Gulf Coast Electric Cooperative, Inc. v. Clark

674 So. 2d 120, 169 P.U.R.4th 662, 21 Fla. L. Weekly Supp. 221, 1996 Fla. LEXIS 900, 1996 WL 271187
CourtSupreme Court of Florida
DecidedMay 23, 1996
DocketNo. 85464
StatusPublished
Cited by5 cases

This text of 674 So. 2d 120 (Gulf Coast Electric Cooperative, Inc. v. Clark) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gulf Coast Electric Cooperative, Inc. v. Clark, 674 So. 2d 120, 169 P.U.R.4th 662, 21 Fla. L. Weekly Supp. 221, 1996 Fla. LEXIS 900, 1996 WL 271187 (Fla. 1996).

Opinion

OVERTON, Justice.

We have on appeal a decision by the Florida Public Service Commission (the Commission) resolving a territorial dispute between Gulf Coast Electric Cooperative, Inc. (Gulf Coast) and Gulf Power Company (Gulf Power). We have jurisdiction. Art. V, § 3(b)(2), Fla. Const. For the reasons expressed, we reverse the Commission’s order awarding service to Gulf Power and remand for entry of an order awarding service to Gulf Coast.

The relevant, unrefuted facts in this record are as follows. In April 1993, Gulf Coast became aware that the Florida Department of Corrections (DOC) was planning to locate a prison in West Florida and was considering sites in several counties, including one in Washington County. In that same month, Gulf Coast made a public proposal to the Washington County Commission for a $45,-000 grant and for assistance in securing a loan of $300,000 to acquire Washington County property for the prison. Gulf Power, which also served the Washington County area, made no similar proposal. The loan and grant were put in place and a site was [121]*121selected and secured. Gulf Coast was selected to provide service to the site by Washington County, and DOC approved that choice.

To serve the prison, Gulf Coast relocated its existing Red Sapp Road single-phase line, which was located on the prison site, and upgraded the line to three-phase at a total cost of $51,579. The relocation cost was $36,997 and the upgrade to three-phase cost was $14,583. This existing line had to be relocated, regardless of whether Gulf Coast or Gulf Power served the prison. The line was relocated by Gulf Coast across the road from Gulf Power’s existing three-phase line that was constructed during the early 1970s.

In September 1993, Gulf Power filed with the Commission a petition seeking to serve the prison and asserting that Gulf Coast had constructed facilities that duplicated Gulf Power’s. In resolving the dispute, the Commission followed Florida Administrative Code Rule 24-6.0441(2) (1993), which provides:

(2) In resolving territorial disputes, the Commission may consider, but not be limited to consideration of:
(a) the capability of each utility to provide reliable electric service within the disputed area with its existing facilities and the extent to which additional facilities are needed;
(b) the nature of the disputed area including population and the type of utilities seeking to serve it, and degree of urbanization of the area and its proximity to other urban areas, and the present and reasonably foreseeable future requirements of the area for other utility services;
(c) the cost of each utility to provide distribution and subtransmission facilities to the disputed area presently and in the future; and
(d) customer preference if all other factors are substantially equal.

The Commission also applied section 366.04(5), Florida Statutes (1993), which provides:

(5) The commission shall further have jurisdiction over the planning, development, and maintenance of a coordinated electric power grid throughout Florida to assure an adequate and reliable source of energy for operational and emergency purposes in Florida and the avoidance of further uneconomic duplication of generation, transmission, and distribution facilities.

(Emphasis added.)

Under subsection (a) of rule 25-6.0441(2), the Commission found that both utilities had been serving the same area for more than twenty years and that the utilities had a “comparable ability” to serve the prison. Specifically, the Commission found:

Both utilities have been serving customers in the vicinity of the intersection of County Road 279 and State Road 77 for over 20 years. Gulf Coast has served retail customers along Red Sapp Road since 1949-50. Gulf Coast has also maintained two-phase and three-phase service adjacent to the correctional facility site since 1950. Currently, Gulf Coast is serving 665 customers within 5 miles of the site. Gulf Power currently has 532 metered customers within five miles of the site, 330 of which are in Sunny Hills.

The Commission also found that “both utilities have adequate facilities to serve the prison, both are capable of providing reliable electric service, and therefore both have comparable ability to serve.”

Subsection (b) of rule 24-6.0441(2), which concerns the nature of the disputed area (rural with small commercial development), was not at issue in this proceeding.

Under subsection (c) of the rule, the Commission found that Gulf Coast had expended .$14,583 upgrading its single-phase line to a three-phase line in order to provide service. Because Gulf Power had an existing three-phase line capable of providing service to the prison, the Commission found that the $14,-583 represented the cost differential between the two utilities’ “cost to serve.”

The Commission found subsection (d), customer preference, to be inapplicable, concluding that it could consider customer preference in resolving territorial disputes only if all other factors were substantially equal. The Commission determined, however, that all other factors in this ease were not equal [122]*122because Gulf Coast had duplicated Gulf Power’s existing lines and had engaged in a “race to serve.” In making this determination, it said:

We have decided that Gulf Power shall provide electric service to the new correctional facility in Washington County. Our primary reason for this is that Gulf Coast duplicated Gulf Power’s existing facilities in order to serve the prison. We understand that the area in dispute is primarily rural. We understand that the additional cost to Gulf Coast to serve the facility is relatively small. We believe that Gulf Coast is as able as Gulf Power to serve reliably, and we are aware that the customer prefers Gulf Coast even though its rates are higher. We simply cannot ignore the fact that Gulf Coast’s upgrade of the relocated Red Sapp Road single-phase line to three-phase duplicated Gulf Power’s existing facilities. We always consider whether one utility has uneeonomically duplicated the facilities of the other in a “race to serve” an area in dispute, and we do not condone such action.
[[Image here]]
... [W]e are very conscious of the role Gulf Power played in this matter. Gulf Coast made the effort and spent the money necessary to bring the new correctional facility to Washington County. But for Gulf Coast’s efforts, the facility would not be there for anyone to serve. Gulf Power was aware of Gulf Coast’s efforts, but said nothing.

Based on these facts, the Commission awarded service to Gulf Power and directed Gulf Power to reimburse Gulf Coast for the $36,997 cost of relocating the Red Sapp Road line. The Commission also ordered the two companies to develop a territorial agreement to avoid future duplication of facilities and to establish territorial boundaries.

Gulf Coast has appealed the Commission’s award of service to Gulf Power; Gulf Power has cross-appealed the Commission’s directive that Gulf Power reimburse Gulf Coast for the cost of relocation. The Commission’s order regarding the development of a territorial agreement is not at issue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Choctawhatchee Electric Cooperative, Inc. v. Art Graham, etc.
132 So. 3d 208 (Supreme Court of Florida, 2014)
WEST FLORIDA ELEC. CO-OPERATIVE ASSOCIATION v. Jacobs
887 So. 2d 1200 (Supreme Court of Florida, 2004)
S.E. Iowa Cooperative Electric Ass'n v. Iowa Utilities Board
633 N.W.2d 814 (Supreme Court of Iowa, 2001)
SE IOWA CO-OP. ELEC. v. Iowa Util. Bd.
633 N.W.2d 814 (Supreme Court of Iowa, 2001)
GULF COAST ELEC. CO-OP., INC. v. Johnson
727 So. 2d 259 (Supreme Court of Florida, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
674 So. 2d 120, 169 P.U.R.4th 662, 21 Fla. L. Weekly Supp. 221, 1996 Fla. LEXIS 900, 1996 WL 271187, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gulf-coast-electric-cooperative-inc-v-clark-fla-1996.