony at the original trial indicates repeatedly that the Corps of Engineers allowed resumption of the channel excavation because the damage to the proposed levee base had already been done.

At the first trial on the merits, Bernard, himself, responding to an inquiry regarding the stoppage of the cutting of the channel by the Corps of Engineers, responded as follows: “They told him to go on because the damage had already been done.” (Emphasis ours.) This was reiterated by him when, in response to the question: “Do you know when the cut was finally finished?”, he responded: “Whenever they said go ahead and finish cutting because the damage had already been done. . . . ” Essentially the same acknowledgement is apparent throughout Bernard’s first trial testimony.

The same is true of Perez’ testimony, who, in responding to an inquiry regarding the removal of the barge, answered: “Because the damage had already (sic) done to the levee based area . '. .” and, further, “So, then, the last part then was just cut on the basis of the decision that this was just as good of a way of getting out of there as any other way and that most of the damage had been already done.”

On the question of whether the entire amount of shells was used in the affected area, no additional evidence was adduced on remand. At the first trial, Bobby Dagley, Hughes’ representative, testified that the Corps of Engineers supervised the job so that the filling of the cut would comply with their specifications. On the basis of this evidence, we are of the view that plaintiff made a prima facie showing of the use of the shells for the required repair. Bernard did not go forward with any evidence to the contrary.

We conclude that at least two-thirds of the levee base was excavated (more likely, all of it), and, accordingly, the judgment against the Sherman A. Bernard House Moving and Shoring Corporation in the amount of $16,992.28 is supported by the record and should be affirmed.

Dagley testified that he did not remember Bernard saying anything about a corporation when he called to lease the barge. [1030]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. C.P., K.P.P. & K.M.P.
768 So. 2d 134 (Louisiana Court of Appeal, 2000)
Freeman v. Wal-Mart Stores, Inc.
775 F. Supp. 208 (W.D. Louisiana, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
355 So. 2d 1027, 1978 La. App. LEXIS 3964, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-b-buster-hughes-inc-v-bernard-lactapp-1978.