Guinn v. Rapides Parish Police Jury

649 So. 2d 1148, 94 La.App. 3 Cir. 980, 1995 La. App. LEXIS 132, 1995 WL 35750
CourtLouisiana Court of Appeal
DecidedFebruary 1, 1995
Docket94-980
StatusPublished
Cited by3 cases

This text of 649 So. 2d 1148 (Guinn v. Rapides Parish Police Jury) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guinn v. Rapides Parish Police Jury, 649 So. 2d 1148, 94 La.App. 3 Cir. 980, 1995 La. App. LEXIS 132, 1995 WL 35750 (La. Ct. App. 1995).

Opinion

649 So.2d 1148 (1995)

Jimmie B. GUINN, et al., Plaintiffs-Appellees
v.
RAPIDES PARISH POLICE JURY, Defendant-Appellant.

No. 94-980.

Court of Appeal of Louisiana, Third Circuit.

February 1, 1995.

*1149 Guy E. Humphries Jr., Alexandria, for Jimmie B. Guinn et ux.

Robert Lewis Bussey, Asst. Dist. Atty., for Rapides Parish Police Jury, et al.

Before DOUCET, C.J., and THIBODEAUX and SULLIVAN, JJ.

THIBODEAUX, Judge.

Defendant-appellant, the Rapides Parish Police Jury, appeals the trial court's judgment in favor of plaintiffs, Jimmie and Ava Guinn. After a bench trial, the trial court determined that the Police Jury failed to place spoil from a drainage project on the plaintiffs' property as contemplated by the contract between the parties. It awarded damages of $75,000.00 and $8,000.00 in attorney's fees.

For the following reasons, we affirm the trial court's judgment on liability, amend the damage award to $154,333.00 and reverse the award of attorney's fees.

I.

ISSUES

The Rapides Parish Police Jury raises six assignments of error which can be condensed into the following issues:

1) whether the trial court properly interpreted the contract between the Rapides Parish Police Jury and the Guinns;
2) whether the trial court erred in not allowing defense exhibits, proffers number one, two, and three as well as the testimony concerning those documents; and,
3) whether the trial court erred in granting attorney's fees when the contract did not provide for fees.

II.

FACTS

On April 22, 1974, the Guinns entered into a contract with the Rapides Parish Police Jury through their attorney, Gus Voltz. The Guinns granted the parish permission to dredge a drainage canal that runs along the southern boundary of their property. The right of way was necessary for construction, maintenance, and improvement of drainage facilities along the channel of Flat Bayou.

The contract stated the consideration for the grant was "the expectation of benefits to said property as a result of the drainage improvement program." The agreement also provided, "In Section 77, where possible, spoil will be placed on grantor's property so as to form a levee so that the drainage water will not flood onto grantor's property."

The sole issue at trial was whether the Police Jury breached its agreement by not placing the spoil in Section 77 on the Guinns' property. The spoil in this section was placed on the opposite bank on the Eskew property. As a result, the Guinns' property now floods in heavy rains, and the ponds on *1150 their property, previously stocked with game and fish, are now mudholes. The trial judge found the Police Jury breached its contractual agreement. The Police Jury appeals, alleging several assignments of error. The Guinns answered the appeal, requesting an increase in the damages awarded and the assessment of costs to the appellant.

III.

LAW & ANALYSIS

A. Liability

The correct interpretation of a contract requires a determination of the intent of the parties. La.Civ.Code art. 2045. Where the language of the contract is clear and unambiguous and leads to no absurd consequences, no further search for the parties' intent should be made. La.Civ.Code art. 2046. Where words or provisions in the contract are susceptible to more than one meaning, the meaning given must be that which renders the contract effective and best reflects the object of its makers. La.Civ. Code arts. 2048, 2049. However, if the meaning of a provision is doubtful, the interpretation must be made in accordance with the nature of the contract, equity, usages, the parties' conduct prior and subsequent to the formation of the contract, and according to other contracts of a like nature between the same parties. La.Civ.Code art. 2053. Breach of an obligation gives the obligee the right to recover damages for the obligor's failure to perform, or his defective or delayed performance. La.Civ.Code art. 1758.

Because the spoil was not placed to form a levee, the Guinns' property flooded when the canal water rose above normal. As the trial court stated, the Guinns also lost fish and wildlife in their ponds after the floods. When the flooding subsided, their ponds drained and became mudholes.

The trial court found the Police Jury failed to comply with the terms of the agreement and was liable to the Guinns for their losses from the jury's noncompliance. It noted losses from noncompliance include the cost of repairing any defects or of completing the work. It found the Guinns were entitled to the cost of forming a levee, and awarded $75,000.00 and $8,000.00 for attorney's fees.

We agree with the result reached by the trial judge, but for different reasons. He found liability on the basis of La.Civ.Code art. 2769, which addresses a contractor's liability for noncompliance with a contract. In the present case, we find the contract can be interpreted solely on the face of the document.

Mr. Guinn granted the Police Jury a right of way on his property. In the contract, Mr. Guinn stated his consideration for the grant was his expectation of benefits to his property as a result of the drainage project. He specifically requested the placement of spoil in Section 77 to prevent his home and his property from flooding. The Police Jury breached its contractual agreement, and therefore, is liable for the damages caused by their breach.

The Police Jury argues the trial judge erred by basing his decision on his finding that a principal-agent relationship existed between the Police Jury and their contractor. We do not agree. The trial judge based his decision on contractual principles. The trial judge did note the Police Jury, through its agent and contractor, Holloway Construction Company, did not comply with the contract terms. However, this statement is not the basis for the trial court's decision. The Police Jury incurred the obligation to fulfill the terms of the right of way agreement.

The Police Jury complains the trial judge erred by not allowing proffered evidence which would have established the lack of legal relationship between the Police Jury and the contractor, Wendell Johnson. The Police Jury also asserts the proffered evidence would have shown the State of Louisiana controlled the actions of the contractor on the Flat Bayou project, and the Police Jury was a mere sponsor for the project. The Police Jury's third proffer consists of survey maps which the jury asserts would have shown whether placement of the spoil on the Guinns' property was possible and whether the Guinns' property would have flooded in spite of the requested placement of spoil.

*1151 The trial judge, of course, is granted broad discretion in conducting a trial and in determining whether to receive or refuse testimony and evidence. Ware v. Medical Protective Insurance Co., 621 So.2d 54 (La. App.2d Cir.), writ denied, 629 So.2d 354 (1993).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guinn v. Rapides Parish Police Jury
708 So. 2d 835 (Louisiana Court of Appeal, 1998)
Thomas v. Fidelity Brokerage Services, Inc.
977 F. Supp. 791 (W.D. Louisiana, 1997)
Cott Index Co. v. Jagneaux
685 So. 2d 656 (Louisiana Court of Appeal, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
649 So. 2d 1148, 94 La.App. 3 Cir. 980, 1995 La. App. LEXIS 132, 1995 WL 35750, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guinn-v-rapides-parish-police-jury-lactapp-1995.