Groveland Water and Sewer Dist v. City of Blackfoot

CourtIdaho Supreme Court
DecidedMarch 3, 2022
Docket48654
StatusPublished

This text of Groveland Water and Sewer Dist v. City of Blackfoot (Groveland Water and Sewer Dist v. City of Blackfoot) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Groveland Water and Sewer Dist v. City of Blackfoot, (Idaho 2022).

Opinion

IN THE SUPREME COURT OF THE STATE OF IDAHO

Docket No. 48654

GROVELAND WATER and SEWER, ) DISTRICT (GWSD), governmental ) Subdivision of the State of Idaho ) ) Boise, January 2022 Term Plaintiff-Respondent, ) ) Opinion Filed: March 3, 2022 v. ) ) Melanie Gagnepain, Clerk CITY OF BLACKFOOT, a municipal, ) Corporation ) ) Defendant-Appellant. ) ____________________________________)

Appeal from the District Court of the Seventh Judicial District of the State of Idaho, Bingham County. Darren B. Simpson, District Judge.

The decisions of the district court are affirmed.

Garrett H. Sandow, Blackfoot, attorney for Appellant. Garrett H. Sandow argued.

Manwaring Law Office, PA, Idaho Falls, for Respondent. Kipp L. Manwaring argued. _________________________________ BEVAN, Chief Justice. This case arises from a dispute over provisions in a written contract for sewer drainage and treatment services between Groveland Water and Sewer District (“GWSD”) and the City of Blackfoot (“the City”). The dispute arose when individuals living outside city limits, or entities located outside city limits, but within GWSD, were required to sign a “consent to annex” form in order for the City to agree to connect them to sewer services. The dispute ultimately made its way to district court, where GWSD alleged that the City’s requirement violated GWSD’s jurisdictional sovereignty under Idaho Code section 42-3212. GWSD’s complaint against the City sought: (1) a declaratory judgment, (2) a finding of anticipatory breach of contract; and (3) injunctive relief. On

1 motions from the parties, the district court granted GWSD’s request for preliminary injunction and for partial summary judgment on the anticipatory breach claim. After further motions, the district court granted summary judgment to GWSD on the remaining claims. The City appeals. For the reasons below, we affirm the district court’s decisions. I. FACTUAL AND PROCEDURAL BACKGROUND GWSD is an autonomous governmental entity that owns sewer lines, pumps, lift stations, and connected sewer systems for serving public sewer needs within its territorial district, including area contiguous to its district and lying outside the Blackfoot City limits. GWSD operates as a governmental subdivision of the State of Idaho under Idaho Code, Title 42, Chapter 32, located within Bingham County. The City of Blackfoot is a municipal corporation also located within Bingham County. GWSD’s sewer system is connected to a wastewater treatment plant (“the plant”) jointly owned by GWSD and the City. In February 2012, GWSD and the City entered into a written agreement (“the contract”) for sewer services. Under Section I.1.A of the contract, the City agreed to process and treat all raw sewage collected and transmitted through GWSD’s system to the plant. Under Section II.5 of that agreement, GWSD and the City agreed that GWSD would prepare a pre-connection request form (called Addendum B) to notify “both the City and the district, in advance, of any new proposed connections to the systems.” Addendum B also addressed “current fees, collection, and payment of fees.” The contract required that a copy of Addendum B be approved and signed in triplicate by both GWSD and the City before any permits or contracts were issued for connections that would use any part of GWSD’s systems. From February 2012 through April 2019, the City never stated or demanded that a petition for annexation to the City would be required for it to sign the Addendum B Form. Under the contract, GWSD and the City had to meet each year “prior to the 15th day of April” to “discuss fees, number of patrons and any business relating to the working relationship between [GWSD] and the City.” As a result, according to GWSD, the parties met in April 2019 and agreed to update Addendum B, but the City never brought up its intent to require applicants for sewer services in GWSD to execute a petition for annexation to the City. A follow up meeting took place in May 2019 where Addendum B was discussed in detail, resulting in the parties finalizing amendments to the Addendum B form. The amended Addendum

2 B contained no reference to consent to annexation being required as a condition for approval by the City. In May 2019, a developer for Wildflower Meadows subdivision applied for sewer services through GWSD. The developer completed Addendum B and took the form to the City for approval. The City, however, refused to sign the form. Instead, the City presented the developer with a petition for annexation and told the developer that the petition had to be signed as a precondition to the City approving the application for connection of sewer services in GWSD. When GWSD contacted the City to ask about this condition, the City claimed the consent form was always a requirement for connections to City services but explained that the City had never demanded enforcement in the past. GWSD immediately gave notice to the City that it had breached the terms of the contract and requested the City cease its demand for a petition of annexation as part of its approval for hookups to GWSD’s sewer system. The City responded in a letter, suggesting the consent forms were “commonly used by cities throughout Idaho, and other states[,]” and that such a form was “required by City Code.” The City also relied on a portion of the contract in support of its newly required annexation form. After this exchange, both the Snake River School District and County Haven Homeowners Association applied for services with GWSD, but when these organizations presented Addendum B to the City, both were also informed that signed petitions for annexation were required as a precondition to approving the connections. Because of the ongoing conflict, GWSD filed for pre-litigation mediation pursuant to the contract. The mediation proved unsuccessful. GWSD then filed a complaint seeking: (1) a declaratory judgment declaring the 2019 version of Addendum B as the only approval form required to connect and receive sewer services; (2) a finding of anticipatory breach of contract by the City; and (3) injunctive relief preventing the City from requiring a petition for annexation as part of its contractual approval of connections to GWSD’s sewer system. The City brought a motion to dismiss on the basis that GWSD lacked standing to pursue its claims and GWSD responded with a motion for a preliminary injunction. There is a transcript of the hearing that took place on both motions in November 2019. During that hearing the district court noted that because of “the subsequent pleadings [and] . . . affidavits filed,” the court would “convert [the motion to

3 dismiss] to a summary judgment hearing.” The district court asked both counsel for the City and for GWSD if they had any disagreement with proceeding in the matter and both consented. The district court first granted GWSD’s request for a preliminary injunction, along with granting partial summary judgment for GWSD on its anticipatory breach of contract claim. The City then moved for reconsideration, which the district court denied. GWSD then moved for summary judgment on its remaining claim for damages on the anticipatory breach claim. According to the district court’s opinion granting summary judgment to GWSD, there was a motion to strike made by the City. The district court granted the City’s motion to strike in part and granted summary judgment on GWSD’s damage claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Knox v. STATE EX REL. OTTER
223 P.3d 266 (Idaho Supreme Court, 2009)
Spencer v. Jameson
211 P.3d 106 (Idaho Supreme Court, 2009)
Friends of Minidoka v. Jerome County
281 P.3d 1076 (Idaho Supreme Court, 2012)
Randall v. Ganz
537 P.2d 65 (Idaho Supreme Court, 1975)
Miles v. Idaho Power Co. Ex Rel. Evans
778 P.2d 757 (Idaho Supreme Court, 1989)
State v. Flint
761 P.2d 1158 (Idaho Supreme Court, 1988)
Belk v. Martin
39 P.3d 592 (Idaho Supreme Court, 2001)
Gunter v. Murphy's Lounge, LLC
105 P.3d 676 (Idaho Supreme Court, 2005)
Schneider v. Howe
133 P.3d 1232 (Idaho Supreme Court, 2006)
Van Valkenburgh v. Citizens for Term Limits
15 P.3d 1129 (Idaho Supreme Court, 2000)
Bach v. Bagley
229 P.3d 1146 (Idaho Supreme Court, 2010)
Campbell v. Parkway Surgery Center, LLC
354 P.3d 1172 (Idaho Supreme Court, 2015)
Tiller White, LLC v. Canyon Outdoor Media, LLC
374 P.3d 580 (Idaho Supreme Court, 2016)
Silver Creek Seed, LLC v. Sunrain Varieties, LLC
385 P.3d 448 (Idaho Supreme Court, 2016)
Tracy Tucker v. State of Idaho
394 P.3d 54 (Idaho Supreme Court, 2017)
Christina J. Greenfield v. Ian D. Smith
395 P.3d 1279 (Idaho Supreme Court, 2017)
Lunneborg v. My Fun Life, Corp.
421 P.3d 187 (Idaho Supreme Court, 2018)
Taylor v. Taylor
422 P.3d 1116 (Idaho Supreme Court, 2018)
Rencher/Sundown LLC v. Pearson
454 P.3d 519 (Idaho Supreme Court, 2019)
Oaic Commercial Assets, L.L.C. v. Stonegate Village, L.P.
234 S.W.3d 726 (Court of Appeals of Texas, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
Groveland Water and Sewer Dist v. City of Blackfoot, Counsel Stack Legal Research, https://law.counselstack.com/opinion/groveland-water-and-sewer-dist-v-city-of-blackfoot-idaho-2022.