Groundworx, LLC v. Thomas A. Blanton

234 So. 3d 363
CourtMississippi Supreme Court
DecidedJuly 27, 2017
DocketNO. 2015-CA-00152-SCT
StatusPublished
Cited by1 cases

This text of 234 So. 3d 363 (Groundworx, LLC v. Thomas A. Blanton) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Groundworx, LLC v. Thomas A. Blanton, 234 So. 3d 363 (Mich. 2017).

Opinion

MAXWELL, JUSTICE,

FOR THE COURT:

¶ 1. Groundworx, LLC, appeals the judgment dismissing Groundworx’s breach-of-contract action against the City of Hattiesburg. We review this judgment de novo, employing the same standard as the trial court. Taking Groundworx’s allegations as true, we will affirm dismissal only if it appears beyond doubt that Groundworx will be unable to prove any set of facts to support its claim.

¶ 2. After reviewing .the contract between Groundworx and the City, which Groundworx attached to its complaint, we are left with no doubt that Groundworx’s complaint was properly dismissed' for failure to state a claim. Even when we take all of Groundworx’s allegations as true, Groundworx can cite no contractual provision the City, allegedly breached. Even if Groundworx expended millions of dollars preparing to perform under the contract, it did so before securing the necessary financing to complete the project. And unfortunately for Groundworx, the contract was clear — if Groundworx did not secure financing by a certain date, the City had the right to terminate the contract. So Groundworx can prove no set of facts to show the City breached the contract.

¶ 3. Nor can Groundworx prove the City was liable under a theory of promissory estoppel. Groundworx claims to have reasonably relied on actions ai\d assurances made by City officials. But under Mississippi law, the City can be liable only for actions entered "on its minutes and approved by its mayor. So as a matter of law, Groundworx cannot recover based on unofficial City promises.

¶4. We therefore affirm the judgment dismissing Groundworx’s complaint.

Background Facts 1 and Procedural History

I. City-Groundworx Contract

¶ 5. In 2010, the City’s wastewater system was discovered , to be noncompliant with federal pollution laws. Under order to remedy the problem, the City sought proposals for a land-application treatment system for sewage and wastewater. On November 11, 2013, Groundworx responded *366 with a proposal to construct, operate, and maintain a land-application system.

¶6. After negotiations, the City and Groundworx executed a contract on January 21 and 27, 2014. Under the contract, Groundworx agreed to “design, build, construct, own, operate and maintain the System for the purpose of collecting, treating, storing, transporting, and disposal of the City’s Wastewater .... ” In exchange, the “City unconditionally and irrevocably covenanted] and agree[d] to pay to Ground-worx ... the interest portion of Ground-worx’s Debt Service payments” — along with other significant payments. 2

II. Groundworx’s Attempted Financing

¶ 7. While the City agreed to make payments sufficient to service the debt, it was Groundworx that had to obtain the $147 million to finance the project. And the contract contained a termination provision. It expressly provided, “[i]n the event that Groundworx has not closed its financing for the acquisition and construction of the System by June 2, 2014, either party shall have the right to terminate this Agreement by written notice to the other delivered on or after June 2, 2014, and before the date such financing is closed.”

¶ 8. Before the contract was entered, the City’s mayor sent a letter to the Mississippi Business Finance Corporation (MBFC) in December 2013. This letter explained the City was negotiating with Groundworx “for this public/private project” and. encouraged “MBFC to induce the bonds for Groundworx financing.” City representatives also participated in a written presentation to potential bond insurance agencies in New York City. And the day after the contract was executed, City representatives traveled to New York to participate in the meeting between Groundworx and Stephens, Inc. — Groundworx’s would-be financier.

¶ 9. According to Groundworx, “[i]t was clear to the parties that neither the bond rating agencies nor the bond insurers would be interested in bonding the financing ... but for the City’s promise to increase sewer rates to pay for the financing.” So at the meeting, the City officials talked about raising sewer rates to show “the City’s commitment to bond financing the project.”

¶ 10. Two and a half weeks later, during its February 18, 2014 meeting, the city council adopted a resolution to raise sewer rates. But nine days later, the mayor vetoed the resolution. So sewer rates were never raised.

*367 ¶ 11. The June 2,2014 financing deadline passed without Groundworx having closed on its financing.

III. Groundworx’s Original Complaint

¶ 12. Two weeks after the financing deadline, on June 19, 2014, Groundworx sued the City. It argued the City had breached its duty to maintain a revenue stream 1.3 times the amount of Ground-worx’s anticipated debt-service payments. Groundworx demanded specific performance — that the City be required to comply immediately with the obligation to identify a sufficient revenue stream. If not, Groundworx alleged it would not be able to secure financing for the project. Ground-worx also requested more than $6 million in compensatory damages.

¶ 13. Groundworx also filed for a temporary restraining order (TRO) prohibiting the City from cancelling the contract. The TRO was denied on July 14,2014.

¶ 14. The City filed its answer on July 18, 2014. Along with its answer, the City filed a countercomplaint for declaratory relief. The City asked the chancellor to declare: (1) the City had no contractual duty to identify a source of revenue, but rather only a duty to make payments when due; (2) therefore, the City had not yet breached any contractual obligation; and (3) the City had the unilateral right to cancel the contract based on Groundworx’s failure to obtain financing.

¶ 15. The City did not wait for a declarative judgment to cancel the contract. Instead, on August 5, 2014, the City exercised its contractual right to walk away from the agreement.

IV. Groundworx’s Amended Complaint

¶ 16. With the contract now terminated, Groundworx moved for and was granted permission to file an amended complaint. The amended complaint brought two counts against the City.

¶ 17. Count I alleged breach of contract, premised on two theories. First, Ground-worx alleged the contract itself obligated the City to raise revenue to cover 1.3 times the amount of the debt service payments. And second, after the contract was executed, the City entered an “express agreement” to raise sewer rates so Groundworx could obtain financing.

¶ 18. Count II alleged promissory estop-pel. Groundworx claimed the City representatives assured Groundworx and Stephens'the City would raise sewer rates, knowing Groundworx would be unable to obtain financing if the City did not. Groundworx claimed it detrimentally relied on these assurances to incur significant expenses on the project. Groundworx requested the chancellor award at least $6,266,753.42 in damages — the amount Groundworx had spent on the now-failed project.

¶ 19.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
234 So. 3d 363, Counsel Stack Legal Research, https://law.counselstack.com/opinion/groundworx-llc-v-thomas-a-blanton-miss-2017.