Grieves v. State

40 Ill. Ct. Cl. 130, 1987 Ill. Ct. Cl. LEXIS 49
CourtCourt of Claims of Illinois
DecidedAugust 19, 1987
DocketNo. 84-CC-3301
StatusPublished

This text of 40 Ill. Ct. Cl. 130 (Grieves v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grieves v. State, 40 Ill. Ct. Cl. 130, 1987 Ill. Ct. Cl. LEXIS 49 (Ill. Super. Ct. 1987).

Opinion

Raucci, J.

This is an action brought by Claimant for damages for an alleged breach of contract.

On April 30,1982, bids were opened at the office of Starved Rock State Park for carpentry work for the period of July 1,1982, through June 30,1983.

The work to be performed under the contract was defined in the request for bids as follows:

“2. Services generally may be defined as preventative maintenance services, routine repair services, and emergency repair services.”

There were two bids. Edward J. Muhich bid $26.00 per hour for labor and 15% above cost of materials, while Claimant, John L. Grieves (also known as Grieves Construction Company) bid $17.00 per hour for labor and 5% above cost of materials. (Resp. Ex. 1).

Claimant was awarded the contract, and subsequently the contract was extended for another year, through June 30, 1984. No written contract documents were ever signed, but see the following in Respondent’s answer to Claimant’s interrogatories:

“Interrogatory No. 7: Did the State of Illinois have any contracts with the claimant, Grieves Construction Company during the years 1982-1983 and 1983-1984? If the answer to the above is yes, then:

A) State the precise nature of each contract and describe the work to be done thereunder;

B) Provide the date each contract was entered into and its duration;

C) Provide the times and dates Grieves Construction Company was called to perform work under said contract.”

Answer to interrogatory No. 7:

“Yes

A) Carpentry preventive maintenance services, routine repair services and emergency repair services.

B) Fiscal year 1983 from July 1,1982 to June 30,1983 signed April 30,1982; Fiscal Year 1983 from July 1,1983 to June 30,1984 signed May 10,1983.

C) None.”

Thus, for the purposes of this case, whether or not the State actually entered into a contract with Claimant is not an issue. Respondent has conceded that a contract exists.

The language appearing at the bottom of the certification of the opening of the bids reads:

“Amount to Encumber for this Trade Starved Rock: $1,000
Matthiessen: $ 500”

Thus, it is clear that no work could be performed under the contract that would involve an expenditure in excess of $1,000.00 at Starved Rock and $500.00 at Matthiessen.

The explanation for this limitation can be found in section 6(5) of the Illinois Purchasing Act (Ill. Rev. Stat., ch. 127, par. 132.6 (5)), the Department of Conservation Physical Operations Handbook (referred to in testimony but not introduced into evidence), and the Comptrollers Uniform Statewide Accounting System.

Mr. Bobby Ray Wise, procurement and operations officer for the Department of Conservation, summarized these purchasing limitations as follows:

“We have certain in house limits that we have in our general services or physical operations handbook., And those are stated to our site managers, number one. In that particular handbook it indicates to the site people that you can go up to $1,000 on their own. Site people with approval of the regional land managers can go up to $2,500. Anything over $2,500 that had to be approved by the Springfield office. And at that time a Cod form, C-o-d, or comptrollers obligation document have to be filed with those folks. Anything over and above those amounts up to $5,000 can be filed after it has been advertised in a case like this and obligated with the comptroller with no problems. That is for a single project. Any project over $5,000, but not exceeding ten has to be advertised, also. No project over $10,000 can be handled by the Department. At that time the Capital Development Board takes over. And they have to advertise the contract or with their authority they could authorize it back to the Department under their jurisdiction and sign off.” (Tr. 120-21).

In addition to entering into a maintenance contract with Claimant in the spring of 1982, the Department of Conservation began the paperwork required to replace 82 windows at the Starved Rock State Park Lodge at an estimated cost of $25,000.00 for the windows.

Thus, by letter of June 22, 1982, the Department of Conservation wrote a letter to the Capital Development Board requesting the Capital Development Board to fund the project in the amount of $25,000.00.

An undated project description form (Resp. Ex. 15) prepared by Mario Vitale, states:

“We need to replace the windows in the guest rooms of the lodge because the window frames are deteriorating and do not close properly. The windows are to be replaced by the Regional Hot Shot Crew.”

The form has a section for methods of execution, reproduced below:

EXECUTION METHOD

x Purchase Materials/DOC Construct

_ Purchase Materials/Contractor Construct

_ Contractor Furnish Materials, Labor & Construction

The foregoing indicates that the Department did not contemplate that an outside contractor would perform the labor of installing the windows. Rather, it was contemplated that the installation would be done by Department of Conservation Personnel. This is corroborated in Respondent’s exhibits 14 and 18. Exhibit 14 reads:

“June 29,1982
Mr. Thomas Madigan, Director of Operations Capital Development Board 3rd Floor, Wm. G. Stratton Bldg.
Springfield, Illinois 62706
RE: Starved Rock Lodge — Window Replacement $25,000
Dear Mr. Madigan:
The Illinois Department of Conservation desires to program this project as a purchase, DOC construct. It is felt this is the most viable alternative due to the following:
1. The region’s carpenter staff is located at the Starved Rock site. This crew is capable of doing this work and their proximity to the site will cut the cost of construction.
2. Utilizing DOC’s crew and a purchase will result in the maximum number of windows being installed at the cheapest cost. Two years ago the A/E on the rehabilitation project estimated the cost of this work at $42,000. When inflation contingencies and A/E fees are added to this figure a savings of at least 502! should be realized by executing this project as proposed.
Please advise if additional information is required.
Sincerely,
Robert E. Corrigan, Chief Division of Technical Services”

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
40 Ill. Ct. Cl. 130, 1987 Ill. Ct. Cl. LEXIS 49, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grieves-v-state-ilclaimsct-1987.