Ground Improvement Techniques, Inc. v. Merchants Bonding Co.

63 F. Supp. 2d 1272, 1999 U.S. Dist. LEXIS 13540
CourtDistrict Court, D. Colorado
DecidedAugust 27, 1999
DocketCivil Action 97-K-1203, 96-K-1622
StatusPublished

This text of 63 F. Supp. 2d 1272 (Ground Improvement Techniques, Inc. v. Merchants Bonding Co.) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ground Improvement Techniques, Inc. v. Merchants Bonding Co., 63 F. Supp. 2d 1272, 1999 U.S. Dist. LEXIS 13540 (D. Colo. 1999).

Opinion

MEMORANDUM DECISION ON RECONSIDERATION OF MAY 11, 1999 ORDER

KANE, Senior District Judge.

I. INTRODUCTION.

This litigation arose between Ground Improvement Techniques (GIT) and Merchants Bonding Company (Merchants) after Merchant’s subcontractor, Robinson & Son (Robinson) defaulted on the Slick Rock, Colorado, Uranium Mill Tailings Remedial Action Project. Merchants issued bonds to guarantee the performance and payment obligations of Robinson to GIT under the subcontract. After Robinson defaulted, GIT sought indemnification from Merchants for the work to have been performed by Robinson. Merchants seeks to avoid its obligation on the bond, claiming fraudulent concealment of material facts by GIT at the time the bond was issued.

On May 11, 1999, I issued an Order Granting GIT’s Motion for Summary Judgment on Merchant’s Counterclaim for Rescission. Merchants moved for reconsideration of that Order in light of case law in the area of insurance fraud that it had failed to cite previously. I agreed to reconsider and the parties have now briefed the issue in this new light. The motion for reconsideration is now pending. Jurisdiction is proper under 28 U.S.C. § 1332. State law provides the legal standards to be applied, while procedural issues are governed by the Federal Rules of Civil Procedure.

II. BACKGROUND.

These related cases arose out of an environmental remediation and restoration *1274 project initiated by the United States Department of Energy (DOE). The DOE contracted with Morrison Knudsen Company to collect contaminated mill tailings from different sites in the United States and bury them in a massive disposal cell to be constructed near Slick Rock, Colorado. Morrison Knudsen subcontracted with GIT, which in turn subcontracted with Robinson, to excavate the disposal cell in Burro Canyon.

Shortly after Robinson began the excavation work, it applied to Merchants for surety bonds guaranteeing its performance and costs under the subcontract. During its review of Robinson’s application, Timothy Toole, then an underwriter trainee at Merchants, called Jeff Walker, Slick Rock project manager for GIT, to inquire about Robinson’s bid on the excavation work and competency to perform the work. Later that day, Merchants approved performance and payment bonds guaranteeing Robinson’s performance and insuring labor and material payments under the subcontract with GIT.

Almost immediately after Robinson began excavation in Burro Canyon, a dispute arose between Robinson and GIT on the one hand, and GIT and Morrison Knudsen on the other, concerning acceptable excavation methods for the project. Because the different subcontracts were unclear on the excavation methods, Robinson proposed a single drill and blast plan based on test bores of the area and what Robinson claims to be the accepted industry standard. The subcontracts called for payment of one rate for excavation of softer top soil and a higher rate for nonrippable rock (harder soil or rock that had to be .drilled and blasted before excavation). Based on this price structure for the excavation project, Morrison Knudsen rejected Robinson’s proposed single drill and blast plan and insisted the excavation proceed piecemeal by removing any softer layers of topsoil and then drilling and blasting layers of rock before removal.

GIT initially sided with Robinson in this dispute, arguing the slower, step-by-step process would be more costly and result in time and cost overruns. GIT approached Morrison Knudsen seeking approval for Robinson’s proposed single drill and blast plan, or, in the alternative, for increased time payment under the GIT/Morrison Knudsen contract to cover the original plan. Morrison Knudsen rejected both requests. GIT ultimately relented and informed Robinson the excavation would have to proceed by the slower step-by-step method at the original subcontract price.

For several months, Robinson tried to comply with these restrictions while continuing to insist on its original proposed excavation method or an increase in time and money under the subcontract. When it became clear Morrison Knudsen and GIT would not relent either on the money or excavation methodology, Robinson abandoned the project and defaulted on its subcontract claiming impossibility of performance and frustration of purpose.

After Robinson’s departure, GIT approached Merchants under the performance bond for monies to replace Robinson and complete the excavation work. Merchants refused and GIT unsuccessfully attempted to do the work itself. GIT ultimately filed the instant lawsuit against Merchants seeking payment on the bonds, and Merchants counterclaimed for rescission based on fraud. In its counterclaim, Merchants contends GIT fraudulently concealed material facts about Robinson at the time the surety bonds were issued. Specifically, Merchants claims GIT was aware of the dispute over the excavation methodology at the time Robinson applied for the bonds, was cognizant of the impending default by Robinson due to the dispute, was in a position to inform Merchants of this information before the issuance of the bonds but did not due so, and is therefore responsible for Merchants issuing the performance bonds while the ongoing excavation dispute foretold the impending default of Robinson.

*1275 The factual disputes over who, as between GIT, Robinson, and Merchants knew, or is chargeable with knowing, of the excavation methodology dispute and the legal duties of each with respect to ascertaining or coming forward with this information, form the fulcrum upon which GIT’s Motion for Summary Judgment must be reconsidered.

In its original opposition to GIT’s Motion for Summary Judgment, Merchants argued GIT Project Manager Jeff Walker fraudulently concealed or misrepresented material information intending Merchants Underwriter Timothy Toole rely on the negative inference created by the omission to underwrite the Robinson subcontract. (Def.’s Resp. Pl.’s Mot.Summ.J. at 5-6.) In my May 11 Order, I determined Merchants had not presented sufficient evidence to create a triable question on the claim that Walker fraudulently misrepresented or concealed facts material to the issuance of the bonds and granted GIT’s Motion for Summary Judgment. Merchants’ Motion to Reconsider recasts the issue as one of insurance fraud, in which knowledge of the excavation dispute between GIT, Morrison Knudsen and Robinson is imputed to Walker, who was then duty bound as an “applicant” for the bond to disclose the dispute to Toole.

III. MERITS.

In the May 11, 1999 Order, I found there were “simply no facts from which scienter or any otherwise actionable state of mind can be inferred on the part of Walker with respect to his May 1995 telephone conversation with Toole.” Focusing on this point, Merchants’ first argument on reconsideration is that a showing of intent is unnecessary to a claim for fraudulent concealment in the surety bond, citing Wade v. Olinger Life Insurance Co., 192 Colo.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wade v. Olinger Life Insurance
560 P.2d 446 (Supreme Court of Colorado, 1977)
First National Bank v. Clark's Estate
59 Colo. 455 (Supreme Court of Colorado, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
63 F. Supp. 2d 1272, 1999 U.S. Dist. LEXIS 13540, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ground-improvement-techniques-inc-v-merchants-bonding-co-cod-1999.