Gte Telephone Oper. v. Jh Reinforcing, Unpublished Decision (5-20-2002)

CourtOhio Court of Appeals
DecidedMay 20, 2002
DocketCase No. 01CA2808.
StatusUnpublished

This text of Gte Telephone Oper. v. Jh Reinforcing, Unpublished Decision (5-20-2002) (Gte Telephone Oper. v. Jh Reinforcing, Unpublished Decision (5-20-2002)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gte Telephone Oper. v. Jh Reinforcing, Unpublished Decision (5-20-2002), (Ohio Ct. App. 2002).

Opinion

DECISION AND JUDGMENT ENTRY
This is an appeal from a Scioto County Common Pleas Court judgment in favor of JH Reinforcing Structural Erectors, Inc., defendant below and appellee herein, on the claims against it by GTE Telephone Operations, plaintiff below and appellant herein. The following errors are assigned for our review:

FIRST ASSIGNMENT OF ERROR:

"THE TRIAL COURT ERRED WHEN IT FAILED TO FIND DEFENDANT/APPELLEE NEGLIGENT, AND, THEREFORE, LIABLE FOR DAMAGES, FOR FAILING TO NOTIFY THE OHIO UTILITIES PROTECTION SERVICE, AS REQUIRED BY O.R.C. SECTION 3781.28-3781.30."

SECOND ASSIGNMENT OF ERROR:

"THE TRIAL COURT'S DECISION, AS A MATTER OF LAW, IS IN ERROR."

A brief summary of facts pertinent to this appeal is as follows. The Ohio Department of Transportation (ODOT) retained appellee to work on a bridge reconstruction project in Sciotoville. As part of that project, appellee was to remove a sidewalk. Appellee's employees began to cut a concrete sidewalk with a saw when they sliced into a conduit that contained appellant's phone cables.

Appellant commenced the action below on April 12, 2000, and alleged that appellee was liable for damage to its cables. Appellant asked for $31,392.47 in compensation. Appellee denied liability. The matter came on for a bench trial on August 29, 2001.

No question exists whether appellee cut into the conduit and damaged the phone cables. The central issue at trial was whether appellee and its employees behaved prudently in the process. To that end, considerable evidence was adduced to show that a "preconstruction meeting" occurred between appellee and various utility representatives. Eric McLaughlin, an ODOT engineer and appellee's employer on the project, testified that the purpose of the preconstruction meeting was to locate utility lines before work began. McLaughlin further related that they were informed that the phone lines ran beneath, not "in," the sidewalk. Because the construction plans only called for the removal of the sidewalk, without any excavation of the ground underneath, appellee's employees were not concerned about the possibility of phone line damage. Don Hadsell, appellee's owner, and project supervisor Jeff Clevenger, corroborated this story. Both witnesses testified that a Randy Chamberlin from the "phone company" had told them, before work began, that the cables were positioned underneath the sidewalk. In particular, Hadsell, related that Chamberlin told him that he could remove the sidewalk and that he would have no problems with the cables as long as he did not dig underneath the sidewalk.

As it turned out, the phone cables were buried or embedded inside the four inch (4") concrete sidewalk. McLaughlin testified that he had never seen cables embedded in a sidewalk. Indeed, Chamberlin, who previously worked for appellant, testified that the company typically buried cables thirty inches (30") under ground and did not embed cables in sidewalks.1 As for the preconstruction meeting, Chamberlin testified that he could not recall telling appellee that he could remove the sidewalk. By the same token, however, he also could not definitively say that he did not approve the sidewalk's removal.

At the conclusion of trial the court found in appellee's favor. The Court explained that appellee acted both "diligently" and "reasonably" in removing the sidewalk. Further, the Court found it credible that phone company representatives told appellee that it could remove the sidewalk as long as it did not dig underneath the sidewalk. The trial court filed its judgment on August 31, 2001. This appeal followed.

We jointly consider appellant's two assignments of error because they raise similar arguments. Our analysis begins from the premise that "[t]here is a positive nondelegable duty imposed on one excavating below ground to inform himself as to whether telephone cables are there so he can avoid damaging them." GTE North, Inc. v. Carr (1993),84 Ohio App.3d 776, 779, 618 N.E.2d 249. The failure to discharge that duty results in an excavator proceeding at his own risk for liability for cable damage. Id. at 780.

Trial court judgments are generally affirmed if they are supported by some competent and credible evidence. See Shemo v. Mayfield Hts.,88 Ohio St.3d 7, 10, 2000-Ohio-258, 722 N.E.2d 1018; Vogel v. Wells (1991), 57 Ohio St.3d 91, 96, 566 N.E.2d 154; C.E. Morris Co. v. FoleyConstruction Co. (1978), 54 Ohio St.2d 279, 376 N.E.2d 578, at the syllabus. This standard is highly deferential and even "some" evidence is sufficient to sustain the judgment and prevent a reversal. Barkley v.Barkley (1997), 119 Ohio App.3d 155, 159, 694 N.E.2d 989; also see LivingWaters Fellowship, Inc. v. Ross, Scioto App. No. 00CA2714, 2000-Ohio-1973; Simms v. Heskett (Sep. 18, 2000), Athens App. No. 00CA20. Moreover, determinations as to the weight of the evidence and the credibility of witnesses were issues for the trial court as trier of fact. See Cole v. Complete Auto Transit, Inc. (1997), 119 Ohio App.3d 771,777-778, 696 N.E.2d 289; Reed v. Smith (Mar. 14, 2001), Pike App. No. 00CA650; also see generally State v. Frazier (1995), 73 Ohio St.3d 323,339, 1995-Ohio-235, 652 N.E.2d 1000; State v. DeHass (1968),10 Ohio St.2d 230, 277 N.E.2d 212, at paragraph one of the syllabus. A trier of fact is free to believe all, part or none of the testimony of any witness who appeared before it. Rogers v. Hill (1998),124 Ohio App.3d 468, 470, 706 N.E.2d 438; Stewart v. B. F. Goodrich Co. (1993), 89 Ohio App.3d 35, 42, 623 N.E.2d 591; also see State v.Nichols (1993), 85 Ohio App.3d 65, 76, 619 N.E.2d 80; State v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barkley v. Barkley
694 N.E.2d 989 (Ohio Court of Appeals, 1997)
State v. Harriston
577 N.E.2d 1144 (Ohio Court of Appeals, 1989)
State v. Nichols
619 N.E.2d 80 (Ohio Court of Appeals, 1993)
Ohio Edison Co. v. Wartko Construction
658 N.E.2d 1118 (Ohio Court of Appeals, 1995)
Cole v. Complete Auto Transit, Inc.
696 N.E.2d 289 (Ohio Court of Appeals, 1997)
Stewart v. B.F. Goodrich Co.
623 N.E.2d 591 (Ohio Court of Appeals, 1993)
Gte North, Inc. v. Carr
618 N.E.2d 249 (Ohio Court of Appeals, 1993)
Rogers v. Hill
706 N.E.2d 438 (Ohio Court of Appeals, 1998)
State v. Dehass
227 N.E.2d 212 (Ohio Supreme Court, 1967)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
Vogel v. Wells
566 N.E.2d 154 (Ohio Supreme Court, 1991)
State v. Frazier
652 N.E.2d 1000 (Ohio Supreme Court, 1995)
Shemo v. Mayfield Heights
722 N.E.2d 1018 (Ohio Supreme Court, 2000)
State v. Frazier
1995 Ohio 235 (Ohio Supreme Court, 1995)
Shemo v. Mayfield Hts.
2000 Ohio 258 (Ohio Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Gte Telephone Oper. v. Jh Reinforcing, Unpublished Decision (5-20-2002), Counsel Stack Legal Research, https://law.counselstack.com/opinion/gte-telephone-oper-v-jh-reinforcing-unpublished-decision-5-20-2002-ohioctapp-2002.