This text of 299 F.2d 655 (Gustavsson Contracting Co. v. Floete) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gustavsson Contracting Co. v. Floete, 299 F.2d 655, 1962 U.S. App. LEXIS 5995 (2d Cir. 1962).

Opinion

299 F.2d 655

OVE GUSTAVSSON CONTRACTING CO., Inc., Plaintiff-Appellant,
v.
Franklin G. FLOETE, as Administrator of General Services Administration, Michael Brennan, individually and as Contracting Officer of General Services Administration, and William A. Boyd, Defendants-Appellees.

No. 70.

Docket 26814.

United States Court of Appeals Second Circuit.

Argued November 9, 1961.

Decided February 5, 1962.

Anthony B. Cataldo, New York City, for plaintiff-appellant.

Ann B. Miele, Asst. U. S. Atty., Brooklyn, N. Y. (Joseph P. Hoey, U. S. Atty., Eastern Dist. of New York, Brooklyn, N. Y., on the brief), for defendants-appellees.

Before LUMBARD, Chief Judge, and MEDINA and WATERMAN, Circuit Judges.

MEDINA, Circuit Judge.

Plaintiff, Ove Gustavsson Co. Inc., a New York corporation, appeals from an order and summary judgment in an action against certain officials of the federal Government, in their individual capacity, for damages caused by the alleged wilful and malicious acts of these officials in filing allegedly false reports concerning Gustavsson's performance of a Government construction contract, as a result of which reports the contract was cancelled. While the complaint was dismissed in its entirety, the appeal brings up for review only the summary judgment for defendants on the second claim for relief set forth in the complaint. Gustavsson also appeals from the order, made simultaneously with the granting of the summary judgment, denying Gustavsson's motion to sever the action and remand the second claim for relief to the New York Supreme Court, Queens County, where the action was commenced and from which it was removed to the United States District Court for the Eastern District of New York, pursuant to the provisions of 28 U.S.C. § 1442(a) (1). The opinion of Judge Zavatt is reported at 187 F.Supp. 839. We affirm.

The United States needed a dehumidification hutment at Burlington, New Jersey, for the protection and storage of precision machinery, and on May 28, 1958 Gustavsson entered into a contract with the Government for the construction of the required hutment. A hutment is an enclosed area in a warehouse built by joining panels of sheet metal together, and the one contracted for was to be equipped with dehumidification units. The contracting agency for the Government was the General Services Administration; defendant Brennan was the Contracting Officer and defendant Boyd was his Assistant. Floete, a defendant in the first claim for relief only, was Administrator of the General Services Administration. The original completion date was October 2, 1958, ninety days after Gustavsson received notice to proceed. Although some equipment had arrived at the job site by October 2, the work was far from completion and the contracting office of the General Services Administration had granted Gustavsson an extension. While the cause of further delay is a matter of dispute between the parties, it is clear that even as late as January 12, 1959, Gustavsson had failed to complete the construction work called for by the terms of the contract.

The contract contained the general provisions of a standard Government construction contract, and it included the following clauses:

"If the Contractor refuses or fails to prosecute the work, or any separable part thereof, with such diligence as will insure its completion within the time specified in this contract, or any extension thereof, or fails to complete said work within such time, the Government may, by written notice to the Contractor, terminate his right to proceed with the work or such part of the work as to which there has been delay.

* * * * *

"If the Contractor fails to proceed at once with the replacement of rejected material and/or the correction of defective workmanship the Government may terminate the right of the Contractor to proceed * * *."

Boyd, after investigating the facts and communicating with the contractor, recommended to his superior, Brennan, that the contract be terminated because of plaintiff's unsatisfactory performance. Brennan agreed, and a report was sent to the Washington office of the General Services Administration. The Washington office approved the report, authorized the termination, and on January 12, 1959 Gustavsson was notified that the contract had been terminated.

On February 6, 1959 Gustavsson appealed the termination to the Administrator of the General Services Administration in accordance with the "disputes" clause of the contract, and this appeal is still pending. Gustavsson also commenced an action in the United States District Court for the Southern District of New York against Franklin G. Floete, Administrator of General Services Administration, Michael Brennan, Contracting Officer, and William A. Boyd, Assistant Contracting Officer, in their official capacities. The relief prayed for in this first action was for an injunction, restraining defendants from awarding the contract to another contractor to complete the work on the as yet useless hutment, to review the decision terminating Gustavsson's contract, and for damages. This action was dismissed for lack of jurisdiction. Ove Gustavsson Contracting Co. Inc. v. Floete, S.D.N.Y., 1959, 176 F.Supp. 544, aff'd, 2 Cir., 1960, 278 F.2d 912, cert. denied, 364 U.S. 894, 81 S.Ct. 225, 5 L.Ed.2d 188.

On June 26, 1959, while its appeal in the first action was still pending, Gustavsson commenced a second action, the subject of this appeal, in the New York State Supreme Court, Queens County. This second action was removed to the United States District Court for the Eastern District of New York, pursuant to 28 U.S.C. § 1442(a) (1), and Gustavsson's motion to remand was denied, 176 F.Supp. 841. The complaint alleged two claims for relief. The first, against the defendants Floete and Brennan "in their representative capacities," was dismissed because the same plaintiff was seeking the same relief against the same defendants in the then still pending Southern District action. As Gustavsson no longer contests the propriety of the dismissal of the first claim for relief in the second action, it need concern us no longer.

The gist of the second claim for relief in the second action, asserted against defendants Brennan and Boyd "individually," is that said defendants, with intent to harm and injure the plaintiff, knowingly, intentionally, wilfully, and maliciously made untruthful reports concerning the performance of the contract by Gustavsson, and by reason of such untruthful reports caused the contract to be cancelled. Defendants' motion to dismiss the complaint pursuant to Federal Rule Civ.Proc. rule 12(b), 28 U.S.C. was granted also as to this second claim for relief in the second action, the District Judge very properly treating the motion as one for summary judgment, as voluminous affidavits were submitted and considered in support of and in opposition to the motion. At the same time the District Court denied Gustavsson's cross-motion to sever the claims and to remand the second claim for relief, which the court treated as a motion for reconsideration of its prior order denying the original motion to remand the case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Little v. Barreme
6 U.S. 170 (Supreme Court, 1804)
United States v. Lee
106 U.S. 196 (Supreme Court, 1882)
Belknap v. Schild
161 U.S. 10 (Supreme Court, 1896)
Spalding v. Vilas
161 U.S. 483 (Supreme Court, 1896)
Tindal v. Wesley
167 U.S. 204 (Supreme Court, 1897)
Scranton v. Wheeler
179 U.S. 141 (Supreme Court, 1900)
Philadelphia Co. v. Stimson
223 U.S. 605 (Supreme Court, 1912)
Yearsley v. W. A. Ross Construction Co.
309 U.S. 18 (Supreme Court, 1940)
Dalehite v. United States
346 U.S. 15 (Supreme Court, 1953)
Hatahley v. United States
351 U.S. 173 (Supreme Court, 1956)
Howard v. Lyons
360 U.S. 593 (Supreme Court, 1959)
Gregoire v. Biddle
177 F.2d 579 (Second Circuit, 1949)
Banco De Espana v. Federal Reserve Bank of New York
114 F.2d 438 (Second Circuit, 1940)
Barr v. Matteo
360 U.S. 564 (Supreme Court, 1959)
Ove Gustavsson Contracting Co. v. Floete
299 F.2d 655 (Second Circuit, 1962)
Ove Gustavsson Contracting Co. v. Floete
176 F. Supp. 544 (S.D. New York, 1959)
Ove Gustavsson Contracting Co. v. Floete
176 F. Supp. 841 (E.D. New York, 1959)
Ove Gustavsson Contracting Co. v. Floete
187 F. Supp. 839 (E.D. New York, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
299 F.2d 655, 1962 U.S. App. LEXIS 5995, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gustavsson-contracting-co-v-floete-ca2-1962.