Gundersen & Son, Inc. v. Cohn

596 F. Supp. 379, 1984 U.S. Dist. LEXIS 22426
CourtDistrict Court, D. Massachusetts
DecidedOctober 26, 1984
DocketCiv. A. 71-0832-C
StatusPublished
Cited by1 cases

This text of 596 F. Supp. 379 (Gundersen & Son, Inc. v. Cohn) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gundersen & Son, Inc. v. Cohn, 596 F. Supp. 379, 1984 U.S. Dist. LEXIS 22426 (D. Mass. 1984).

Opinion

OPINION

CAFFREY, Chief Judge.

This is a civil action in which plaintiff, Gundersen & Son, Inc., a Massachusetts corporation, seeks to recover sums allegedly owed to it by defendants Albert and Sylvia Cohn, residents of New Jersey, for the construction of a summer home on the island of Martha’s Vineyard. Defendants counterclaim for water damage to the house allegedly caused by plaintiff’s faulty workmanship, and for the value of certain items of defendants’ personal property which plaintiff allegedly removed from the construction site.

Plaintiff initially brought suit in state court, and defendants removed the case to federal court on the basis of diversity of citizenship. 28 U.S.C. §§ 1332, 1441. The ease was then heard before a master, pursuant to Fed.R.Civ.P. 53. Both parties object to findings contained in the master’s report, and the case is now before this Court on cross motions for judgment.

The central issue in this case is whether the parties agreed that plaintiff would build defendants’ house for a predetermined maximum price, or whether they agreed that defendants would pay plaintiff’s construction expenses plus a fixed profit margin, regardless of the total cost of the project. The master made numerous findings of fact concerning the communications between the parties. Presented below is a summary of his findings, which are firmly supported by the evidence, along with certain additional facts which are also established by the Record.

In August, 1969, the parties met several times to discuss plaintiff’s building a house for defendants on Martha’s Vineyard. Master's Report, If 13. Defendants showed plaintiff’s representatives, Roy Gundersen and Earle Ray, their preliminary plans and specifications. Defendants also informed Mr. Gunderson and Mr. Ray that they wanted to pay no more than $90,000 for the house. Testimony of Roy Gundersen, Record at 1-71 (May 23, 1975). In order to bring the cost of the project under $90,000, *381 plaintiff’s agents insisted that certain changes be made in the plans and specifications. Master’s Report, II26. Defendants agreed to these changes, which included eliminating the garage, reducing the size of the deck, and using less expensive materials in many areas of the house. Master’s Report, ¶ 27.

As a result of these discussions, plaintiff’s agents prepared a letter of intent, to be signed by Mr. Cohn, authorizing plaintiff to proceed with construction. Master’s Report, 1116. This letter of intent, dated August 15, 1969, stated in part:

It is our intention to enter into a formal contract with you within a period of 10 days based on The American Institute of Architects Agreement (AIA Document A 111), and the General Conditions of the Contract for the cost of the work plus a fee of 15% for overhead and profit. If for any reason whatsoever it is not possible to conclude the formal contract, we agree to pay you the net cost of (materials, labor, rental and cost of moving equipment). To the above costs will be added 15% for overhead and profit____ Upon execution of the formal contract this Letter of Intent shall be superseded by it.

Master’s Report, 1122.

Before signing this letter, Mr. Cohn added the following handwritten amendment: “Upset price is $90,000. Completion by June 1, 1970.” Master’s Report, 1124. “Upset price,” a term commonly used in the building trade, means a guaranteed maximum price given by a builder to an owner. Master’s Report, 1125.

Prior to August 27, 1969, defendants’ architect, Norman Hoberman, filled out and sent to plaintiff a form contract drafted by the American Institute of Architects. Master’s Report, U 28. However, neither this contract, nor any other formal agreement was ever executed by the parties. Master’s Report, 1131 and 1139.

By letter of August 27, 1969, Mr. Gundersen informed Mr. Cohn that he wished to amend several provisions of the proposed form contract. This letter concluded:

Also, Addendum No. 1, dated 8/20/69, does not include all the changes that we discussed in setting the upset price at $90,000 and as yet we have not received the amended drawings dated 8/20/69, numbered Al-All, as specified in this article.
We agree to this contract with the understanding that this letter becomes part of the contract documents and that if after we receive the amended drawings we find it necessary to increase the upset figure, any costs exceeding $90,000.00 would not be subject to the 15% for profit and overhead, but would represent only the cost of the work.

Master’s Report, ¶ 30.

Plaintiff began construction of the Cohns’ house in September of 1969. Master’s Report, ¶ 35. The completed plans for the house, including the cost-cutting changes which plaintiff had suggested, were in plaintiffs possession by the middle of that month. Master’s Report ¶ 34. After receiving these amended plans, plaintiff never found it necessary to increase the original upset figure of $90,000. Master’s Report, 1141; Testimony of Roy Gundersen, Record at 1-83, 84 (May 23, 1975).

On October 30, 1969, plaintiff’s agent, Earle Ray, wrote Mr. Cohn a letter stating, in part:

As per our conversation of 10/30/69, it is my understanding that we shall continue construction under the letter of intent originally agreed upon.
However, upon completion of the exteri- or ... we shall meet and discuss in detail the interior finish schedule and at that time enter into a formal contract agreement with an upset price for completion.

Master’s Report, ¶ 38.

From October 11, 1969 to September 21, 1970, plaintiff sent defendants fifteen invoices, totalling $116,124.73. Master’s Report, ¶ 42 and H 44. Plaintiff admits, however, that defendants were inadvertantly overchanged $3,500.00. Master’s Report, *382 II49. Therefore, total billing for the job should have been $112,624.75.

From October 11, 1969 through May 11, 1970, each of plaintiffs invoices included a 15% fee for overhead and profit. On the invoice of May 11, 1970, however, there appeared for the first time a calculation of the total cost of the project to date. This invoice indicated that defendants had been billed a total of $90,117.62. All subsequent invoices charged for labor and materials only and did not include a 15% fee. Master’s Report, 1142 and U 43.

The Cohns paid plaintiff a total of $91,-123.97 for the construction of the house. Defendants submitted their last payment to plaintiff on June 29, 1970. Master’s Report, ¶ 3. Thereafter, defendants refused to make any further remittances. *

Defendants moved into their new summer home in the late spring of 1970. Soon after taking up residence, they observed water leaking into the structure and staining the interior. The walls became damp and musty, some floors became warped and blackened, and the staining worsened with every storm. Master’s Report, 1156-58. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
596 F. Supp. 379, 1984 U.S. Dist. LEXIS 22426, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gundersen-son-inc-v-cohn-mad-1984.