Griffith v. Maxfield

218 P. 105, 62 Utah 51, 1923 Utah LEXIS 80
CourtUtah Supreme Court
DecidedJuly 27, 1923
DocketNo. 3940
StatusPublished
Cited by1 cases

This text of 218 P. 105 (Griffith v. Maxfield) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Griffith v. Maxfield, 218 P. 105, 62 Utah 51, 1923 Utah LEXIS 80 (Utah 1923).

Opinion

THURMAN, J.

Plaintiffs J. L. Griffith Company are successors in interest of a partnership of the same name previously existing in which one John Zoss was a member. The principal place of business of the partnership was in Salt Lake City, Utah, and prior to the alleged wrongs complained of in plaintiffs’ complaint said partnership entered into a written agreement with said city for the construction of an extension to the East Jordan canal, of which Salt Lake City was the owner. On the 17th day of February, 1920, the J. L. Griffith Company entered into a written agreement with the defendants Maxfield and Brinton, by the terms of which the defendants agreed to perform all the necessary work in excavating, constructing, and completing the extension of said canal, situated in Salt Lake county, Utah, including the clearing of the ground, and [54]*54removing and replacing fences, to the extent that the same became necessary in the course of construction. The canal to be constructed was approximately 19,300 linear feet, and the same was to be completed for the price named in the contract in a good, substantial, and workmanlike manner; defendants agreeing to furnish all tools, labor, and material necessary to properly perform and complete the work for use in accordance with the plans and specifications contained in the contract and in the contract theretofore entered into between the said J. L. Griffith Company and Salt Lake City.

The defendant United States Fidelity & Guaranty Company' (engaged in the general business of surety for compensation) for a valuable consideration executed its bond of indemnity to the J. L. Griffith Company, and thereby became surety for said defendants for the faithful performance of the work. The defendants further agreed to commence said work as soon as directed by J. L. Griffith Company and continue the same without interruption to a full completion within 100 days thereafter, Sundays and legal holidays excepted. Pursuant to notification defendants commenced said work on or about February 26, 1920. It was further agreed that time was of the essence of the contract, and that for every day the work remained unfinished after the expiration of 100 days J. L. Griffith was authorized to deduct and retain $10 out of any money due or to become due said defendants for material and labor furnished by them pursuant to the contract. In the event there was no money due them, defendants agreed to pay said $10 per day as liquidated compensatory damages. A short time previous to August 13, 1920, defendants failed and neglected to proceed with the work or to furnish material therefor, and on the date last mentioned J. L. Griffith Company notified the defendant U. S. Fidelity & Guaranty Company of such failure and neglect on the part of defendants, and requested said company to either take over and complete the work in accordance with its bond of indemnity or authorize the J. L. Griffith Company to complete the same. On the 14th day of August, 1920, defendants formally notified J. L. Griffith Company, in writing, that they were unable to finish the work, and expressly consented that the same might be [55]*55completed by their surety or by the J. L. Griffith Company, on such terms as might be just in the premises.

Plaintiffs, after alleging, in substance, the matters above stated, further allege that they have duly performed all the terms and conditions of said contract to be by them performed, and that, after defendants Maxñeld and Brinton failed, neglected, and refused to further furnish material or perform further labor under said contract, J. L. Griffith Company was compelled to furnish labor and material for the completion of said work solely at their own expense in the sum of $11,139. It is also alleged that the superintendency of said work by J. L. Griffith Company was of the reasonable value of $856.65, together with liquidated damages in the sum of $1,370, for which amount, with interest thereon at 8 per cent, per annum, plaintiffs pray judgment.

Defendants answering admit the allegations of the complaint as far as the contract is concerned and their failure to complete the same as therein alleged, but by way of defense they allege, in substance, that it was the duty of plaintiffs to furnish a right of way for the construction of said canal, but that plaintiffs failed to do so before the irrigation season commenced, and that by reason of such failure defendants were unable to enter upon and complete the work before the ground became saturated with water from irrigation; that by reason of such failure they were not only delayed in their work but the work was rendered far more difficult and expensive. This defense was especially .made applicable to a section of the work extending through what is denominated the Little Cottonwood district in which the land is of a gravelly nature and absorbs and maintains a large quantity of water from the irrigation of adjacent lands lying above the canal.

It is also alleged as a defense that the money expended by J. L. Griffith Company to complete the canal was expended voluntarily and without the request of defendants, and was expended solely because plaintiffs had failed to furnish rights of way, and had thereby compelled defendants to incur great and additional expense; that said money was expended by plaintiffs for their own benefit, with the implied understand[56]*56ing that no claim therefor would be made against the defendants. Finally, it is alleged as a defense that, well knowing that defendants had a claim against plaintiffs for a large amount, on account of the failure of plaintiffs and Salt Lake City to furnish said rights of way as before stated, .and well knowing that defendants, in connection with plaintiffs, had a cause of action against Salt Lake City for damages for failure to furnish rights of way, and that said damages had been suffered and sustained by the defendants, the said plaintiffs presented a claim against Salt Lake City for damages, representing that damages had been sustained by plaintiffs, when in truth and in fact such damages had been sustained by defendants, by reason of said city’s failure to furnish said rights of way; that said claim so presented by plaintiffs was for the sum of $10,544.54; that plaintiffs received from said city the sum of $4,900 in settlement of said claim, and accepted the same to cover all losses by reason of delay and other matters relating to the construction of said canal; that by reason of the same it operated as a settlement of any claim that plaintiffs might have against the defendants, and the said plaintiffs thereby waived any claim it might have against defendants, and are estopped from making any such claim.

By way of counterclaim on account of damages sustained for failure to furnish rights of way, defendants allege their damages to be the sum of $5,000. They pray judgment for that amount, and that plaintiffs take nothing by reason of their complaint.

The case was tried to the court without a jury. The court found in favor of the plaintiffs, with an allowance to defendants, on their counterclaim, for damages. Defendants appeal and assign 49 errors, 5 of which are relied on in the argument, and the remainder abandoned.

The principal contention of appellants is that the court failed to find on the material issues tendered by their answer and counterclaim. These issues as stated by appellants are, in substance, as follows: (1) That defendants had been induced to enter into the contract upon representations by plaintiffs that plaintiffs had secured all rights of way, that [57]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hotel Last Frontier Corp. v. Frontier Properties, Inc.
385 P.2d 776 (Nevada Supreme Court, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
218 P. 105, 62 Utah 51, 1923 Utah LEXIS 80, Counsel Stack Legal Research, https://law.counselstack.com/opinion/griffith-v-maxfield-utah-1923.