Guggenheim v. United States

61 Ct. Cl. 571, 1926 U.S. Ct. Cl. LEXIS 553, 1926 WL 2690
CourtUnited States Court of Claims
DecidedFebruary 15, 1926
DocketNo. B-101
StatusPublished

This text of 61 Ct. Cl. 571 (Guggenheim v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guggenheim v. United States, 61 Ct. Cl. 571, 1926 U.S. Ct. Cl. LEXIS 553, 1926 WL 2690 (cc 1926).

Opinion

GRAham, Judge,

delivered the opinion of the court:

The plaintiffs here seek to recover the sum of $63,752.52 as prospective profits by reason of an alleged breach of a contract due to the cancellation of same by the defendant. The contract was dated June 7, 1917, and expired December 31, 1917. It provided for the manufacture and delivery of 50,000 cotton service coats, and 85,000 woolen service coats. The cotton coats were to be delivered, 10,000 during July, 20,000 during August, and 20,000 during September. The woolen coats were to be delivered, 15,000 during September, 20,000 during October, 25,000 during November, and 25,000 during December. The defendant was to furnish the cloth for both kinds of coats, to be delivered f. o. b. Cleveland, Ohio. The contract, in terms, fixes no time for delivery. In addition to the price of $0,847 for each cotton coat manufactured, delivered, and accepted, and $1,749 for each woolen coat, the plaintiffs were to have the rags and clippings provided the Government did not decide to purchase them at a price to be determined by the authorities of the Department of Commerce. The Government did not purchase the rags and clippings, and the plaintiffs retained them.

The Government, as stated, was to furnish the cloth; the plaintiffs were to furnish all other things necessary to turn out the completed garments, including braid, labor, etc. It is admitted that there were 250 cotton coats undelivered at the time the company ceased operations, between the 1st and 15th of February, 1918, and that only 11,050 woolen coats had been manufactured and delivered at that time.

The theory upon which plaintiffs seek to recover is that they were delayed in commencing work by the failure of the defendant to furnish the cloth required for the manufacture of the cotton coats, which, under the contract, it was obligated to furnish. There is no claim that there was delay in delivery of the cloth for the woolen coats, the manufacture of which was not to commence until the first of September. The delay complained of was the failure of the [581]*581Government to deliver any cloth for the manufacture of the cotton coats until the latter part of July or the first of August.

Plaintiffs claim that they were ready to commence operations in the early part of July, with the necessary equipment, supplies, and force of workmen; that by reason of the delay and the nonemployment of their workmen, the latter drifted away and sought other employment so that when the cloth began to arrive during the latter part of July and the first of August their organization was so crippled that they could not proceed with the work as they had prepared to do and were unable to procure the needed employes; that this situation had a continuing effect, and accounted for their failure to manufacture and deliver the coats in the quantities and at the time fixed in the contract; and that for this reason the Government was not justified in cancel-ling the contract on account of delay and unsatisfactory conditions of production and delivery, as these circumstances had been brought about by the Government’s failure to deliver the cloth promptly.

As early as September 6, just as plaintiffs were beginniEg the manufacture of the woolen coats, which were by far the largest part of the contract both as to volume and amount of money involved, they asked to have their contract cancelled and the whole contract for the woolen coats transferred to someone else, for the reason that their manager, who was taking care of the contract for them, had proved inefficient and incapable of handling it, and they offered to transfer the materials purchased, and which under the contract they were called upon to purchase, to the defendant at cost price. Whereupon, on September 11, the depot quartermaster at Chicago, to whom the manufactured goods were to be delivered, recommended the cancellation of the contract, stating that the plaintiffs had never been engaged in the manufacture of anything but ladies’ shirt waists and had not shown ability to manufacture men’s garments, and that the contract should be transferred to the Bloch Uniform Co., of Cleveland, who already had a contract for overcoats and were showing excellent progress and evident ability to serve the interests of the Government.

[582]*582On October 8 the depot quartermaster at Philadelphia wrote to the depot quartermaster at Chicago, saying that if the plaintiffs wished the contract cancelled as to the woolen coats the Government would do so, but that the latter would be unwilling to agree to take the trimmings off plaintiffs’ hands. It appears that plaintiffs later made amicable arrangements with the Bloch Uniform Co. to take these trimmings off their hands.

On December 18, owing to the default of the plaintiffs in delivering materials at the times and in quantities fixed in the contract, the defendant sent a representative to Cleveland to look into the situation. Pie had a conference with several members of the plaintiffs’ company. He was informed that they would be glad! to be released from their obligations on the woolen coat part of their contract, among other reasons assigning S. D. Guggenheim’s ill health, their lack of proper equipment and experience, and that it was a costly venture and they were losing money.

Defendant’s representative reported this to his superior and recommended that the contract be transferred to the Bloch Uniform Company, with whom, as above stated, the Guggenheims afterwards made amicable arrangements for taking off their hands the materials they had purchased for completing the contract.

On December 22 the same representative of the defendant was instructed to confer with the Guggenheim Company with a view to having them complete the.garments already cut. The instructions were carried out and the representative sent the following communitíation to his superior: “ * * * stopped all cutting. Guggenheim will complete all in work and cut. Bloch will be in Washington December 28.”

On January 8, 1918, the defendant wrote a letter to the plaintiff company notifying them that that portion of the contract pertaining to the manufacture of the 85,000 woolen coats was cancelled except garments- then cut, which were to be completed by the company, and directing them to turn over the materials on hand belonging to the Government to the Bloch Unifonm Co. Thereupon, without protest or objection, the plaintiff company turned over the materials on [583]*583hand to the Bloch Company, completed the manufacture of the cut garments, and were paid the contract price for all garments manufactured and delivered, both cotton and woolen.

Plaintiffs never presented a claim to the Claims Board of the War Department in connection with the matter. It does appear that they presented a claim, the time is not shown, to the Auditor of the War Department, who refused to pay it, and some time later, when, it is not shown, they presented a claim to the Comptroller of the Treasury, payment of which was refused. On May 15, 1922, more than four years from the date of the cancellation of the contract, they filed their petition in this court.

The court has found that there was no satisfactory proof that the delay in furnishing material for the cotton coats caused the delay in the manufacture and delivery of the woolen coats, and therefore the delay in the manufacture and delivery of the woolen coats was not due to any neglect or default upon the part of the defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
61 Ct. Cl. 571, 1926 U.S. Ct. Cl. LEXIS 553, 1926 WL 2690, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guggenheim-v-united-states-cc-1926.