GSL Holdings, LLC v. Lyon Township

CourtDistrict Court, E.D. Michigan
DecidedOctober 1, 2021
Docket2:21-cv-11664
StatusUnknown

This text of GSL Holdings, LLC v. Lyon Township (GSL Holdings, LLC v. Lyon Township) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GSL Holdings, LLC v. Lyon Township, (E.D. Mich. 2021).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MICHIGAN SOUTHERN DIVISION

GSL HOLDINGS, LLC,

Plaintiff, v. Case No. 21-11664 Honorable Victoria A. Roberts THE CHARTER TOWNSHIP OF LYON, et al.,

Defendants. ______________________________/

ORDER: (1) SUSTAINING DEFENDANTS’ OBJECTIONS TO EVIDENTIARY HEARING [ECF No. 23]; (2) CANCELLING OCTOBER 5, 2021 EVIDENTIARY HEARING; AND (3) DENYING PLAINTIFF’S MOTION FOR TEMPORARY RESTRAINING ORDER OR PRELIMINARY INJUNCTION [ECF No. 4]

I. INTRODUCTION AND BACKGROUND

GSL Holdings, LLC (“Plaintiff”) owns approximately 6.2 acres of property (the “Property”) in Lyon Township (the “Township”). In November 2020, Plaintiff began planning to build a structure on the Property (the “Project”) to lease to Moba Americas, Inc. (“Moba”). Plaintiff says that during a pre-application meeting between representatives of Plaintiff and the Township on November 12, 2020, Township representatives assured that the Township would do what it could to help Plaintiff obtain construction approval for the Project as soon as reasonably possible. After that meeting, Plaintiff entered into a lease agreement for the Property with Moba. Under the agreement, Moba needed to take occupancy and begin operations by October 1, 2021. During a Township meeting on January 11, 2021, the Township

Planning Commission approved the site plan for the Project. Plaintiff says that after this meeting, the Township began a pattern of delaying the beginning of construction, despite its knowledge that Moba needed to begin

operations by October 1, 2021. Ultimately, Plaintiff did not meet all requirements under the Township permit ordinance to receive shell and foundation construction permits by the date that would allow Moba to take occupancy in October 2021. Moba

terminated its lease with Plaintiff on May 4, 2021 and found a different property to lease. Plaintiff filed suit against the Township and Township Supervisor,

John Dolan (“Defendants”) on July 18, 2021. It alleges violation of: (1) equal protection rights; (2) due process rights; (3) First Amendment rights; and (4) Michigan’s Freedom of Information Act, M.C.L. 15.231 et seq. Plaintiff seeks injunctive relief and $18 million in damages – which it says is

its lost income from the lease with Moba. Before the Court are: (1) Plaintiff’s motion for a temporary restraining order and/or preliminary injunction [ECF No. 4] – which the Court set for an

2 October 5, 2021 evidentiary hearing; and (2) Defendants’ objections to evidentiary hearing [ECF No. 23]. The motion and objections are fully briefed.

A hearing is unnecessary. The Court SUSTAINS Defendants’ objections and CANCELS the evidentiary hearing. For the reasons below, the Court DENIES Plaintiff’s motion for

temporary restraining order and/or preliminary injunction. II. LEGAL STANDARD

When determining whether to issue a temporary restraining order or preliminary injunction, the Court must consider four factors: (1) whether the movant has a strong likelihood of success on the merits; (2) whether the movant will suffer irreparable harm absent the injunction; (3) whether the injunction would cause substantial harm to others; and (4) whether issuing

the injunction would serve the public interest. Overstreet v. Lexington- Fayette Urb. Cty. Gov’t, 305 F.3d 566, 573 (6th Cir. 2002). These factors are not prerequisites to issuing a preliminary injunction; they are factors the Court must balance against each other. Id.

A preliminary injunction is an extraordinary remedy that will only be granted if Plaintiff shows that circumstances clearly demand it. Id. “The purpose of a preliminary injunction is simply to preserve the status quo;

3 thus, findings of fact and conclusions of law made by a district court in granting a preliminary injunction are not binding at a trial on the merits.” United States v. Edward Rose & Sons, 384 F.3d 258, 261 (6th Cir. 2004).

III. DISCUSSION

Plaintiff’s motion is based only on its first two claims (i.e., equal protection and due process violations). Plaintiff asks the Court for an order requiring Defendants to issue building permits for its Project, allowing it to begin construction of a foundation and building shell on its Property. Plaintiff says Defendants wrongfully prevented it from developing the Project and caused it to miss the October 2021 deadline for Moba to take

occupancy, which resulted in it losing the lease with Moba. However, contrary to Plaintiff’s allegations that Defendants caused it to miss the October 2021 deadline, facts show that the Township did

everything it could to accommodate Plaintiff’s attempt to meet that deadline – including expediting its review process at Plaintiff’s request by engaging in a simultaneous engineering/Planning Department review and review in the Building Department.

In reality, despite the Township’s expedited review, the Township did not issue the shell and foundation construction permits because Plaintiff failed to complete all necessary steps for issuance of the permits under the

4 Township Code until just a few days ago. Indeed, until September 27, 2021, Plaintiff had not received a permit to construct an on-site septic system (“Septic Permit”) from Oakland County Health Division (“OCHD”).

Under Section 15-9(c) of the Township Code, Plaintiff was required to submit the Septic Permit to the Township before the Township Engineer could approve Plaintiff’s engineering construction plan. [See ECF No. 1-

29, PageID.249 (“Applicant must submit copies of the documentation from other agencies . . . to the Township Engineer indicating that the plans have received their approval for work . . . prior to the Township Engineer granting any engineering construction plan approval.”)].

Throughout this process, the Township informed Plaintiff that it could not issue building permits until Plaintiff engaged in a utility preconstruction meeting, and that the utility preconstruction meeting could not be held until

after Plaintiff received the Septic Permit from OCHD and provided it to Defendants. [See, e.g., ECF No. 4-12, PageID.394; ECF No. 26-2, PageID.994]. Because Plaintiff failed to receive the Septic Permit, the Township

could not hold the required utility preconstruction meeting or issue the shell and foundation construction permits. In relevant part, Township Code § 15-10 provides:

5 Sec. 15-10. – Permits/construction. (a) A preconstruction meeting will not be scheduled until all of the required items listed in the engineering approval letter are received by the township engineer.

(b) When engineering construction plans have been approved, the applicant may apply for a building permit from the township building department. The number of permits and any other building issues will be at the discretion of the building official. Prior to the start of construction, the applicant must secure all necessary permits from other agencies as applicable to the project and attend a preconstruction meeting.

* * *

(e) All other permits and payment of associated fees required to perform the work shall be the responsibility of the applicant and/or his designee. No construction may commence until permits, as applicable to the project are secured from the appropriate agencies.

[ECF No. 1-29, PageID.249-50 (emphasis added)]. Furthermore, Sections 15-2(h) and (i) of the Township Code provide: (h) Permits—Jurisdiction—Notification.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rondigo, L.L.C. v. Township of Richmond
641 F.3d 673 (Sixth Circuit, 2011)
Seguin v. City Of Sterling Heights
968 F.2d 584 (Sixth Circuit, 1992)
Ronald Loesel v. City of Frankenmuth
692 F.3d 452 (Sixth Circuit, 2012)
EJS Properties, LLC v. City of Toledo
698 F.3d 845 (Sixth Circuit, 2012)
Braun v. Ann Arbor Charter Township
519 F.3d 564 (Sixth Circuit, 2008)
Schubiner v. West Bloomfield Township
351 N.W.2d 214 (Michigan Court of Appeals, 1984)
Village of Willowbrook v. Olech
528 U.S. 562 (Supreme Court, 2000)
Daily Services, LLC v. Tracy Valentino
756 F.3d 893 (Sixth Circuit, 2014)
Taylor Acquisitions, L.L.C. v. City of Taylor
313 F. App'x 826 (Sixth Circuit, 2009)
Tuscola Wind III, LLC v. Almer Charter Twp.
327 F. Supp. 3d 1028 (E.D. Michigan, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
GSL Holdings, LLC v. Lyon Township, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gsl-holdings-llc-v-lyon-township-mied-2021.