GSF ENERGY, LLC v. Padron

355 S.W.3d 700, 2011 Tex. App. LEXIS 4250, 2011 WL 2184368
CourtCourt of Appeals of Texas
DecidedJune 2, 2011
Docket01-09-00622-CV
StatusPublished
Cited by1 cases

This text of 355 S.W.3d 700 (GSF ENERGY, LLC v. Padron) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GSF ENERGY, LLC v. Padron, 355 S.W.3d 700, 2011 Tex. App. LEXIS 4250, 2011 WL 2184368 (Tex. Ct. App. 2011).

Opinion

OPINION ON REHEARING

EVELYN V. KEYES, Justice.

Both appellant and appellees have filed motions for rehearing. Appellees have also filed a motion for en banc reconsideration. We grant rehearing, withdraw our previous opinion, deny appellant’s and ap-pellees’ requested relief, and dismiss as moot the motion for en banc reconsideration. 1 Our judgment of February 10, 2011 remains unchanged.

*703 This appeal arises out of the death of Adan Padrón, who was killed when debris fell on him while he was cleaning the inside of a processing-plant tank. Padron’s wife and children sued the plant operator and Padron’s employer for negligence and premises liability. 2 We must decide whether the plant operator exercised or retained control over the manner in which Padron’s employer, an independent contractor, performed its work such that the plant operator can be liable for Padron’s death. In addition, we must determine whether the trial court erred in submitting the jury charge. We reverse the trial court’s judgment and remand the case for further proceedings.

Background

Appellant GSF Energy, LLC operates a landfill-gas processing plant on McCarty Road in Houston. The plant gathered gas produced from wells drilled into a landfill owned by BFI and processed the landfill gas into saleable natural gas. The components of the plant had been previously used as a plant at a landfill in California before being moved to McCarty Road. There was conflicting testimony at trial regarding whether the components of the plant were owned by GSF or LFG Management Services, L.L.C.

On a daily basis, the plant takes in about 9 million cubic feet of landfill gas and produces about 4 million cubic feet of sale-able natural gas. As part of the gas processing, the landfill gas is filtered through a pressurized tank filled with “iron sponge.” The tank is about 15 feet tall. Iron sponge is made up of wood chips impregnated with iron oxide, and it removes hydrogen sulfide from the landfill gas. Over time, iron sponge becomes spent and no longer removes hydrogen sulfide from the gas passing through the tank. The iron sponge must then be replaced, generally two to three times per year. The iron sponge clumps together into hard pieces and sometimes adheres to the walls of the tanks. GSF has known since 1986 that iron sponge adheres to the walls of the tanks. The McCarty Road plant has two iron-sponge tanks, or vessels, which are known as V321A and V321B. The accident that killed Adan Pa-drón occurred in V321B.

Beginning in 2001, GSF hired CES Environmental Services to periodically come to the plant to clean out the iron-sponge tanks. CES’s employees would clean one of two tanks, while the other tank remained in operation. CES’s employees cleaned the tanks by “hydroblasting” the inside of the tank with high-pressure water. They would climb on top of the tank and spray down into the tank through a “manway” that had been unbolted and removed. The hydroblasting breaks up the iron sponge, which is then vacuumed out through a hose.

On February 16, 2005, three CES employees, Adan Padrón, Jose Ramirez, and Joe Carrillo, went to the McCarty Road plant to clean V321B. The last time that V321B had been cleaned was a year before. Carrillo received a “general and hazardous safety work permit” from James Jannise, who is an “operator” for GSF. Part of Jannise’s job is to assist with filling the iron — sponge tanks. The purpose of the permit was to ensure that GSF had properly shut down the tank so the area would be safe to work in, and it was required to be issued as a part of GSF’s work permit program. Michael Sawyer, *704 an independent process safety consultant, testified at trial that GSF’s work permit indicated that only two of the four valves on the tank had been closed, which was improper.

Padrón, Ramirez, and Carrillo spent four days hydroblasting the tank from the top. On February 21, Carrillo told Jan-nise that there was still some iron sponge they had not been able to remove through hydroblasting and that “we had to make tank entry” in order to remove the remainder. The next morning, Jannise told Carrillo that he had talked to Gary Valdez, the GSF McCarty Road plant' manager, and that Valdez wanted the tank fully cleaned out. Valdez then came out to the tank and Carrillo told him that the hydroblasting was not working. At trial, Carrillo testified that Valdez never told him that the CES employees had to go inside the tank from the bottom, but he was impeached with his prior deposition testimony in which Carrillo said Valdez directed CES to carry out the work by having workers enter the tank. During his deposition, Carrillo stated he felt that he could not say “no” to Valdez. Valdez acknowledged he had a'conversation with Carrillo about entering the tank to clean it, but Valdez did not testify that he told Carrillo to enter.

Carrillo testified that Valdez told him what tools and equipment they would need to work inside the tank. Carrillo said that Valdez told him to use nonsparking, brass tools so the CES workers would not create a spark that could accidentally ignite the combustible atmosphere inside the tank. Marlin Moser, a CES vice president, also told Carrillo to use brass tools. Because the CES workers were entering the tank, Valdez expanded the project by telling Carrillo to remove river rock and a broken screen from the bottom of the tank. Valdez then called CES’s president, Matt Bowman, and discussed the need to enter the tank, and Bowman said he would send a “six-pack” of breathing air out to the plant.

GSF’s work permit program required a “confined space safety work permit” to be issued before anyone entered the tank. Valdez testified that the CES workers could not enter the tank until he approved such a permit. Carrillo filled out a CES confined-space entry permit authorizing entry into the tank. The preprinted language of the permit stated, “Entry cannot be approved if any squares are marked in the ‘No’ column.” Even though two boxes were checked “no,” indicating the absence of required communications equipment and other safety equipment, Valdez nonetheless approved the permit.

Carrillo and Padrón entered the tank and took turns using the pick to break the iron sponge into chunks, while the other person used a shovel to pile the debris into a pile to be vacuumed out. Carrillo testified that he had never before used a pick or shovel to clean iron sponge out of a tank and that the sponge in the tank was as “hard as a rock.” Within 15 to 30 minutes of their entering the tank, a huge chunk of iron sponge fell, hit the ladder, and bounced off and hit Padrón. Carrillo tried to lift the sponge, but it was too heavy.

After Carrillo was pulled from the tank, he called Moser, who went to the McCarty Road plant. Moser and Ramirez entered the tank and used an axe to break up the iron sponge that had fallen on Padrón, who was then taken in an ambulance to the hospital. Padrón was later pronounced dead, and an autopsy determined that the cause of death was blunt-force injuries to the head and neck.

Moser was asked for his explanation of why the iron sponge fell from the tank’s roof. Moser testified without objection as to hearsay that Carrillo told him the following:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
355 S.W.3d 700, 2011 Tex. App. LEXIS 4250, 2011 WL 2184368, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gsf-energy-llc-v-padron-texapp-2011.