Guaranty & Surety Co. v. Poe

114 A. 481, 138 Md. 446, 1921 Md. LEXIS 103
CourtCourt of Appeals of Maryland
DecidedMay 4, 1921
StatusPublished
Cited by3 cases

This text of 114 A. 481 (Guaranty & Surety Co. v. Poe) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guaranty & Surety Co. v. Poe, 114 A. 481, 138 Md. 446, 1921 Md. LEXIS 103 (Md. 1921).

Opinion

Thomas, J.,

delivered the opinion of the court.

On the 3rd of October, 1905, John P. Agnew, of Chicago, Illinois, entered into a contract with the City of Chicago- by which he agreed to construct a concrete tunnel under the shoal water of Lake Michigan, according to the plans- and specifications made a part of said contract, and under the direction and supervision of the commissioner of public works of the city. The- contract provided that the work was to be completed on or before July 31st, 1906, and that Agnew was to receive $138.33 per lineal foot for the work completed and finally accepted by the commissioner of public works. The contract and specifications; further provided that, if the progress of the work was satisfactory to the commissioner of public works, monthly estimates of the value of the work actually constructed should be made by him; that tin or about tiie 6th day of the following month vouchers should be issued for eighty-five per cent, of such estimated value, and that the remaining fifteen per cent, should be reserved until the acceptance of the whole work. The faithful performance of said contract by Agnew wasi secured by a bond executed by him and the Title Guaranty and Surety Company of Scranton, Pennsylvania, as surety, to the City of Chicago in the sum of $379,024. In October, 1906, the City of Ohicagp authorized a modification of the- contract of 1905 by extending the time for the completion of the work to May 31st, 1907, and Agnew accordingly executed a supplemental agreement to- that effect and a. new hond to the city, with the same guaranty company as surety, in the sum of $380,000, guaranteeing the performance of the original and supplemental contract. -Shortly after the execution of said supplemental agreement and new hond, a, dispute arose between Agnew and the commissioner of public works as to *448 the proper allowance for certain preliminary work spoken of in the record as “box-heading.” In the estimates that had been made of the value of the work Agnew had been allowed twelve dollars per1 foot for this work. He insisted that he should be allowed twenty dollars per foot, but the commissioner of public works refused to make the additional allowance, and finally referred Joseph Hanreddy, another contractor, who went to see him in regard to the matter, to the Mayor. On the 12th of November, 1906, the City C'ouncil of Chicago passed the following order:

“Ordered, That the Commissioner of Public Works be and he is hereby authorized and directed, in preparing estimates for payments to John P. Agnew under the contract for the construction of the Lawrence Avenue intake sewer, to estimate the cost of constructing the box heading at the rate of twenty dollars ($20) per lineal foot; provided, however, that before any such estimate is made to said Agnew, the said Agnew shall deliver to said Commissioner of Public-Works a good and sufficient conveyance of all his right, title and interest in the plant used in the construction of said tunnel, said plant to become the property of' the said Agnew whenever said tunnel is fully completed; and provided, further, that Joseph Hanreddy shall execute and deliver to the city his bond in the-penal sum of forty thousand dollars ($40,000.00), with surety to be approved by the Commissioner of Public Works, conditioned that if the said Agnew shall for any reason fail to complete said tunnel according to the terms of his contract, he, the said Hanreddy, shall complete the Said tunnel at a cost not exceeding the sum named in the contract between the said Agnew and the city.”

In accordance with the order of the City Council, Agnew,. on the 16th of November1, 1906, assigned his plant to the city; Joseph Hani’eddy, as principal, and.the United Surety Company of Baltimore, Maryland, as surety, executed a bond to the city in the sum of $40,000; an estimate was- *449 made allowing' Agnew twenty dollars a foot for the box-heading, and, he received the same, less the amount previously paid and the fifteen per cent, retained under the terms of the contract. Some time after obtaining the additional allowance for the box-heading, Agnew ceased to do any work under his contract, and the contract was, finally cancelled by the commissioner of public works about the1 12th of March, 1907. The Title Guaranty and Surety Company, surety on Agne-w’s bond, having declined to complete the work, the work was re-let by the city on the 6th of September, 1907, to another contractor, and was completed at a, cost to the city of about $102,000 more than the amount of Agnew’s contract. The city brought suit against Agnew and the Title Guaranty and Surety Company for that amount, and recovered a judgment against the company for $71,54541. It is said in City of Chicago v. Agnew, 182 Ill. App. 504: “The case was tried before the court without a jury, and after deducting from the city’s demand the additional amount paid for box-headings, and $10,800 paid to the second contractors as a bonus, the court, entered judgment for the remainder, $71,545.41.” That judgment was affirmed in City of Chicago v. Agnew, 264 Ill. 288. On the 18th of October, 1911, the City of Chicago filed a claim for the amount of Hanreddy’s, bond for $40,000 in the Circuit Court of Baltimore City against the receivers of the United Surety Company of Baltimore, and the Title Guaranty and Surety Company, after paying the judgment to the City of Chicago in 1914, and. after having procured for its, benefit an assignment of the judgment and of said bond, filed its, claim for the amount of said bond against the receivers on the Oth of February, 1915. Upon the evidence produced, in support- of the claim, the auditor of the court, below allowed it to the City of Chicago to the amount of $7,048. Thereafter the City of Chicago filed exceptions to the account, of the auditor on the ground that the claim should have been allowed in full, and the, Title Guaranty and Surety Company filed exceptions to said account on the ground (1) that the allowance made by the auditor should *450 have been made to it instead of the City of Chicago; and (2) on the ground that the claim should have been allowed to the amount of the bond and interest thereon. Thomas H. Bowles, as a creditor of the United Surety Company, also excepted to said allowance by the auditor on the ground that the claim was not supported by the evidence in the case. After a hearing, the court below overruled the exceptions of the City of Chicago and of the Title Guaranty and .Surety Company; sustained the exceptions of Thomas. II. Bowles and disallowed the claim, and from that order1 the City of Chicago and the Title Guaranty and Surety Company have1 brought this appeal.

The conditions of the bond to tire City of Chicago, given by Hanreddy and the United 'Surety Company of Baltimore, upon which the claim in dispute is based, are as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hamlen v. Rednalloh Co.
291 Mass. 119 (Massachusetts Supreme Judicial Court, 1935)
Lasby v. Burgess
289 P. 1028 (Montana Supreme Court, 1930)
Cumberland & Westernport Transit Co. v. Metz
149 A. 4 (Court of Appeals of Maryland, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
114 A. 481, 138 Md. 446, 1921 Md. LEXIS 103, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guaranty-surety-co-v-poe-md-1921.