Gte Southwest v. Pub. Util. Com'n of Texas

37 S.W.3d 546
CourtCourt of Appeals of Texas
DecidedMarch 15, 2001
Docket03-00-00551-CV
StatusPublished

This text of 37 S.W.3d 546 (Gte Southwest v. Pub. Util. Com'n of Texas) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gte Southwest v. Pub. Util. Com'n of Texas, 37 S.W.3d 546 (Tex. Ct. App. 2001).

Opinion

37 S.W.3d 546 (2001)

GTE SOUTHWEST INCORPORATED, Appellant,
v.
PUBLIC UTILITY COMMISSION OF TEXAS, Appellee.

No. 03-00-00551-CV.

Court of Appeals of Texas, Austin.

February 15, 2001.
Rehearing Overruled March 15, 2001.

Amanda Atkinson Cagle, Asst. Atty. Gen., Austin, for appellee.

Celina Romero, Clark, Thomas & Winters, Austin, for appellant.

Before Justices KIDD, B.A. SMITH and PURYEAR.

BEA ANN SMITH, Justice.

GTE Southwest Incorporated (GTE) sought judicial review of a final order issued by the Public Utility Commission. MCI Communications Corporation (successor to MFS Communications, Inc.) and MCI WorldCom Communications, Inc. (successor to WorldCom Technologies, Inc.) intervened in the suit to defend the order.[1] GTE appeals from a trial-court *547 judgment that affirms the order. We vacate the trial court's holding that GTE is aggrieved by the Commission's order and dismiss the suit for judicial review.

THE CONTROVERSY

The underlying dispute concerns an interconnection agreement between GTE, an incumbent local telephone exchange company, and MFS, a new entrant in the local exchange telecommunications market. Such agreements are crucial for new entrants to compete in the local telephone market. Both federal and state laws have been enacted to promote competition in local telephone markets and to require interconnection and procedures for negotiating and enforcing such agreements. See Federal Telecommunications Act (FTA) of 1996, 47 U.S.C. §§ 251-53 (Supp.2000); Public Utility Regulatory Act (PURA), Tex. Util.Code Ann., §§ 60.121-.128 (West 1998).

In September 1996, GTE and MFS entered into an interim interconnection agreement. The agreement contemplated a final agreement, but at the time of this dispute one has not been executed. Furthermore, the parties did not comply with the federal procedures set forth in the FTA when they inadvertently failed to seek the Commission's approval of their interim agreement. See 47 U.S.C. § 252(e). This, however, did not prevent them from successfully operating under the agreement for three years. But when a dispute over terms of the agreement arose, this failure to seek Commission approval became problematic.

In May 1999, MFS filed its first complaint with the Commission in Docket No. 20870, alleging that GTE had breached the interim agreement by failing to comply with reciprocal compensation provisions for terminating local traffic.[2] The Commission dismissed the complaint without prejudice, ruling that it lacked jurisdiction to consider a dispute arising under an agreement that it had not approved. See Tex. Pub. Util. Comm'n, Arbitration Award (Dismissing Complaint), Docket No. 20870 (June 18, 1999).

In July 1999, MFS initiated a second proceeding in Docket No. 21088, seeking the Commission's approval of the interconnection agreement after the fact, presumably so the Commission could then assert its jurisdiction to resolve the parties' contractual dispute. GTE refused to join in the application for approval, saying the agreement was no longer in the public interest. GTE asked the Commission to dismiss MFS's application on the grounds that GTE's joinder was necessary before the Commission could approve the agreement. The administrative law judge certified this question to the Commission: Can the Commission approve an agreement, even if a signatory party does not support its approval?

The Commission considered the unique circumstances of the dispute: an agreement that was supported by both parties when it was signed; an agreement that was intended to govern the parties' dealings for a short time until a final agreement was reached but that had in fact been in effect for three years; and the parties' inadvertent failure to seek the Commission's approval for the agreement (it "fell between the proverbial cracks"[3]). *548 The Commission then declined to answer the certified issue and reversed its earlier decision in Docket No. 20870 that it lacked jurisdiction to settle this dispute. Referring to the unique facts outlined above, the Commission found that although the parties had failed to comply with the FTA's requirement that the Commission approve the interim agreement, the Commission nevertheless had jurisdiction to resolve the dispute under state law because PURA does not require the Commission's prior approval of the agreement to vest the Commission with authority to review these agreements. The Commission then entered its final order in Docket No. 21088, dismissing as moot MFS's application for approval of the interim agreement. See Tex. Pub. Util. Comm'n, Order, Docket No. 21088 (Jan. 13, 2000). It is from that order that GTE brought its suit for judicial review.

Subsequently, MFS filed a third complaint in Docket No. 21706 seeking the reciprocal compensation it claimed for termination of internet service provider calls under the interim agreement. In December 2000, the Commission awarded MFS approximately $10 million in compensation under the interim agreement. GTE has filed suit in district court for judicial review of that order in Docket No. 21706. That contractual dispute, including the issue of the Commission's authority to hear the dispute under state law, is not before us today.

This cause concerns only the dismissal of MFS's application for approval of the interim agreement. We hold that because the Commission granted the relief that GTE sought by dismissing MFS's application, GTE is not an aggrieved party and is thus not entitled to seek judicial review of the Commission's final order in Docket No. 21088.

AGGRIEVED PARTY

The Administrative Procedure Act (APA) grants judicial review of an agency decision to a party "who has exhausted all administrative remedies available within a state agency and who is aggrieved by a final decision" of the agency. Tex. Gov't Code Ann. § 2001.171 (West 2000) (emphasis added). This Court has previously held that one must be aggrieved by the final order and not merely by an underlying finding or conclusion to have standing to seek judicial review of that order. See Champlin Exploration, Inc. v. Railroad Comm'n, 627 S.W.2d 250, 252 (Tex.App.-Austin 1982, writ ref'd n.r.e.). In that decision, we rejected Champlin's attempt to "maintain an appeal in this Court for the sole purpose of striking findings and conclusions with which it does not agree." Id. Subsequently, we followed this ruling in C.O.N.T.R.O.L. v. Sentry Envtl., L.P., 916 S.W.2d 677, 679 (Tex.App.-Austin 1996, writ denied), holding that an appellant who prevailed in getting the agency to deny an application for a solid-waste permit was not "aggrieved" because the agency chose to deny the permit on a ground different than the one appellant had urged. "[A]ppellants' substantial rights do not include the right to mold an agency determination such that it will better thwart future permit applications...." Id. at 679-80. We are unable to distinguish GTE's status as an aggrieved party from that of the appellants in Champlin and C.O.N.T.R.O.L.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Champlin Exploration, Inc. v. Railroad Commission
627 S.W.2d 250 (Court of Appeals of Texas, 1982)
GTE Southwest Incorporated v. Public Utility Commission of Texas
37 S.W.3d 546 (Court of Appeals of Texas, 2001)
C.O.N.T.R.O.L. v. Sentry Environmental, L.P.
916 S.W.2d 677 (Court of Appeals of Texas, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
37 S.W.3d 546, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gte-southwest-v-pub-util-comn-of-texas-texapp-2001.