Gross v. Southcoast Contractors, Inc.

261 So. 2d 383, 1972 La. App. LEXIS 6572
CourtLouisiana Court of Appeal
DecidedApril 17, 1972
DocketNos. 8781, 8782
StatusPublished
Cited by2 cases

This text of 261 So. 2d 383 (Gross v. Southcoast Contractors, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gross v. Southcoast Contractors, Inc., 261 So. 2d 383, 1972 La. App. LEXIS 6572 (La. Ct. App. 1972).

Opinion

LANDRY, Judge.

Defendants, American Employers Insurance Company (American), PHP, Inc. (PHP), and R. W. Inns of Louisiana, Inc. (R-W Inns), appeal adverse judgments of the trial court in favor of plaintiffs, Billy B. Gross (Gross) and Superior Concrete Finishers, Inc. (Superior), for labor and materials furnished by plaintiffs on certain construction projects undertaken by South-coast Contractors, Inc. (Southcoast) as prime contractor whose performance bond was written by American. We affirm.

By verbal agreement with Southcoast, Gross subcontracted to tape, float, texture and paint the sheetrock ceilings and walls, do certain exterior painting, install ceramic bath tile, soap receptacles and grab bars, and clean windows, baths, sinks and floors and vacuum carpeting in the Maison Terrebonne Apartments (Apartments) owned by PHP and Rodeway Inn (Rode-way), a motel owned by R-W Inns, situated in Houma, Louisiana. Gross also subbed the work of laying the forms for and finishing the surface of the concrete parking area of the motel project. With the full knowledge and consent of Southcoast, Gross resubbed the job of finishing the parking area to Superior.

Gross sought recovery of the sum of $9,120.86 from the named defendants and [385]*385Southcoast, together with recognition oí his recorded lien and the privileges resulting therefrom. The trial court awarded Gross $8,914.86. Gross has neither appealed nor answered Appellants’ appeal. Superior was awarded judgment below in the sum of $1,536.88. Judgment was rendered below against Southcoast by default inasmuch as said defendant made no appearance. Southcoast has not appealed the judgment against it. Appellants have bonded plaintiffs’ liens and resist plaintiffs’ claims on the grounds that Gross did not complete his contract obligation, and that a considerable portion of the sheetrock finishing and painting work was performed in an unworkman-like manner and had to be redone at considerable expense to the respective owners. R-W Inns also contends the paving of its parking area was totally unacceptable due to inferior workmanship.

The record discloses that Gross commenced work on the two projects on an undisclosed date in 1966. It also appears that by late November, 1966, time became an important factor in that the prime contracts were due to be completed by about the end of December, 1966, and the owners were anxious to take possession, especially of the motel. On behalf of Southcoast, construction was supervised by its President, Clarence “Boots” Pruyn, Jr., his father, Clarence Pruyn, Sr. (now deceased) and Southcoast’s Superintendent, Bill Jenkins. During November and December, 1966, the work was supervised principally by the older Pruyn and Jenkins because Boots Pruyn was then engaged in handling a project for Southcoast in New Orleans, Louisiana. In late December, 1966, John F. Higgins, a stockholder in both PHP and R-W Inns, commenced assisting in supervision of the activities at both construction sites apparently with the view of expediting construction. When Higgins observed Gross and Superior pouring the motel parking area in the rain, he requested that the Pruyns dismiss Gross which was done immediately. Gross was denied further access to either project, the complete supervision of which was then assumed by Higgins. In January, 1967, Southcoast defaulted on its prime contracts. On December 8, 1966, R-W Inns filed an acceptance of the work on its motel. Gross’ lien was filed February 10, 1967. Superior filed its lien February 14, 1967. A second acceptance of the motel work was filed by R-W Inns February 15, 1967.

Appellants’ brief urges primarily the factual question that the trial court erred in rejecting their defense that Gross’ work was incomplete and improperly performed. Incidentally, Appellants contend the lower court improperly awarded plaintiffs the amount of the entire contract price inasmuch as the work was not completed. In this regard, Appellants contend judgment should have been granted plaintiffs only for loss of profits of which plaintiffs were denied by the owners’ refusal to let plaintiffs complete the work.

GROSS’ CLAIM FOR FINISHING AND PAINTING SHEETROCK, TILE WORK AND CLEANING UP.

The record establishes that Gross had performed approximately 98% of the work of finishing and painting interior sheet-rock, exterior painting, ceramic tile work and cleaning up. Gross so testified, but conceding that of the tile work there remained only the installation of soap dishes and grab bars in the 46 units of the apartments and the 69 units of the motel. Higgins’ testimony on this score is that he had to expend $610,00 to complete the tile work and an additional $200.00 to regrout some of the tile Gross installed. Gross countered by stating that while he was on the job, no complaints were received regarding the tile work and no request made for regrouting of work performed.

Gross’ testimony was to the effect that the sheetrock and painting work called for was almost 100% complete when his services were terminated. In this respect, he was corroborated by his employee, Wilfred E. McCoy, Jr., who deposed that [386]*386this phase of the work was at least 90% complete when Gross was run off the job by Higgins.

Regarding the quality of the sheetrock finishing and painting, Gross conceded the work was not done according to normal practices. On this score, Gross was supported by McCoy and Cleveland W. McCorkel, a sheetrock contractor who performed the taping and floating of approximately 15 of the apartment units. In substance, these witnesses explained that upon orders from Boots Pruyn, the nails affixing the sheetrock to the studs were not set and puttied, but were merely painted over to cut costs and expedite completion of the projects. Both Gross and McCoy testified that Boots Pruyn directed that the ceiling and wall texture and finish, which are normally different, be done identically to reduce cost and accelerate construction. It is significant that although Boots Pruyn testified at the trial, he did not deny having given the aforesaid instructions regarding the finishing and painting of the sheetrock walls and ceilings. Nor was Southcoast’s Superintendent Jenkins called as a witness. Higgins testified as to the inferior workmanship on the ceilings and walls, and also indicated that the interior of the motel rooms had to be redone to meet the requirement of uniformity of texture and finish common to all Rodeway Motels. Higgins also testified the sum of $5,674.89 was expended to refinish the sheetrock and painting at the apartments and $1,360.00 was spent to redo the ceilings at Rodeway.

It is uncontroverted that the projects remained dormant from the time of Southcoast’s defalcation in early 1967, until August or September, 1967, when work was resumed under Higgins’ personal supervision. Gross testified unequivocally that before his ouster from the projects, he had cleaned the windows, tile work and sinks according to his agreement. Gross conceded he had not swept the floors, and neither had he vacuumed the carpets which had not then been laid. Gross also estimated the cost of installing soap receptacles and grab bars at between $.60 and $1.00 per apartment and motel unit. Contrarily, Higgins testified Gross performed no clean up work whatsoever, and after completion of the projects, a considerable sum was expended in cleaning operations which Gross should have performed. In holding for plaintiff Gross, the trial court obviously accepted the testimony of Gross and his witnesses rather than that offered by Appellants’ witnesses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alumaglass Corp. v. Adm'x of Succession of Kendrick
303 So. 2d 911 (Louisiana Court of Appeal, 1975)
Hurston v. Dufour
292 So. 2d 733 (Louisiana Court of Appeal, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
261 So. 2d 383, 1972 La. App. LEXIS 6572, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gross-v-southcoast-contractors-inc-lactapp-1972.