Guarisco Construction Company v. Talley
This text of 126 So. 2d 793 (Guarisco Construction Company v. Talley) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
GUARISCO CONSTRUCTION COMPANY, Inc. Plaintiff and Appellee.
v.
J. B. TALLEY, Defendant and Appellant.
Court of Appeal of Louisiana, Third Circuit.
*794 Willis & Willis, by Earl R. Willis, St. Martinville, for defendant.
Faris, Leake & Emmett, by Camille A. Cutrone, New Orleans, for plaintiff.
Before HOOD, SAVOY and CULPEPPER, JJ.
On Application for Rehearing en Banc February 21, 1961.
CULPEPPER, Judge.
Guarisco Construction Company, Inc. brings this action against John B. Talley for the recision of a verbal contract of exchange whereby it alleges that Mr. Talley agreed to allow plaintiff to remove dirt from 3¼ acres of land in exchange for a dragline and $1,000 worth of shells. Plaintiff alleges that it delivered the dragline to Mr. Talley and stood ready to deliver the shells but that Talley actively breached his obligation under the contract by divesting himself of title to the land, thereby making it impossible for him to perform. Plaintiff seeks to recover the dragline plus a reasonable rental therefor and damages incurred by plaintiff in reliance on the contract.
The lower court refused to hold that there was a contract of exchange, giving as its reason that at the time the contract was entered into Mr. Talley owned no interest in the land. However, the lower court's judgment decreed plaintiff to be the owner of the dragline and ordered defendant to surrender it to plaintiff. From this judgment the defendant has appealed.
Plaintiff has answered the appeal asking that the judgment be amended so as to allow a reasonable rental for the dragline during the time it was in possession of the defendant plus damages incurred by reason of defendant's breach of contract.
The facts as found by the lower court and as amply supported by the record are that in the year 1952 Mr. Talley obtained a contract with the Federal Government to build a levee near Morgan City, for which he needed a large quantity of dirt. In order to obtain the necessary dirt plaintiff purchased from Morgan City Company, Inc., represented by its agent, Mr. Robert E. Brumby, for a consideration of $5,735 cash a tract of land containing 11.47 *795 acres together with a right-of-way across an adjacent tract in order to gain access to the property. Although not contained in the deed nor in any other written instrument, Mr. Talley verbally agreed with Mr. Brumby that when he had removed all of the dirt he needed to fulfill his levee contract, he would convey the property back to Morgan City Company, Inc. The deed was dated January 22, 1952 and recorded in the Conveyance Records on February 11, 1952.
When Mr. Talley completed his levee contract there were approximately 3¼ acres of the original 11.47 acre tract left unexcavated. In about September of 1955 the plaintiff corporation, which is apparently managed by Mr. Anthony Guarisco, needed dirt for certain of its construction jobs and accordingly entered into a negotiation with Mr. Talley to obtain the dirt from the 3¼ acres which remained unexcavated. There is some conflict in the testimony as to whether Mr. Talley told Mr. Guarisco that any agreement which they entered into would have to be subject to the approval of Mr. Brumby. Mr. Talley testified that he told Guarisco he owned only "an equity" in the property and it would be necessary to get a "clearance" from Mr. Brumby. Guarisco testified that he was not informed by Talley that it would be necessary to have Brumby's approval or consent. Mr. Brumby testified that during the period of negotiation between Guarisco and Talley he told Mr. Guarisco that Talley "did not have all the rights that he seemed to have to the property" and warned him not to deal with Mr. Talley without discussing the matter with Brumby.
Regardless of the above conflict in the testimony there is no dispute that finally Mr. Talley agreed to allow plaintiff to remove the dirt from the unexcavated 3¼ acres in exchange for the dragline and $1,000 worth of shells. On December 5, 1955 plaintiff turned over the dragline to Mr. Talley. Upon learning of this agreement Mr. Brumby became alarmed and requested that Mr. Talley honor his verbal agreement to convey the property back to the Morgan City Company, Inc. which Mr. Talley did by deed dated December 12, 1955 and recorded on the same date in the conveyance records of St. Martin Parish. Mr. Brumby testified that at the time this deed was signed he discussed with Talley the agreement which Talley had made with Guarisco and since they were both his close friends he concluded that the equitable thing to do would be to allow Mr. Guarisco sufficient time to remove from the pit an amount of dirt approximately equal to the value of the dragline which he understood to be $2,750. As was found by the trial judge, the evidence does not show that Mr. Guarisco was ever informed by Talley or Brumby that his excavation of the property could or would be so limited by Mr. Brumby.
Soon thereafter Mr. Guarisco prepared the property for his use by building a shell road and clearing the area and also agreed to pay $2,000 to Mr. William J. Cotten for a right of passage over adjacent lands. Guarisco expected to remove approximately 100,000 yards of dirt from the pit over a period of about four (4) years.
In May of 1956 Mr. Brumby wrote a letter to Mr. Guarisco requesting that he cease removing dirt from the property. Brumby testified that he felt the five months which he had allowed was sufficient time for Guarisco to remove dirt equal to the value of the dragline. Actually, Mr. Guarisco had only removed about 75 truck loads of dirt valued at approximately $350. On receipt of Brumby's letter Mr. Guarisco protested to both Talley and Brumby and there is evidence in the record to indicate he was led to believe, at least by Mr. Talley, that some arrangement would be made whereby Guarisco could remove the rest of his dirt.
Under the above facts the lower court concluded that at the time Talley and Guarisco entered into their agreement Mr. Talley owned no right or interest in the *796 property because of his verbal agreement to reconvey the property back to the Morgan City Company, Inc. The trial judge held that therefore there was no binding contract between Talley and Guarisco. Although we agree with the trial court's finding of fact, we do not agree with its conclusion of law. The evidence is clear that at the time Talley and Guarisco entered into their contract, Mr. Talley was the record owner of the property in question. His verbal agreement to reconvey the property back to Morgan City Company, Inc. was clearly not legally binding as Mr. Brumby readily admitted from the witness stand during the trial of this case. We therefore conclude that as a matter of fact and of law Talley did own the property at the time he entered into the agreement of exchange with Guarisco and that this agreement was a valid contract of exchange.
It is our opinion that Mr. Talley actively breached his contract with Guarisco by deeding the property back to Morgan City Company, Inc. only seven days after he had received the dragline. Under the provisions of LSA-Civil Code, Article 1931 a contract is violated actively by doing something inconsistent with the obligation it has proposed. In the present case Talley contracted to lease to Guarisco the use of this 3¼ acres of land for the purpose of excavating dirt therefrom and then seven days later sold the property thereby making it impossible for Talley to fulfill his obligation. Clearly this is an active breach.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
126 So. 2d 793, 1961 La. App. LEXIS 1723, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guarisco-construction-company-v-talley-lactapp-1961.