Gurnet

235 F. 595, 1916 U.S. Dist. LEXIS 1393
CourtDistrict Court, D. Maine
DecidedJuly 31, 1916
DocketNo. 324
StatusPublished
Cited by2 cases

This text of 235 F. 595 (Gurnet) is published on Counsel Stack Legal Research, covering District Court, D. Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gurnet, 235 F. 595, 1916 U.S. Dist. LEXIS 1393 (D. Me. 1916).

Opinion

HALE, District Judge.

On September 18, 1914, the steamer Gurnet was seized upon this libel to enforce a maritime lien. On November 12, 1914, she was sold at a marshal’s sale by virtue of an interlocutory order of sale, and the proceeds of the sale were paid into the registry of this court. On the day of filing the libel, Joseph C. Noyes intervened, by petition, to enforce a lien for labor and materials furnished for installing the boiler and machinery of the steamer. It is alleged that this lien is a construction lien, and arises under section 8 of chapter 93 of the Revised Statutes of Maine, as follows:

“Sec. 8. Whoever furnishes labor or materials for building a vessel, has a lien on it therefor, which may be enforced by attachment thereof, within four days after it is launched; but if the labor and materials have been so furnished by virtue of a contract not fully completed at the time of the launching of the vessel, the lien may.be enforced within four days after such contract has been completed. * * * ”

The proofs show that the labor and materials were furnished by the intervener, Noyes, for the installation of a pinch wheel, an appliance for turning the engine over, and a spring bearing.

[597]*597It is contended on behalf of the trustee in bankruptcy that Noyes was to install the engine, not as a contract job, but that he was to be paid a fair value for the material furnished, and for the labor by the day; that the steamer entered into the service for which she was built on July 9, 1914; that the constructive work was completed at that time, and that Noyes did not enforce his claim to a lien within four days afterwards, and that, therefore, he has lost his lien; that the appliances furnished were not necessary for the working of the engine, or for the operation of the boat but that the steamer could, and did, operate without them; that inasmuch as the contract was not completed before the vessel went into service, no enforceable lien ever attached to the steamer; that, even though Noyes may have had an uncompleted contract during the summer of 1914, during that period he had only an inchoate right to a lien under certain conditions; that such right could not be enforced, under the terms of the statute, until he had completed his contract and established his lien; that, in any event, it could not be enforced at any other time than “within four days after such contract has been completed,” as provided by the statute; that, under the statute, when labor and materials are furnished, in accordance with the terms of the contract, nothing but the completion of the contract can create a valid lien, and that, up to the time of the completion of the contract, there exists only an inchoate right to a lien; that such right is given, not by a federal statute, but by a state law; and that neither the federal court nor any other court car. enforce a right that does not comply with the terms of the state statute.

[1] 1. It becomes necessary to examine the proofs to see what the contract was between the parties. The steamer Gurnet was owned by the Portland-Bath-Casco Bay Rapid Transit Company, a corporation organized in November, 1913, to carry on a passenger and freight business. Captain Oscar Randall was a director and the president; George W. Brown was the general manager and treasurer. Captain Oscar Randall had followed the sea for more than 30 years as master of sailing vessels and motorboats. He is well known to me as being experienced in maritime matters. Mr. Brown, at the time he went into this business, had no experience in maritime affairs. Captain Randall testifies that while Brown was the general manager, he himself made the contract for the building of the Gurnet, after consulting Brown; that his understanding was that Brown was to consult with him, as a director, in making the contracts and giving directions as to what should he done, and that he himself should have the superintendence of the boats. Captain Randall says that both he and Brown entered into a contract with Mr. Noyes. Bfown himself testifies that it was understood that Noyes was to furnish everything necessary, with the exception of the feed water heater, boiler, condenser, and pump, and some incidentals, and that Noyes was given orders to furnish everything else necessary to install and fix up the boat. He adds:

“I considered that we had entered into an agreement with him [Noyes], and that he was to complete the work unless there was some unusual proceeding ; hut I had every confidence in Mr. Noyes doing the work right.”

[598]*598It appears that one Ray Marshall was appointed to superintend the work of installing the machinery for the Gurnet. The proofs lead me to believe that, during the process of installation, it was discovered that the engine, a secondhand one, did not have a pinch wheel upon it, or any other appliance for turning it over; that the shaft was also a secondhand one, with heavy couplings; that no spring bearing was connected with it; that on or about June 19, 1914, Marshall, then acting as superintendent of installation in behalf of the vessel, ordered Noyes to prepare a pinch wheel and spring bearing which were necessary for the operation of the steamer and that he determined where the pinch wheel should be located; that, under Marshall’s directions, Noyes made measurements for the purpose of determining the size of the pinch wheel, and that the shaft was prepared, before it was put into the steamer, for the reception of the spring bearing; that Noyes received orders from the superintendent of construction to make tírese two parts, with the agreement that they should be installed as soon as the steamer could be hauled up long enough to perform the work to be done; that at the time of the installation of the steamer’s machinery Noyes was compelled to put off the work of preparing the parts and construction of the pinch wheel and spring bearing, and, it being necessary that there should be some means of turning over the engine, it was agreed that, while these appliances were being prepared, Noyes was to loan Marshall, for the temporary use of the steamer, a large Stillson wrench; that the installation of the pinch wheel and spring bearing was not completed when the vessel was put into service, July 9, 1914, but it was understood that Noyes should do the work on tire pinch wheel and spring bearing when it was convenient for him; that the pinch wheel was duly installed and the spring bearing delivered on board the steamer, under the contract, on September 15, 1914, within four days before these proceedings were commenced.

Without further reciting testimony, after a full examination of the proofs, I am satisfied that the contract was one relating to the construction of the vessel; that within the meaning of the state statute, the labor and materials were furnished for “building a vessel” ; that the pinch wheel and spring bearing were necessary parts .of the steamer, and were furnished upon the order of the owner of the steamer, by its superintendent of construction, under one continuing contract; and the fact that some time intervened between the time the steamer was put in operation and the time when the pinch wheel and spring bearing were furnished does not affect the validity or priority of the lien.

The jurisdiction of the court over the lien is fixed by the fact that the steamer was seized and sold under admiralty proceedings; the court thereby acquiring jurisdiction over the remnants of the sale in the registry.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Kochaline
25 F.2d 503 (E.D. South Carolina, 1928)
The Yankton
7 F.2d 384 (D. Massachusetts, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
235 F. 595, 1916 U.S. Dist. LEXIS 1393, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gurnet-med-1916.