GROVE ISLE ASSOCIATION, INC. v. JERRY M. LINDZON

District Court of Appeal of Florida·Decided November 10, 2022·No. 22-0913·Published

Opinion

Third District Court of Appeal State of Florida

Opinion filed November 10, 2022.

Not final until disposition of timely filed motion for rehearing.

No. 3D22-913

Lower Tribunal No. 20-15859

Grove Isle Association, Inc., Appellant,

vs.

Jerry M. Lindzon,

Appellee.

An Appeal from a non-final order from the Circuit Court for Miami-Dade County, David C. Miller, Judge.

Law Offices of Geoffrey B. Marks, and Geoffrey B. Marks, for appellant.

Halpern Rodriguez, LLP, and Priscilla S. Zaldivar and Marc A. Halpern, for appellee.

Before EMAS, LINDSEY and GORDO, JJ.

EMAS, J.

INTRODUCTION Grove Isle Association, Inc. (the Association), appeals a nonfinal order granting Jerry M. Lindzon’s motion for leave to amend his complaint to assert a claim for punitive damages. 1 Because Lindzon failed to satisfy the requirements for establishing entitlement to assert a claim for punitive damages against a corporation pursuant to section 768.72, Florida Statutes (2022), the trial court erred in granting Lindzon’s motion to amend, and we therefore reverse.

FACTUAL AND PROCEDURAL BACKGROUND Lindzon owns a unit at Grove Isle Condominium. He alleges his unit suffered severe water damage due to a failing roof assembly. After the Association allegedly ignored his complaints about the failing roof, Lindzon sued the Association for violation of the Declaration of Condominium and under section 718.113(1) for failing to maintain the common elements at Grove Isle.

1 Florida Rule of Appellate Procedure 9.130 authorizes interlocutory appeals of certain enumerated nonfinal orders. In 2022, the Florida Supreme Court amended that rule to add nonfinal orders that “grant or deny a motion for leave to amend to assert a claim for punitive damages.” Fla. R. App. P. 9.130(a)(3)G. See In re Amendment to Florida Rule of Appellate Procedure 9.130, 345 So. 3d 725, 726 (Fla. 2022).

The roof was repaired during the pending litigation. However, when Lindzon began to repair the damage to his own unit, his contractor discovered exposed rebar. This discovery, and the parties’ attempt to address the newly discovered damage, led to the underlying motion to amend the complaint to assert a claim for punitive damages. In his amended complaint, Lindzon added counts for negligence and fraudulent misrepresentation, and sought punitive damages. He also described the following sequence of events:

• The reroofing project began in March 2021, after the underlying lawsuit was filed.

• In October 2021, the re-roofing project was completed, and Lindzon hired a contractor to restore his unit.

• In November 2021, Lindzon’s contractor “discovered multiple areas on the common element slab surrounding the Unit with exposed, rusted rebar, spalling and cracked concrete.” Lindzon twice notified the Association about specific areas of damage to the concrete slab, and each time “the Association inspected the Unit.”

• “On January 31, 2022, the Association’s own contractor confirmed that the work to be performed by the Association include[d] repairs to

rebar which require[d] input from a structural engineer and proper permitting.”

• Rodriguez eventually advised Lindzon that work on the slab was set to commence on February 7.

• Days before the work was set to commence, Lindzon requested a copy of the scope of work and permit information. Upon receiving the request, Rodriguez stated: “[i]t’s such a small job that I don’t think it’s [permits] really necessary.”

• When Lindzon insisted on a copy of the scope of work and permit information, Rodriguez canceled the work, stating that “he instructed his contractor to proceed without a permit, and now that Lindzon requested it, the repairs would be significantly delayed.” 2 In sum—and relevant to the asserted punitive damages claim—

Lindzon alleged: “In an effort to save money, the Association was not intending to retain a structural engineer or pull the necessary permits to

2 The email from Rodriguez to Lindzon’s attorney (attached to the motion to amend) specifically stated: “The contractor did not say that a permit is not required. I am the one that told the contractor that in order to expedite this I would not be requiring a permit. [] If you feel that a permit is necessary then we will go ahead and start the process. This process wit[h] the current backlog with the City of Miami due to Covid will delay this repair for a couple of months while a permit is obtained . . . .”

perform the repairs to the slab contrary to the advice of the Association’s own contractor.”

Attached to the motion to amend were the letters to the Association, and the correspondence between the Association contractor and Rodriguez.

Following a hearing, the trial court granted Lindzon’s motion to amend, concluding that “the proffered misrepresentation regarding the lack of need for a building permit, the willful neglect to get a building permit in the face of expert advice to do [so] evidences a willful and wanton disregard of the Plaintiff[‘]s rights and safety.” This appeal followed.

STANDARD OF REVIEW The parties agree that our standard of review is de novo. Tallahassee Mem’l Healthcare, Inc. v. Dukes, 272 So. 3d 824 (Fla. 1st DCA 2019) (reviewing de novo the trial court’s decision of whether a party should be allowed to plead punitive damages); Est. of Williams ex rel. Williams v. Tandem Health Care of Fla., Inc., 899 So. 2d 369, 376 (Fla. 1st DCA 2005). See also E.R. Truck & Equip. Corp. v. Gomont, 300 So. 3d 1230 (Fla. 3d DCA 2020) (Scales, J. concurring).

DISCUSSION AND ANALYSIS The Association contends that (1) Lindzon “failed to meet the requirements of alleging and proving entitlement to pleading a claim for

punitive damages against a corporation”; and (2) because the amended complaint does not allege acts independent of its contractual and statutory claims, amendment to the complaint was barred by the independent tort doctrine. We agree with the Association’s first contention and reverse the order granting leave to amend to assert a claim for punitive damages.3 “Under Florida law, the purpose of punitive damages is not to further compensate the plaintiff, but to punish the defendant for its wrongful conduct and to deter similar misconduct by it and other actors in the future.” Owens– Corning Fiberglas Corp. v. Ballard, 749 So. 2d 483, 486 (Fla. 1999). See also BDO Seidman, LLP v. Banco Espirito Santo Intern., 38 So. 3d 874, 876 (Fla. 3d DCA 2010) (“Punitive damages are a form of extraordinary relief for acts and omissions so egregious as to jeopardize not only the particular plaintiff in the lawsuit, but the public as a whole, such that a punishment—

3 As a result, we do not reach the merits of the second issue raised on appeal by the Association. See Peebles v. Puig, 223 So. 3d 1065, 1069 (Fla. 3d DCA 2017) (“When, as here, a contract has been breached, a tort action lies only for acts independent of those acts establishing the contract's breach”) (citing Ginsberg v. Lennar Fla. Holdings, Inc., 645 So. 2d 490, 494 (Fla. 3d DCA 1994) (“It is well established that breach of contractual terms may not form the basis for a claim in tort. Where damages sought in tort are the same as those for breach of contract a plaintiff may not circumvent the contractual relationship by bringing an action in tort”)); TRG Desert Inn Venture, Ltd. v. Berezovsky, 194 So. 3d 516, 519 n.3 (Fla. 3d DCA 2016) (“Florida's independent tort rule precludes the recovery of punitive damages for a breach of contract claim unless the claimant has asserted a tort independent of the alleged breach of contract.”)

not merely compensation—must be imposed to prevent similar conduct in the future.”)

Free access — add to your briefcase to read the full text and ask questions with AI

GROVE ISLE ASSOCIATION, INC. v. JERRY M. LINDZON, (Fla. Ct. App. 2022).

GROVE ISLE ASSOCIATION, INC. v. JERRY M. LINDZON (GROVE ISLE ASSOCIATION, INC. v. JERRY M. LINDZON) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Estate of Despain v. Avante Group, Inc.
900 So. 2d 637 (District Court of Appeal of Florida, 2005)
Ginsberg v. Lennar Florida Holdings
645 So. 2d 490 (District Court of Appeal of Florida, 1994)
BDO Seidman, LLP v. Banco Espirito Santo International
38 So. 3d 874 (District Court of Appeal of Florida, 2010)
U.S. Concrete Pipe Co. v. Bould
437 So. 2d 1061 (Supreme Court of Florida, 1983)
Owens-Corning Fiberglas Corp. v. Ballard
749 So. 2d 483 (Supreme Court of Florida, 1999)
Holmes v. Bridgestone/Firestone, Inc.
891 So. 2d 1188 (District Court of Appeal of Florida, 2005)
Williams v. Tandem Health Care of Florida
899 So. 2d 369 (District Court of Appeal of Florida, 2005)
Carraway v. Revell
116 So. 2d 16 (Supreme Court of Florida, 1959)
Rodolfo Valladares v. Bank of America Corporation, etc.
197 So. 3d 1 (Supreme Court of Florida, 2016)
TRG Desert Inn Venture, Ltd. v. Berezovsky
194 So. 3d 516 (District Court of Appeal of Florida, 2016)
Peebles v. Puig
223 So. 3d 1065 (District Court of Appeal of Florida, 2017)
Fetlar, LLC v. Suarez
230 So. 3d 97 (District Court of Appeal of Florida, 2017)
KIS GROUP, LLC, ALERION MANAGEMENT GROUP, LLC and RICARDO DEAVILA v. YVES MOQUIN
263 So. 3d 63 (District Court of Appeal of Florida, 2019)
Tallahassee Memorial HealthCare, Inc. v. Cherelle Dukes
272 So. 3d 824 (District Court of Appeal of Florida, 2019)
Coronado Condominium Ass'n v. Corte
103 So. 3d 239 (District Court of Appeal of Florida, 2012)