Guido and Guido, Inc. v. Culberson County

459 S.W.2d 674, 1970 Tex. App. LEXIS 2514
CourtCourt of Appeals of Texas
DecidedOctober 21, 1970
Docket6123
StatusPublished

This text of 459 S.W.2d 674 (Guido and Guido, Inc. v. Culberson County) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guido and Guido, Inc. v. Culberson County, 459 S.W.2d 674, 1970 Tex. App. LEXIS 2514 (Tex. Ct. App. 1970).

Opinion

OPINION

FRASER, Justice.

This is a suit brought by Culberson County against the defendants for the enforcing of a bid bond submitted by the defendants in connection with the bidding for the construction of a hospital by Culber-son County. Generally, the facts are as follows:

On May 12, 1969 plaintiff-appellee advertised for bids on a construction project known as the Culberson County Hospital in Van Horn, Texas. In response to this invitation for bids, defendant-appellants Guido and Guido, Inc., timely submitted a bid to perform the construction of the project. Accompanying such bid was a bid bond executed by the contractor and the defendant-appellant National Surety Corporation. The bid of defendant Guido and Guido, Inc., provided that if defendant Guido and Guido, Inc., did not execute a formal contract within ten days and de *676 liver a surety bond at the same time, then the bid bond was to become the property of the plaintiff as liquidated damages for the delay and additional expenses caused thereby. Defendant National Surety Corporation bound itself to pay five per cent of the amount of the bid of $524,134.00, which amounts to $26,206.70, in the event Guido and Guido, Inc., failed to deliver an executed contract and a performance bond within ten days of written notice of acceptance of its low bid.

On June 30, 1969 plaintiff notified defendant Guido and Guido, Inc., in writing, that its bid proposal had been accepted. Defendant Guido and Guido, Inc., did not submit either an executed contract or a performance bond in support thereof within the required period of time. Thereafter, on or about July 14, 1969 the contract was awarded to the next low bidder, Area Builders, Inc., of Odessa, Texas, for a contract price of $536,900.00. On October 14, 1969 plaintiff brought suit against the contractor and the surety, and the defendants answered alleging, (1) that the defendants were not liable because the bid was submitted as a result of a unilateral mistake under such circumstances as to entitle the defendant' to the rescission of the bid and bid bond; (2) that the damages should be limited to $8,453.00 because the defendants had tendered to the plaintiff a substitute contractor who was willing to undertake the project for a sum in excess, by that amount, of the bid of Guido and Guido, Inc.; (3) that the maximum liability of the defendants was the sum of $12,766.00, this being the amount by which the second lowest bid on the project in question exceeded the bid of Guido and Guido, Inc.; and (4) that the bid and bid bond documents relied upon by the plaintiff constituted and imposed an unenforceable penalty. Trial was before the court and, after such trial, judgment was entered in favor of the plaintiff in the sum of $26,206.70.

Appellants’ first two points maintain that the trial court erred in finding that the contractor was not entitled to timely withdrawal or rescission of its bid because of an innocent mistake, so as to relieve the contractor and surety of any liability on the bid bond. Appellants’ position is that several days after it had submitted its bid, the contractor Guido and Guido, Inc., was informed by its auditor that it was not financially able to go forward with this undertaking. On June 30, 1969, the ap-pellee notified Guido and Guido, Inc., in writing that its bid proposal had been accepted. Appellants’ position is that they should be relieved because of an innocent mistake, the mistake being that several days after the bid bond and the bid itself had been submitted along with the opening of all other bids, the contractors’ auditor informed appellant contractor that it was not financially able to build this hospital or conform to the bid. Appellants take the position that because of this innocent mistake on the part of the contractors, Culberson County, the appel-lee, should relieve them from the liability on the bid bond. This has been done in other cases, but the cases cited by the appellants are all cases wherein the bidder made a substantial mistake in his arithmetic, from $18,000 to $100,000.00. The courts have relieved in these cases, and the law is well stated in James T. Taylor & Son, Inc. v. Arlington Ind. School Dist., 160 Tex. 617, 335 S.W.2d 371 (1960). The Supreme Court pointed out that before equitable relief would be granted against the unilateral mistake of the bidder, certain conditions must be present. The court went on to point out these conditions to be:

(1) the mistake is of so great a consequence that to enforce the contract as made would be unconscionable; (2) the mistake relates to a material feature of the contract ; (3) the mistake must have been made regardless of the exercise of ordinary care; and (4) the parties can be placed in status quo in the equity sense, i. e., rescission must not result in prejudice to the other party except for the loss of his bargain. We' do not find those elements present here. Here we simply have a situ *677 ation where Guido and Guido, Inc., did not take the ordinary care and precaution to determine whether or not they could comply with their bid if it were accepted; nor is the mistake of so great a consequence that to enforce the contract would be unconscionable. It does not affect a material part of the contract, nor can the parties be placed in status quo. The trial court, in its findings, held that the mistakes testified to by the president of Guido and Guido, Inc., would not have been made if he and other responsible parties of Guido and Guido, Inc., had exercised ordinary care. This was just one of the many findings of the court substantiating its decision. With regard to the matter of status quo, the court found in its Finding of Fact No. 27 that the parties could not be placed in status quo. This finding is amply substantiated by evidence showing that Culberson County suffered losses of time and suffered additional expenses which could only be remedied by payment of damages. As stated above, we have examined the cases cited by appellants and do not find one comparable to the one here existing, as they all relate to substantial mistakes in arithmetic by the bidder, both as to money and one relating to the time feature of one year.

Therefore, because it is evident that the contractors’ inability to perform is caused by its own carelessness, and would result in losses to the appellee, we overrule appellants’ first two points, finding no valid reason that could require or compel the appellee to release the appellants from their obligation.

With regard to the third and fourth points of error, the appellants charge that the court erred on the ground that the bid bond was submitted for security and penalty purposes and, as such, would only limit the county to recover actual pleaded and provable damages. We do not consider this bid bond as a penalty provision or document, but rather as liquidated damages. When the County announced that it was going to build the hospital and invited bids, each bid had to be accompanied by a bid bond to protect the County from the very thing that happened here, and it was stipulated and understood by the bidders that five per cent of their bid would constitute the bid bond which, in this case, was executed by the National Surety Corporation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gaynor Const. Co. v. Board of Trustees
233 S.W.2d 472 (Court of Appeals of Texas, 1950)
Hansen v. Eagle Mountain-Saginaw Independent School District
373 S.W.2d 817 (Court of Appeals of Texas, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
459 S.W.2d 674, 1970 Tex. App. LEXIS 2514, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guido-and-guido-inc-v-culberson-county-texapp-1970.