GSL Holdings, LLC v. Lyon Township

CourtDistrict Court, E.D. Michigan
DecidedJanuary 9, 2023
Docket2:21-cv-11664
StatusUnknown

This text of GSL Holdings, LLC v. Lyon Township (GSL Holdings, LLC v. Lyon Township) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GSL Holdings, LLC v. Lyon Township, (E.D. Mich. 2023).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MICHIGAN SOUTHERN DIVISION

GSL HOLDINGS, LLC,

Plaintiff, v. Case No. 21-11664 Honorable Victoria A. Roberts THE CHARTER TOWNSHIP OF LYON, et al.,

Defendants. /

ORDER GRANTING IN PART AND DENYING IN PART DEFENDANTS’ MOTION FOR SUMMARY JUDGMENT [ECF No. 46] GSL Holdings, LLC (“GSL”), a real estate developer, filed suit against Lyon Township and John Dolan (“Dolan”) for allegedly preventing it from developing a real estate project. GSL alleges violations of: (1) equal protection; (2) due process; (3) the First Amendment; and (4) Michigan’s Freedom of Information Act (“FOIA”). Before the Court is Defendants’ motion for summary judgment. The Court held a hearing on December 12, 2022. Because GSL fails to establish a genuine dispute of material fact in its equal protection and due process claims, the Court GRANTS the motion on these issues. The Court DENIES Defendants’ motion on GSL’s First Amendment and FOIA claims. 1 II. FACTUAL BACKGROUND GSL owns approximately 6.2 acres of property in Lyon Township. In

November 2020, GSL planned to build a structure on the property (the “Project”) to lease to prospective tenant Moba Americas, Inc. (“Moba”). GSL says that during a pre-application meeting on November 12,

2020, Township representatives assured it that the Township would do what it could to help GSL obtain construction approval for the Project as soon as reasonably possible. After that meeting, GSL entered into a lease agreement with Moba. Under the agreement, Moba needed to take

occupancy and begin operations by October 1, 2021. The subsequent chronology of events is as follows. A. 2021 Events

During a Township meeting on January 11, 2021, the Township Planning Commission approved the site plan for the Project. A Township ordinance required GSL to obtain a septic permit from the Oakland County Health Division (“OCHD”) before the Township could

issue GSL the necessary building permits to begin construction on the Project. Due to issues with OCHD, GSL could not obtain the necessary septic permit by March of 2021.

On March 8, 2021, GSL representative Maria D’Agostini emailed 2 Township officials expressing the need for the Project to proceed expeditiously. She requested a conference call with department heads to

discuss moving the Project forward despite the lack of all required permits. At the end of the email, D’Agostini wrote: “I have also copied the Board of Trustees on this email should their participation be required.” [ECF No. 30-

8, PageID.1108-09]. On March 9, 2021, a Township attorney responded, stating: Maria, Please do not communicate directly with the members of the Township Board in this fashion. It is inappropriate.

In addition, there is a process involved in any development and every developer believes that they should have their plans expedited in some fashion. Your veiled threats do not make the process go any faster or smoother.

I understand you have been working with the Township administration on moving this forward. That is the correct way to proceed.

Carol

[ECF No. 30, PageID.1050]. GSL says that after this email exchange, the Township began a pattern of delaying construction on the Project, despite its knowledge that Moba needed to begin operations by October 1, 2021. On March 10, 2021, a Township representative emailed another 3 Township representative, stating: “Maria went too far on that email, copying the entire board. BS!! I was literally on the phone with the Building

Dept begging them to take the plans when she sent that bull!” [ECF No. 15-18, PageID.2396]. On March 31, 2021, GSL “received notice that the building permit

was ready to be picked up from the Township offices . . .” [ECF No. 30, PageID.1052-3]. 5 days later on April 5, 2021, the Township building coordinator emailed D’Agostini, stating that “[p]er John Dolan [a defendant in this

action], it has been decided not to issue the building permit until after your utility Pre-Con.” [ECF No. 30-15, PageID.1132]. On April 6, 2021, D’Agostini replied to the email, expressing

confusion that the Township decided not to issue the building permit when it had already agreed to do so the previous week. On April 7, 2021, another Township representative responded to D’Agostini:

Maria,

Per our discussion, the Building Department will not issue any building permits until after the Utility Pre-Con meeting is held. Please send us your permits as you receive them and once all of the required items are submitted on the approved engineering letter (for a Utility Pre-con) we will schedule it. 4 [ECF No. 30-17, PageID.1137].

The same day, D’Agostini replied: Hi Leslie: I did reach out to the building department about the possibility of footing approval. That would at least buy us the time we need to get our septic approval. I expect to have our Road commission permits this week.

We tentatively have our footing contractor scheduled for the week of April 19. We meet with our contractor today to discuss schedule. If we cannot stay on track with footings this project will be severely delayed and will likely kill the Moba deal. I know I may seem like a pest but we are clearly trying to do whatever we can to keep this project on track. Your assistance throughout this whole thing has been appreciated. Hopefully the Township will reconsider.

[ECF No. 30-18, PageID.1142]. A few minutes later, the Township representative responded: “Maria, [t]he Building Dept has been pretty clear. No building permits until a utility pre-con.” Id. at PageID.1141 (underline emphasis in original). On April 29, 2021, GSL says that Dolan informed it that the Township would release the building permits prematurely (i.e., before GSL obtained the necessary septic permit and held the utility “pre-con” meeting) only if GSL agreed to a “hold harmless” agreement. A hold harmless is an agreement between parties that states that one party will not hold the other party liable for the risk of taking a certain action. On May 3, 2021, an attorney for the Township sent GSL a proposed 5 hold harmless agreement. GSL says that the proposed agreement “include[d] unjustified onerous and burdensome language such as

requiring plaintiff to install a multi-million-dollar sanitary sewer for the entire Lyon Industrial Research Center subdivision if plaintiff would not be able to obtain a [sic] Onsite Sewage Disposal System Permit, among other

issues.” [ECF No. 30, PageID.1056-7]. GSL refused to sign the agreement, protesting this hold harmless language. GSL also says that it was not permitted to connect to the Township’s sanitary sewer line from the rear of its property, although Township

engineering staff previously informed it that such a connection could be made. At the time, Township policy expressed a preference for connections at the front of a developer’s lot, but it contained no provision

that such a connection was mandatory. After this litigation began, the Township changed its Design and Construction Standards to explicitly provide that sanitary sewer line connections could only be made from the front of a lot.

On May 10, 2021, Township representative Carol Rosati emailed GSL representative Emily Kunath: . . .

For the record, as a final attempt to once again assist you with the problem you created, the Township agreed to consider a Hold 6 Harmless Agreement. The Township is under no obligation whatsoever to issue the permits you requested as you have not received all required approvals to be entitled to those permits. Nonetheless, I sent you a proposed agreement. Your response was to assert that the agreement was onerous. However, the terms of the agreement were mandatory for the Township to consider allowing you to prematurely proceed with construction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Adickes v. S. H. Kress & Co.
398 U.S. 144 (Supreme Court, 1970)
Board of Regents of State Colleges v. Roth
408 U.S. 564 (Supreme Court, 1972)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Rondigo, L.L.C. v. Township of Richmond
641 F.3d 673 (Sixth Circuit, 2011)
Seguin v. City Of Sterling Heights
968 F.2d 584 (Sixth Circuit, 1992)
Gene Autrey Adams v. Paul Metiva
31 F.3d 375 (Sixth Circuit, 1994)
Thaddeus-X and Earnest Bell, Jr. v. Blatter
175 F.3d 378 (Sixth Circuit, 1999)
Ronald Loesel v. City of Frankenmuth
692 F.3d 452 (Sixth Circuit, 2012)
EJS Properties, LLC v. City of Toledo
698 F.3d 845 (Sixth Circuit, 2012)
Alexander v. CareSource
576 F.3d 551 (Sixth Circuit, 2009)
Braun v. Ann Arbor Charter Township
519 F.3d 564 (Sixth Circuit, 2008)
Clay v. United Parcel Service, Inc.
501 F.3d 695 (Sixth Circuit, 2007)
Schubiner v. West Bloomfield Township
351 N.W.2d 214 (Michigan Court of Appeals, 1984)
Village of Willowbrook v. Olech
528 U.S. 562 (Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
GSL Holdings, LLC v. Lyon Township, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gsl-holdings-llc-v-lyon-township-mied-2023.