Gurney Industries, Inc. v. St. Paul Fire & Marine Insurance

334 F. Supp. 845, 1971 U.S. Dist. LEXIS 10831
CourtDistrict Court, W.D. North Carolina
DecidedNovember 11, 1971
DocketCiv. A. No. 2614
StatusPublished
Cited by3 cases

This text of 334 F. Supp. 845 (Gurney Industries, Inc. v. St. Paul Fire & Marine Insurance) is published on Counsel Stack Legal Research, covering District Court, W.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gurney Industries, Inc. v. St. Paul Fire & Marine Insurance, 334 F. Supp. 845, 1971 U.S. Dist. LEXIS 10831 (W.D.N.C. 1971).

Opinion

Memorandum of Decision and Order

McMILLAN, District Judge.

THE NATURE OF THE CASE

Gurney Industries, plaintiff, sued St. Paul, the defendant, for alleged damages and for alleged equitable relief due to alleged non-performance of a contract by the two Roberts companies, the principals on St. Paul’s performance bond. The case was tried without a jury in three installments for a total of twenty-one days. Testimony at the trial, not counting depositions and exhibits, amounts to twenty-five hundred pages. Essential findings of fact and conclusions of law follow.

FINDINGS OF FACT, CONCLUSIONS OF LAW AND JUDGMENT

FINDINGS OF FACT

1. Gurney Industries, Inc., a Gastonia, North Carolina textile corporation, owned several textile mills including a knitting mill in Prattville, Alabama. Gurney contracted with Roberts Company and Roberts Engineers, Inc., of Sanford, North Carolina, to build a new yarn spinning mill for Gurney in Pratt-ville, Alabama, for a contract price of $3,500,000.00. The new spinning plant was intended to supply yarn for Gurney’s existing knitting mill in Prattville. The local government (Autauga County, Alabama) provided the financing for the land acquisition and Commercial Credit Industrial Corp. provided the financing for the machinery. The details of those arrangements are not material to the decision of the fundamental issues in the case. St. Paul Fire and Marine Insurance Company issued a performance bond in the principal amount of $3,400,000.00 guaranteeing Robert’s performance of the contract.

2. The contract between Roberts and Gurney was executed as of September 23, 1968. It employed Roberts to design, construct and fully equip a spinning mill for three and one-half million dollars m Prattville, Alabama. It appointed Roberts Engineers to see that the work was done according to plans and specifications and that the plant was built so as to be generally similar to a yarn mill recently built by Roberts at Clarkton, North Carolina. It called for the installation of specifically listed machinery and equipment.

3. Paragraph 6 of the contract states in part that

“Gurney has authorized Roberts Engineers to proceed with the necessary engineering work, the placement of orders for machinery and equipment, and otherwise to proceed with the completion of Roberts Engineers’ obligation under this contract as soon as is reasonably possible and consistent with proper construction, design and engineering standards.”

4. Paragraph 7 of the contract dealt with payments by Gurney — with the time and manner and amount of payments by Gurney to Roberts. Paragraph 7 read as follows:

“7. Each month during the course of this Project, Roberts Engineers will submit to Gurney invoices representing eighty-five per cent (85%) of the value of work performed on the construction, and on the project machinery listed in Schedule III, plus materials and project machinery delivered to the job site or suitably stored, [847]*847less the aggregate of prior progress payments, which invoices Gurney shall arrange to have paid net within ten (10) days after invoice date, and Roberts will submit to Commercial Credit invoices representing eighty-five per cent (85%) of the agreed price of project machinery listed in Schedule IV delivered to the job site and/or suitably stored in a manner acceptable to Gurney, less the aggregate of prior progress payments.
“The remaining ten per cent (10%) of the Contract Price shall be paid, upon acceptance of the Project, by Gurney as to Schedule III, and by Commercial Credit as to Schedule IV, after certification by Roberts Engineers that the Project has been completed. ‘Completion of the Project’ shall mean: (a) That the building has been constructed in accordance with the Building Contract Documents, and such construction and engineering has been approved, (b) That all equipment, machinery and fixtures have been installed and are in operating condition, (e) That the machinery and equipment is capable of producing 100,000 pounds of 26’s single yarn of sixty per cent (60%) combed cotton and forty per cent (40%) carded cotton material each week through said Mill; and (d) That the product at each stage of the manufacturing process of the yarn meets the “A” Quality Standards established by N. C. State University, at Raleigh, North Carolina, which said standards are attached hereto as Schedule V. In the event the Parties hereto fail to agree as to the fulfillment of such product standards, samples of each product at each stage of the manufacturing process shall be submitted to N. C. State University Testing Division for final determination of the issue.” (Emphasis added.)

5. Paragraph 9 of the agreement read as follows:

“9. It is understood that Roberts Engineers will be required to test the operation of the Mill in the manufacture of yarn and, to this end, Gurney agrees to furnish the labor necessary for this operation and to provide the material for the manufacturing process. The labor is to be paid by Gurney, and Gurney is to pay for the cotton and the power.” (Emphasis added.)

6. Paragraph 11 of the contract read as follows:

“11. Roberts Engineers projects the following time schedule for the various stages of the project, starting from date of execution of this Agreement and written notification from Autauga County that the sale of its proposed Bonds has been consummated and the plant site made available for commencement of construction.

Activity Increment Time Lapse Total Time Lapse

1. Completion of Site Preparations and Foundations 2 weeks 2 weeks

2. Steel and Roof Structure 4 weeks 6 weeks
3. Walls 10 weeks 16 weeks —
4. Floor 8 weeks from week 6 16 weeks

5. Utilities & Exterior Finish 12 weeks from week 6 20 weeks

6. Machine Erection 16 weeks from week 16 32 weeks
7. First Yarn Production 22 Csic] weeks
8. Building and Installation Completed 34 weeks
9. Full Plant Start-up 42 weeks" (Emphasis added.)

7. However, no time of completion was guaranteed, and no penalty was provided in the contract for failure to complete the work by a particular day.

8. Actual construction of the mill had begun several months before the formal execution of the contract. Actual manufacture of some of the machinery had also begun at earlier times,

[848]*8489. The building was completed and the machinery was installed and capable of operating and there was, in fact, a “full plant start-up” by May of 1969, within forty-two weeks from the original contract date. During the summer of 1969, the mill exceeded ninety thousand pounds a week in quantity of output of spinning yarn. However, it never at any time reached one hundred thousand pounds of yarn per week and it never produced any substantial amount of yarn which met the “A” quality standards of North Carolina State University at Raleigh, which were referred to in the contract provisions of paragraph 7 relating to payments.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
334 F. Supp. 845, 1971 U.S. Dist. LEXIS 10831, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gurney-industries-inc-v-st-paul-fire-marine-insurance-ncwd-1971.