Grinnell Fire Protection Systems Co., Inc. v. W. C. Ealy & Associates, Inc.

552 S.W.2d 747, 1977 Tenn. App. LEXIS 256
CourtCourt of Appeals of Tennessee
DecidedFebruary 25, 1977
StatusPublished
Cited by1 cases

This text of 552 S.W.2d 747 (Grinnell Fire Protection Systems Co., Inc. v. W. C. Ealy & Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grinnell Fire Protection Systems Co., Inc. v. W. C. Ealy & Associates, Inc., 552 S.W.2d 747, 1977 Tenn. App. LEXIS 256 (Tenn. Ct. App. 1977).

Opinion

OPINION

ABRIDGED FOR PUBLICATION

TODD, Judge.

The plaintiff, Grinnell Fire Protection Systems Co., Inc., sued defendant, W. C. Ealy & Associates, Inc., for balance due for performance of a construction subcontract. The defendant filed a cross action for breach of said contract. The Chancellor allowed the amount sued for by plaintiff and sustained part, but not all, of defendant’s cross action. Both parties have appealed.

This case arises out of the construction of a manufacturing plant in Lewisburg, Tennessee for the owner, Koh-i-noor Radio-graph, Inc.

On August 9, 1973, said owner contracted in writing with defendant to furnish all labor and materials for construction of a building according to plans and specifications attached to the contract.

On October 11, 1973, plaintiff wrote to defendant the following letter:

“Gentlemen:
We are pleased to confirm our verbal quotation in the amount of Thirty-Four Thousand Nineteen and 00/100 Dollars ($34,019.00), for the necessary labor and material to provide automatic wet pipe sprinkler protection throughout the proposed 180' X 350' manufacturing building and 40' X 80' office area at the subject location.
We propose to start at the valve pit approximately 80'-0" from the northwest corner of the building, provide underground supply piping on the north, east and west side of the building supplying hydrants on the southeast and southwest corners and one hydrant on the north side at the approximate center of the building and two riser supply entrance points at the north wall, including excavating and backfilling. We further propose to furnish the control valves, alarm valves, six (6) small hose stations, necessary Duras-peed brass finish pendent and upright sprinklers, including additional sprinkler protection for the concealed space of the Cosmotology Area, Rooms 27-33, pipe, fittings and hangers.
We do not include connection to the existing city water main, piping from the city main to within 80'-0" of the northwest corner of the building, construction of the valve pit complete, rock excavation, painting or electrical wiring.
Our terms of payment are in the sum of ninety percent (90%) of the price of materials delivered and work performed in the month immediately preceding and the balance within thirty days after completion.
Thank you for the opportunity to quote. We will proceed with the installation upon receipt of two (2) signed copies of our proposal, your purchase order or contract.
Very truly yours,”

Thereafter, on November 7, 1973, plaintiff contracted in writing to furnish all labor and materials for construction of a sprinkler system in said building for the price of $34,019.00. Said contract contained the following material provisions:

“2. The Subcontractor shall furnish all labor, materials, equipment, fees, licenses, permits, etc., and shall per[749]*749form all the Work for: Sprinkler System in accordance with the requirements of Factory Mutual Insurance Company. Furnish all labor, material, engineering and drawings, also extra requirements of Double Sprinkler Systems over Cosmotology Area. Rock Excavation shall be extra to the contract. Furnish proper Certification of Acceptance from Factory Mutual Insurance Company.
“3. The Subcontractor shall promptly submit shop drawings and samples as required in order to perform Work efficiently, expeditiously and in a manner that will not cause delay in the progress of the Work of the Contractor or other Subcontractors. The Subcontractor agrees to begin installation of the Work within five (5) days after receiving notice, either written or oral, from the Contractor. Should the Subcontractor, at any time, fail, refuse or neglect to supply sufficient material, tools, labor or properly skilled workmen to complete the Work without delaying job progress, for five (5) days after written notice of such default to Subcontractor, Contractor may at any time thereafter take over and complete the Work. The cost to Contractor of completing such work shall be deducted from any moneys due Subcontractor; .if such costs exceeds any such moneys, Subcontractor shall reimburse Contractor.”

Plaintiff completed the installation of the sprinkler system which was approved by a representative of Factory Mutual Insurance Company, and plaintiff received partial payment reducing the amount due for performance of the contract to $16,229.48.

Sometime after the execution of the contract and before performance of same, it was discovered that the water pressure of the available water supply was inadequate for proper performance of the sprinkler system and that a “booster pump” was required to supply the desired pressure. Plaintiff notified defendant of the situation and offered to install the necessary booster pump (without a pump house or shelter) for $15,275.00. Defendant insisted, and now insists, that it was the duty of plaintiff to supply and install the “booster pump” without additional charge. Plaintiff denied any such obligation and declined to provide the booster pump without additional compensation.

Finally, the desired pump and necessary pump house was provided by defendant. As a result of delay in final completion of the project, defendant was penalized the contract penalty of $1,000.00 per week for 20 weeks.

The original suit of plaintiff was for the $16,229.48 due for its performance of the contract. This amount is admitted to be correct and was allowed by the Chancellor.

The countersuit of defendant was for the cost of pump installation and $20,000.00 penalty suffered for delay.

The Chancellor allowed plaintiff’s claim of $16,229.48, but also allowed the counterclaim of defendant to the extent of $30,-061.25 for pump and pump house, resulting in a net judgment in favor of defendant and against plaintiff in the amount of $13,-831.77.

The plaintiff has filed seven assignments of error, the determinative essence of which is that plaintiff had no duty to install the pump.

It is not denied that this was a “design and build” contract, wherein the general contractor was given only general or “skeleton” specifications of the construction, and the general contractor was required to provide specific design details for attainment of a suitable result. Plaintiff admits responsibility for design and construction of a sprinkler system, but denies responsibility for design or construction of a water supply system.

Thus, the issue is whether the contract of plaintiff with defendant, requiring plaintiff to design and furnish a sprinkler system, either expressly or otherwise included the duty to investigate the nature of the water [750]*750supply in terms of quantity, rate of flow and pressure, and to include in the design of the sprinkler system the necessary equipment (pump) to produce the necessary supply, flow and pressure.

The term “Sprinkler Systems,” as used in said contract, does not connote a duty to design and install the equipment necessary for producing the quantity, rate of flow and pressure of water required for the sprinkler system.

There is no evidence that the term, “Sprinkler Systems” has such a recognized meaning in the trade so as to bind plaintiff accordingly.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vinings Bank v. Homeland Community Bank
Court of Appeals of Tennessee, 2019

Cite This Page — Counsel Stack

Bluebook (online)
552 S.W.2d 747, 1977 Tenn. App. LEXIS 256, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grinnell-fire-protection-systems-co-inc-v-w-c-ealy-associates-inc-tennctapp-1977.