Guidry v. Dwight Manuel, Inc.

877 So. 2d 346, 3 La.App. 3 Cir. 1236, 2004 La. App. LEXIS 1775, 2004 WL 1506526
CourtLouisiana Court of Appeal
DecidedJuly 7, 2004
DocketNo. 03-1236
StatusPublished
Cited by1 cases

This text of 877 So. 2d 346 (Guidry v. Dwight Manuel, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guidry v. Dwight Manuel, Inc., 877 So. 2d 346, 3 La.App. 3 Cir. 1236, 2004 La. App. LEXIS 1775, 2004 WL 1506526 (La. Ct. App. 2004).

Opinion

JjWOODARD, Judge.

The Plaintiffs appeal the jury’s determinations concerning fault allocation and damages. Defendant and third-party Plaintiff, Manuel, appeals the fault allocation, as well. We affirm the trial court’s fault allocation but increase the damages awarded to $243,970.00.

*****

In May 1998, Sandres J. Guidry and his wife, Cathy, retained Acadiana Architects (Acadiana) to design a building to serve as the new office and warehouse for his company, Guico Specialty Company, Inc., (Gui-co). Guico distributes high pressure products, such as hoses, valves, fittings, and high pressure pumps. When Acadiana finished the plans and specifications for the new building, the Guidrys took bids from different contractors, ultimately hiring Dwight Manuel, Inc. (Manuel) to construct the building. Mr. Manuel subcontracted Baldwin Redi-Mix (Redi-Mix) and Mr. Daniel Popillion, a concrete finisher. Redi-Mix was supposed to deliver concrete of a certain compression strength, specifically described as 3000 pounds per square inch (psi), for the building and 3500 psi concrete for the parking lot. The Plaintiffs became dissatisfied with Manuel’s performance and terminated their contract. They hired MPW Construction, Inc., (MPW) to finish the project. At this point, Redi-Mix had already poured the concrete.

MPW finished construction and Guico began operating out of the new building. However, the concrete started cracking, prompting Mr. Guidry to have it tested. The tests revealed that the concrete’s strength was only approximately 1750 psi. Testimony and delivery tickets revealed that the concrete was diluted with water at the job site, reducing the compression strength. Accordingly, Mr. and Mrs. Gui-dry filed suit against Manuel, Acadiana, MPW, and two individuals associated with Acadiana and MPW, William W. Koetting and William P. Mills. Mr. Guidry’s company, Guico, was also a Plaintiff, alleging that the Defendants disturbed its rights as lessee of the building. Manuel filed a third-party demand against Redi-Mix and Mr. Popillion, the concrete finisher. The [348]*348Plaintiffs also added a claim against Redi-Mix. Because of an inability to timely serve Mr. Popillion, the trial court severed the claim | ^against him, and he was not a party in this litigation. Nonetheless, the jury was asked to consider whether Mr. Popillion bore any responsibility.

At the end of the Plaintiffs’ case, the trial court directed a verdict in favor of all Defendants except for Manuel and its insurer, Maryland Casualty Company, and Redi-Mix. The jury found Manuel 100% at fault and awarded Mr. and Mrs. Guidry $67,120.00, reduced by $29,120.00 for their failure to mitigate their damages, for a total award of $38,000.00. The jury rejected Guico’s claims. The trial court rendered judgment in accord with the jury’s finding and dismissed Manuel’s third-party demand against Redi-Mix. Manuel appeals, only, the dismissal of its third-party demand against Redi-Mix. Plaintiffs, also, appeal Redi-Mix’s dismissal, as well as the amount of damages and the jury’s failure to recognize Guico’s claims.

* * :|c 4c *

STANDARD OF REVIEW

Negligence or fault determinations, as well as the quantum of damages, are factual determinations which are entitled to great deference.1 This court must review the jury’s verdict for manifest error.2 If we find a reasonable basis for the jury’s determinations, we must affirm even though we would have made different determinations had we been the trier of fact.3

Redi-Mix’s Liability

Manuel alleges that Redi-Mix breached its oral contract to provide concrete of the designated strength. Alternatively, Manuel claims that the defective concrete is a result of Redi-Mix’s negligence. The Plaintiffs’ claims against Redi-Mix are predicated upon negligence.

There is a reasonable basis in the record for the jury’s determination that Redi-JMix3 did not breach a duty, either in contract or in tort. The record supports that Redi-Mix delivered concrete of adequate strength to the construction site. Thus, Redi-Mix argues that it fulfilled its duty. Contrarily, the Plaintiffs and Manuel argue that Redi-Mix’s duty extended to pouring concrete of adequate strength. However, there was ample testimony that once the Redi-Mix trucks arrive at the job site, the general contractor or his subcontractors are responsible for directing and supervising the pour. While, only, the Redi-Mix employees are authorized to turn the nozzle on the trucks that actually adds the water, even Manuel admitted:

Well, typically, if there is no supervisor on site and it’s just the finishers there, like let’s suppose it’s some other job, and I’m not there, and it’s just the finishers and the concrete truck, well the finisher is going to tell the concrete truck how much water to put. Certainly, the concrete guy not on his own is going to put water. It is true. Those concrete finishers will tell them if they need more or less water.

Nonetheless, Manuel continued to state that on this particular pour, he was not present the whole time and because Mr. Huval, Redi-Mix’s sales representative, was present, he was relying on him to make sure it was a good pour. Thus, Manuel’s testimony implies that even though, typically, the contractor is respon[349]*349sible, Mr. Huval assumed the responsibility in this instance, simply by being present the entire time. However, Mr. Huval testified that he did not direct the truck operators to add any water. Furthermore, Mr. Clint Bishop, Redi-Mix’s owner testified that its sales representatives’ responsibilities were as follows:

They’re there to actually regulate, make sure that the trucks show up, and what happens is they wait for somebody to give them the go-ahead to order the trucks. They call the plant and they make sure that the trucks don’t get lost on the way to the job, they don’t run into any problems getting to the job. From there they make sure the truck gets to the job site. They also monitor them at their washout area to make sure they don’t stand around and goof off, and they get back to the plant so that we have an efficient turn around time, and that we don’t have somebody waiting on concrete.

Additionally, Dr. Jerry Householder, an expert in construction management, structural and civil engineering, testified that the contractor or subcontractors were responsible for determining whether water should be added to the concrete. He further testified:

|4Q. Hypothetically, let’s assume that a general contractor wasn’t there when a pour was being placed. Would the responsibility at that point shift to the concrete supplier?
A. No, not the supplier. It’s never in the line of fire. It shifts to the person who represents the general contractor or the finisher. The finisher is always going to be there, but if the concrete truck rolls up and there’s nobody there, he’s going to turn around and go back. Somebody’s got to be there to accept the delivery.

Accordingly, we find a reasonable basis for the jury’s determination that Manuel was the sole responsible party at the time the water was added to the concrete.

The Plaintiffs and Manuel, also, argued that Redi-Mix used fly ash, an add mixture, in the concrete mix without any authorization. However, testimony revealed that fly ash is regarded as a cementious material that is commonly used in the industry.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guidry v. Dwight Manuel, Inc.
887 So. 2d 456 (Supreme Court of Louisiana, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
877 So. 2d 346, 3 La.App. 3 Cir. 1236, 2004 La. App. LEXIS 1775, 2004 WL 1506526, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guidry-v-dwight-manuel-inc-lactapp-2004.