Groghan v. Billingsley
This text of 313 So. 2d 255 (Groghan v. Billingsley) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Alfred W. GROGHAN
v.
Paul BILLINGSLEY et ux.
Court of Appeal of Louisiana, Fourth Circuit.
*256 Gordon Hackman, Boutte, for plaintiff-appellant.
Vial, Vial & Lemmon, Leon C. Vial, III, Hahnville, for defendants-appellants.
Before SAMUEL, STOULIG and BEER, JJ.
SAMUEL, Judge.
Plaintiff, Alfred W. Groghan, filed suit against defendants, Mr. and Mrs. Paul Billingsley, demanding among other things their eviction from a house owned by him in Willowdale Subdivision, St. Charles Parish, Louisiana, fair rental value for the premises at the rate of $400 per month, *257 $2,000 in damages for depreciation of the house by virtue of defendants' occupancy thereof, forfeiture of a deposit made in connection with a contract to sell the house and lot in question, payment of a real estate agent's commission of $1,233.84, $3,500 attorney's fees, compensation for extra work allegedly performed by plaintiff in the sum of $3,850, and damages for trespass in the amount of $2,500.
The defendants answered, denied the allegations of the petition, and reconvened for various items of special damages totaling $6,226.99, a refund of the $2,000 deposit together with an additional $2,000 as a penalty, and an additional $3,500 for attorney's fees. The basis for the reconventional demand was the alleged defective and incomplete construction of the house plaintiff had agreed to build on his lot for defendants, after which both the house and lot were to be sold to them. Defendants aver that as a result of the defective workmanship they were unable to obtain conventional financing as provided in the contract to sell thereby entitling them to the damages claimed.
Plaintiff's answer to the reconventional demand avers he could not complete construction because of various defendant change orders, the unavailability of the house because it was locked and inaccessible after the defendants moved in before completion, and that the failure to obtain conventional financing was due to contrivance between them and the lending agency.
After a trial on the merits, there was judgment awarding plaintiff $1,100 for rent, awarding defendants $817.99 for expenditures made by them for curtain rods, draperies, a deposit on a cook-top unit, a medicine cabinet and light fixtures (all of which remained in the house), ordering both parties to direct the holder of the purchase deposit to return it,[1] rejecting all other claims, and ordering each party to pay his own cost.[2] Both plaintiff and defendants have appealed.
Some of the facts are not in dispute. On May 20, 1972, the parties signed a contract to sell and purchase a lot in Willowdale Subdivision, Luling, Louisiana, and a house to be constructed by the plaintiff-seller in accordance with plans and specifications made part of the contract. The purchase price was $41,128, and the sale was conditioned upon the ability of the purchaser to obtain conventional financing.[3] The completion date was scheduled for November 21, 1972. In pertinent part the standard form real estate buy-sell contract called for a deposit of $2,000 by the purchaser with the real estate agent and provided that in the event the purchasers failed to comply with the agreement within the time specified, the seller had the right to declare the deposit forfeited, and that in the event the seller so failed to comply, the purchaser had the right to the return of the deposit plus an equal amount to be paid as penalty by the seller. The contract also provided that either party who failed to comply became obligated to pay all fees and costs incurred in enforcing collection and damages. Annexed to this contract were the plans and specifications according to which the house was to be built.
We note this case does not involve the normal construction contract nor, for the reasons shown below, are we presented with the question of a contractor's substantial performance and the establishment of the necessary cost to remedy defects left by him.
*258 The evidence produced by the parties is quite lengthy. However, it is not necessary to engage in a detailed recitation of the complaints involved with regard to the defective construction. It suffices to say the evidence produced both by plaintiff and defendants convincingly shows the construction was extremely faulty and this faulty construction eventually resulted in the inability of the defendants to obtain conventional financing, a primary condition of the contract.
Plaintiff introduced an estimate by Earl J. Vicknair, the president of a local contracting firm, which established the cost of repairing most of the defective construction at $6,299. In addition, Vicknair refused to estimate the cost of alignment of certain walls and alignment of the front entry. He would only agree to undertake repair of these items on a cost plus 15% basis. Vicknair's testimony substantiated his written estimate.
Also introduced into evidence were estimates and testimony by Allen J. LeBlanc, a field appraiser for the lending agency which eventually refused to honor its commitment for conventional financing for the defendants. LeBlanc testified that as of May 23, 1972, based on the plans and specifications submitted by the plaintiff, he estimated the fair market value of the projected house and lot at $41,000. However, following his last inspection of the house and because of the defects which were apparent to him from that inspection, he lowered his estimate to $37,000.
The inspections by Vicknair and LeBlanc revealed a sag or dip in the roof, walls which were not plumb, poorly hung wallpaper, improperly finished woodwork and sheetrock, together with defective installation of kitchen cabinets, a stove hood vent and a vanity top. There was also a problem with the alignment in appearance of the front entry to the premises. On January 9, 1973, a representative of the lending agency notified defendant that the defects described prevented it from granting a permanent loan using the house as security.
Apparently with the knowledge that the loan would not be secured, plaintiff filed this suit on January 5, 1973. He requested and obtained the eviction of the defendants from the premises. Defendants vacated the premises on January 20, 1973 after having lived there since October 1, 1972. The trial court awarded plaintiff compensation for the occupancy of the house based upon a three and two-third (32/3) month period at the rate of $300 per month. Defendants argue this award is in error.
While somewhat vague, the evidence establishes defendants occupied the house on October 1, 1972 with the implied consent of the plaintiff. There was never an agreement as to a rental and the basis for the trial court's award is essentially the testimony of the plaintiff.
Mere occupancy of a building does not of itself imply the relationship of lessor and lessee.[4] A lease is a contract by which one party gives to the other the enjoyment of a thing at a fixed price.[5] As in the contract of sale, there are three absolutely essential elements to a lease: the thing forming the subject matter of the contract; the price for the enjoyment of the thing; and the consent or agreement of the parties.[6] There can be no contract of lease in the absence of a stipulation or agreement between the parties as to the amount of rent to be paid.[7]
*259
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
313 So. 2d 255, Counsel Stack Legal Research, https://law.counselstack.com/opinion/groghan-v-billingsley-lactapp-1975.