Guarnieri v. Kewanee-Ross Corp.

263 F.2d 413
CourtCourt of Appeals for the Second Circuit
DecidedFebruary 6, 1959
DocketNo. 144, Docket 24708
StatusPublished
Cited by9 cases

This text of 263 F.2d 413 (Guarnieri v. Kewanee-Ross Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guarnieri v. Kewanee-Ross Corp., 263 F.2d 413 (2d Cir. 1959).

Opinion

MOORE, Circuit Judge.

Kewanee-Ross Corporation (hereinafter referred to as “Kewanee”), the sole defendant in the action instituted by plaintiff to recover damages for the wrongful death of Nazario Guarnieri, appeals from a judgment for $75,000 entered against it in plaintiff’s favor after a jury trial.

Burnham Corporation (hereinafter referred to as “Burnham”), the third-party defendant, brought into the action by Kewanee as the third-party plaintiff, appeals from a judgment in favor of Ke-wanee against it for the same amount, i.e. $75,000. Jurisdiction is based upon diversity, the action having been removed from the New York State Supreme Court.

Plaintiff, as administratrix, brought suit against Kewanee for the death of her husband, an employee of Burnham, who was killed when a cylinder manufactured by Kewanee exploded while being pressure tested in Burnham’s plant by Burnham employees in the presence of United States Government inspectors. The alleged cause of the accident was the failure by Kewanee properly to weld the part of the cylinder which gave way. The issue posed by the complaint was whether Kewanee was negligent in making, manufacturing and welding the cylinder. Any liability on Kewanee’s part was, thus, dependent upon proof of negligence by Kewanee.

Kewanee answered by asserting that the injuries causing death were suffered while the “boiler” (cylinder) was under the exclusive control of Burnham and while it was being tested to discover whether there were any defects in the “boiler.” Kewanee also pleaded as a defense that as between Kewanee and Burnham the tests were to be conducted at Burnham’s factory and that Kewanee relied upon Burnham to make a proper test with adequate safeguards.

About a year and a half after the action was commenced Kewanee impleaded Burnham in a third-party action alleging that decedent’s death was caused not by “any act or omission by third-party plaintiff Kewanee-Ross Corporation, but solely and exclusively the negligence of Burnham Corporation in conducting the aforesaid test, and its negligence in failing to provide proper and adequate safeguards while the test was being conducted.”

The issues between the three parties as framed by the pleadings (and developed during the trial by proof and argument) were quite different both as to matters of law and fact. As between plaintiff and Kewanee, using Kewanee’s own standards, plaintiff had to prove:

“1. The boiler contained a defect when it left Kewanee’s plant; the defect was the result of Kewanee’s failure to exercise due care in constructing the boiler; and Kewanee failed properly to inspect the boiler with the defect before shipping it.
“2. The defect in the weld was the proximate cause of the accident which resulted in the death of plaintiff’s decedent
[416]*416“3. Plaintiff’s decedent was owed a duty of care by Kewanee, and was foreseeably within the risk of harm flowing from Kewanee’s negligence” (Kewanee Brief, pp. 6-7).

To defeat plaintiff’s claim, Kewanee argues that to weld the head of the boiler inadequately was not negligence; that the boiler was not inherently dangerous; that it was incomplete, “uninspected, untested, unready, and understood to be unready for use.” In short, Kewanee disclaims any responsibility to properly weld the head on the boiler because it knew that Burnham was going to pressure test the boiler before it was delivered to the ultimate user.

As between Kewanee and Burnham the issues alleged in Kewanee’s third-party complaint were whether Burnham “undertook to perform tests” and whether Kewanee “relied on, and was justified in relying on, Burnham Corporation to make a proper, careful test of such ‘boiler’ with adequate safeguards”; and whether there was any indemnity by operation of law.

The resolution of these various issues and a fair decision in this case depends in large part upon the proof and the instructions on the law given to the jury to guide them in making this determination. These instructions assume a peculiarly important role in this case because of the distinct differences in the issues between the three parties and the proof applicable thereto.

The Facts.

The Purchase Order

In early 1952 Burnham was engaged in the manufacture of parts of a guided missile referred to under the code name of “Honest John.” The fabrication of the cylinder was entrusted by contract to Kewanee. The contractual arrangements between Burnham and Kewanee were set forth in a series of letters and specifications (Exhs. 1-4). In its letter to Ke-wanee, dated March 8, 1952, Burnham enclosed specifications which stated the work to be done by Kewanee. A more detailed proposal was submitted by Ke-wanee to Burnham, dated March 13,1952, which was embodied in the actual purchase order sent by Burnham to Kewanee, dated April 2, 1952 (Exh. 4).

In substance Burnham ordered 138 “Honest John” units to be manufactured by Kewanee according to drawings and specifications submitted. The cylinders were to be formed from pieces of steel which were to be welded together. On one end of the cylinder a head plate was to be welded. An automatic welding process was used by Kewanee for this purpose.

The instructions amongst other details specified “Weld inside and outside — Do not grind weld”; “Automatic weld circumferential seams”; “Magnaflux or X-ray joints 1st two units only”; “Repair welds if necessary.” The letter of March 13, 1952 (Kewanee to Burnham) further provided “Cost of Magnaflux or X-ray is not included in our quoted price. We understand that you would like to have the first few units X-rayed. We will X-ray as many units as you request — [at Burn-ham’s expense] * * * ” A proof test of the welded seams was to be made by Kewanee “by making a cylinder three feet long and welding a head on each end with one inch couplings in the heads and testing to 1,800 per square inch.” Workmanship was “All to be first class in every respect.” Under the heading “Inspection and Responsibility” of the specifications attached to the purchase order letter of April 2, 1952 (Exh. 4) it was provided: “All fabricated material is subject to inspection and acceptance by representatives of the purchaser and/ or their customer. Although the fabricator is not responsible for the design, he shall be responsible for workmanship and materials furnished by him and shall guarantee such material and workmanship for a period of 6 months from commencement of use by the purchaser’s customer. Therefore, acceptance does not relieve the fabricator of responsibility for poor workmanship or materials, nor does it relieve him of errors in fabrication which may later come to light in the use of this material by the purchas[417]*417er’s customer.” Kewanee accepted the order with certain modifications not relevant to the issues here by letter dated May 22, 1952 (Exh. 5).

Kewanee proceeded to fabricate the cylinders. One operation called for cutting a hole in the head plate, inserting therein a piece of steel known as a “boss” and welding it. The thickness of the metal being s/m of an inch the weld had to be the same thickness. The weld, performed by using an automatic welding machine, required an inside weld and an outside weld which should have fused together forming a solid piece of metal and causing the boss to become firmly attached to the cylinder head to withstand the specified pressure (1,800 pounds per square inch) (Exh. 2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
263 F.2d 413, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guarnieri-v-kewanee-ross-corp-ca2-1959.