Guillot v. Ryan

282 So. 2d 755, 1973 La. App. LEXIS 6457
CourtLouisiana Court of Appeal
DecidedAugust 22, 1973
DocketNo. 9389
StatusPublished

This text of 282 So. 2d 755 (Guillot v. Ryan) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guillot v. Ryan, 282 So. 2d 755, 1973 La. App. LEXIS 6457 (La. Ct. App. 1973).

Opinion

PICKETT, Judge.

This is a suit by the plaintiff, Albin Guillot, d/b/a Al’s Dozer Service, against the defendants, Sam P. Ryan and S & R Adhesive Co., Inc., in which the plaintiff seeks to recover the sum of $3,675.00, the value of certain fill dirt hauled, delivered and spread by the plaintiff at a building site owned by defendants, under the terms of a contract with the defendants. The defendants answered the plaintiff’s petition with a general denial of liability; and reconvened for damages alleged to have resulted from the failure of the plaintiff to comply with the terms of his contract, particularly, but not exclusively, by his failure to provide the quality of material agreed upon, and because of his failure to spread and compact the dirt fill as agreed. Furthermore, the defendants alleged the plaintiff did not deliver the quantity of dirt fill claimed by him.

Judgment was rendered in the lower court in favor of plaintiff, Albin Guillot, and against the defendants, Sam P. Ryan, and S & R Adhesive Co., Inc., jointly, severally and in solido, in the sum of $3,675.-00, plus legal interest thereon from November 17, 1970, until paid, and for all costs of the proceeding. The defendant, Sam P. Ryan, has appealed suspensively.

[756]*756The evidence shows that the defendant, Sam P. Ryan, is the owner of S & R Adhesive Co., Inc., a corporation, located in New Orleans, which is engaged in the manufacture of adhesive compounds. Mr. Ryan decided to relocate his New Orleans plant in St. Tammany Parish. For the purpose of relocating the plant, Mr. Ryan acquired for his plant site a parcel of land in Section 19, Township 6 South, Range 10 East, containing 4.58 acres, situated in St. Tammany Parish, which is more particularly described in Paragraph One of the plaintiff’s petition. On this parcel of land the defendant, Sam P. Ryan, hereinafter referred to as Ryan, erected a prefabricated metal building, which is fifty feet in width and one hundred twenty-five feet in length. The foundation, upon which the building rests, consists of a layer of concrete footing on top of which a chain wall of concrete blocks was constructed around the entire perimeter of the site of the building. The wall was four feet in height. The manufacturing process carried on by Ryan’s corporation required the use of such equipment as a boiler, kettles, and 55-gallon containers and storage tanks. Ryan’s plans called for a concrete slab designed to serve as the interior floor of the building! His construction plan called for the rectangular shaped box-like chain wall of concrete blocks, on which the building would rest, to be filled with dirt to the top of the wall. The concrete floor was to be poured on the dirt fill. It was necessary that the base on which the concrete floor was to be constructed, as well as to the floor itself, should be strong enough to support the heavy equipment to be used in the manufacturing processes to be carried on in the building.

Ryan contracted with Albin Guillot, hereinafter referred to as Guillot, to supply the dirt needed to fill the rectangular box formed by the chain wall of concrete. Accordingly, on July 29, 1970, Guillot and Ryan entered into a contract ■ in which Guillot agreed to deliver and spread with a bulldozer approximately 1,000 cubic yards of clay fill dirt for the price of $25.00 per 12 cubic yards load.

The evidence shows that beginning on or about July 29, 1970, to September 14, 1970, the plaintiff made deliveries of dirt to the plant site with two trucks, each with a twelve cubic yard capacity. Guillot alleges he delivered and spread, according to the terms of the contract, 153 loads of fill dirt. But when Guillot requested Ryan to pay for the dirt he refused to pay for it. Ryan gave as his reasons for his refusal to pay for the dirt that Guillot did not deliver the quantity of dirt claimed by him, and that the dirt delivered was unsuitable for the purposes intended and, furthermore, Guillot did not spread the fill as agreed to in the contract. The defendant reconvened against Guillot for damages which he alleges he suffered because of Guillot’s breach of the contract by his failure to deliver suitable fill dirt and to spread it as agreed upon. Ryan also claims damages because of the plaintiff’s delay in performing what work he did perform.

The appellant alleges the trial judge committed the following errors:

“The evidence shows that the quantity of fill for which S & R Adhesive Company was billed was not received.
The evidence shows that the fill was not compacted.
The evidence shows that the fill was inferior by reason of the debris, roots and stumps found in it.”

The plaintiff, Guillot, in support of his claim for fill dirt hauled, produced 153 delivery tickets, each of which he said represented a truck load of 12 yards of fill dirt. The delivery tickets had been numbered from 1 to 153 consecutively for the purpose of the trial. Mr. Otho E. Sleeth, who was identified as Ryan’s overseer during the time the plaintiff was hauling the fill dirt, testified at length concerning the delivery tickets. He acknowledged his signature on all but a few of the delivery tickets. A few of the delivery tickets were [757]*757signed by either Wayne Dufour, Billy Bennett, or a Mr. Loyd, all of whom, Mr. Sleeth said, were employees of Ryan. Mr. Sleeth testified that each ticket represented one 12 cubic yards load of fill dirt. The delivery receipts filed in evidence shows that 1,800 cubic yards of fill dirt was actually delivered and spread at the job site. In fact, counsel for Ryan admits as much, but suggests that Mr. Sleeth would sign an original ticket and in place of a carbon copy, would sign a blank ticket. Mr. Sleeth was questioned at length about his signatures on the delivery tickets, but he could not be positive that any of the tickets were duplicates, or carbons. The district judge in his oral reasons for judgment dictated into the record, said:

“The court noted the tickets seemed to be numbered, for the purpose of the trial, in sequence from the number one through the number 153 and except for one or two little tickets, the court cannot reach any conclusion that there has been any duplication in these tickets which serve as invoices, or that the dirt was not, in fact, delivered to the site.”

We have carefully reviewed all of the evidence relative to the sufficiency of the delivery tickets, and we are unable to say the findings of fact of the trial court that the fill dirt was delivered to the job site as disclosed by the delivery tickets is manifestly erroneous.

The defendants point out that the quantity of dirt which the plaintiff alleges he hauled could not be placed in the space provided for it. The foundation of the building was 50 feet by 125 feet. A chain wall four feet high was constructed of concrete blocks around the area to be filled with dirt. The defendants contend that the space to be filled by dirt would only contain 967i/2 cubic yards in the interior of the building, and 262]/ cubic yards on the exterior. But Mr. Lyman Ellzey, a consulting civil engineer, a witness for the defendants, who had calculated the capacity of the space to be'filled with dirt, admitted that the loose dirt could be packed so that a quantity of dirt greatly in excess of 967% cubic yards could be physically placed inside the concrete wall of the structure. However, Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

C. M. Penn & Sons v. A. Giambelluca Construction Co.
259 So. 2d 594 (Louisiana Court of Appeal, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
282 So. 2d 755, 1973 La. App. LEXIS 6457, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guillot-v-ryan-lactapp-1973.