Gross Const. Co. v. Hales

1912 OK 97, 129 P. 28, 37 Okla. 131, 1913 Okla. LEXIS 161
CourtSupreme Court of Oklahoma
DecidedJanuary 16, 1912
Docket1339
StatusPublished
Cited by11 cases

This text of 1912 OK 97 (Gross Const. Co. v. Hales) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gross Const. Co. v. Hales, 1912 OK 97, 129 P. 28, 37 Okla. 131, 1913 Okla. LEXIS 161 (Okla. 1912).

Opinion

Opinion by

ROSSER, C.

This suit was brought by the Gross Construction Company against George H. Hales to recover a judgment for the balance claimed to be due it upon a certain building contract, for the construction of a building upon lots 10 and 11, block 7, in Oklahoma. City, amounting, as alleged, to $3,192.11. Tlirsch and Kauffman were made parties because they had become interested in the property since the transaction in controversy. The pleadings, exhibits thereto, and preliminary motions in the case cover 60 pages of the record. Defendant filed an answer and cross-petition. The answer was a general denial, but in the trial it was practically admitted that the plaintiff and defendant entered into the contract sued upon, and the only matter in controversy between them was as *133 to a certain, credit, which the defendant claims he was entitled to on account of certain party walls, for which he claims the plaintiff agreed to pay. The defendant, in his cross-petition, gave a long and complicated description of the lots which had been owned by him, and upon which party walls had been built, certain fractional parts of which, set out minutely in the cross-petition, the defendant had originally been bound to pay for. The cross-petition then alleged that plaintiff was to pay the amount defendant owed for party walls out of the sum agreed to be paid it on the building contract, and that plaintiff’s agreement to pay was contained in the written building contract.

The building contract was upon a form used by the National Association of Architects and Builders, and into the form was written the following: “This contract will include all walls and party walls, which are to be paid for by the contractor.” The plans and specifications, according to which the building was constructed, were not produced at the trial. The defendant, after persistent effort to show by parol testimony what was meant by the provisions in the contract, that it was to “include all walls and party walls, which were to be paid for by the contractor,” offered to amend his cross-petition by alleging that he was induced to sign the contract through fraudulent representations made to him by plaintiff with reference to the construction that would be placed upon the contract which he signed, and that he relied upon the statements made by the plaintiff, and he believed them to be true, and signed the contract, relying upon such representations. The court refused to permit the amendment. The defendant then undertook to prove that the contract to pay for the party walls was made by the plaintiff separate and distinct from the written contract, and that there was a .valid and binding agreement made between the plaintiff and defendant by which the plaintiff agreed to pay defendant’s portion of the price of the construction of the wall on the east side of lot 16. When this evidence was excluded by the court, the defendant asked leave to amend his answer to the effect that the contract sued on did not express the real agreement between *134 the parties, and that the failure to so express said agreement between the parties was a mutual mistake upon the part of the plaintiff and defendant Hales, and that it was the agreement of the parties that plaintiff should pay for that portion of the wall on the east side of lot 16, block 7, of Oklahoma City, or the price of the construction of that wall that defendant, by former agreement entered into with one S. M. Gloyd, had agreed to pay, and also that the same agreement was entered into with reference to the plaintiff paying for that portion of the party Avail on the west side of lot Í0 that defendant was bound to pay, and asked that the agreement be reformed to state what the actual understanding and agreement of the parties was. The court permitted this amendment, and the trial then proceeded, ° and there Avas a verdict and judgment reducing the plaintiff’s claim to the extent of the amount claimed by the defendant for the party wall.

The defendant testified that before the contract Avas signed the plaintiff agreed to pay for half of “Sipes’ wall,” and “Will Hales’ wall, and also the partnership walls on all the rest of the building.” He said that after he had this conversation with the plaintiff that the clause, “This contract will include all walls and party walls, which are to be paid for by the contractor,” was written into the contract. And then stated that he' had a talk with the plaintiff’s manager as to what this meant, and said: ■

“He (meaning plaintiff) told me he would pay for .the east Avail, Mr. Gloyd’s, and all the party Avails. That is the reason that I had it put in that way. I had signed a contract with Mr. Gloyd, and Mr. Gross knew all about it. When we talked this over, Mr. Gross agreed to pay for all the walls for this contract, in this contract.”

Then the examination proceeds as follows:

“Q. Did you tell him that the clause intended he should pay for all these Avails in this contract? A. I told him that he would have to agree, before I would sign this contract, he AArould pay for all the Avails, Jasper Sipes’, W. T. Hales’, Gloyd’s *135 wall, and Heinrich’s wall, and his own wall, and he agreed to and did. That was the conversation.”

Defendant was corroborated to a certain extent by the witness Heinrich. It also appears that plaintiff paid for some of the party walls and gave defendant credit on his account for $550.50 that defendant had paid on the Sipes’ wall.

The grounds urged by plaintiff for a reversal of this case are reducible to two heads: First, that the court erred in permitting the defendant to amend his answer so as to allege that through mistake the contract failed to express the real intention of the parties. Second, that the evidence was not sufficient to support the allegations of the answer as amended.

Plaintiff’s position is that the amendment permitted was inconsistent wih the allegations of the original cross-petition, and that because of its inconsistency the amendment should not have been allowed, and that proof of the allegations of the amendment should not have been allowed.

The amendment, and evidence in its support, was properly received. The fourth paragraph of the cross-petition, on which the parties went to trial, alleged that the building contract provided that the plaintiff should pay for all the walls and party walls that the defendant had been liable for. When defendant was not permitted to show by oral testimony that the provision in the written contract, “This contract will include all walls and party walls, which are to be paid for by the contractor,” meant that plaintiff was to pay for the walls for which defendant had originally been liable, he amended by alleging that the contract did not express the real agreement, and that its failure to express the real agreement was a .mutual mistake of the parties, and that the real agreement was that plaintiff should pay for the walls. This was not inconsistent with the cross-petition as it stood before the amendment was made. Section 5679, Comp. Laws 1909, is as follows:

“The court, may, before or after judgment, in furtherance of justice, and on such terms as may be proper, amend any pleading, process or proceeding by adding or striking out the *136

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phillips v. Johnson
1950 OK 99 (Supreme Court of Oklahoma, 1950)
Atlas Life Ins. v. W. I. Southern, Inc.
105 F.2d 668 (Tenth Circuit, 1939)
Hudson v. Smith
1935 OK 204 (Supreme Court of Oklahoma, 1935)
Whittaker v. White
1934 OK 587 (Supreme Court of Oklahoma, 1934)
Moody v. Smoot Advertising Co.
126 S.E. 919 (West Virginia Supreme Court, 1925)
Lawless v. Tuthill
1924 OK 173 (Supreme Court of Oklahoma, 1924)
E. Van Winkle Gin & MacHine Works v. Brooks
1916 OK 22 (Supreme Court of Oklahoma, 1916)
Shipley v. City of Lawton
152 P. 119 (Supreme Court of Oklahoma, 1915)
Northwest Thresher Co. v. McNinch
140 P. 1170 (Supreme Court of Oklahoma, 1914)
St. Louis S. F. R. Co. v. Long
1913 OK 751 (Supreme Court of Oklahoma, 1913)
Herndon v. St. Louis S. F. R. Co.
1912 OK 99 (Supreme Court of Oklahoma, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
1912 OK 97, 129 P. 28, 37 Okla. 131, 1913 Okla. LEXIS 161, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gross-const-co-v-hales-okla-1912.