Grier-Lowrance Construction Co. v. United States

98 Ct. Cl. 434, 1943 U.S. Ct. Cl. LEXIS 99, 1943 WL 4201
CourtUnited States Court of Claims
DecidedMarch 1, 1943
DocketNo. 43640
StatusPublished

This text of 98 Ct. Cl. 434 (Grier-Lowrance Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grier-Lowrance Construction Co. v. United States, 98 Ct. Cl. 434, 1943 U.S. Ct. Cl. LEXIS 99, 1943 WL 4201 (cc 1943).

Opinion

Madden, Judge,

delivered the opinion of the court:

On May 18,1929, plaintiff, a North Carolina corporation, entered into a contract with the defendant to furnish all labor and materials and perform all work required for the construction of the foundations of the several structures comprising the Bridge Plaza and the Watergate of the Arlington Memorial Bridge project, Washington, I). C., together with any additional work directed by the contracting officer, such additional work to be paid for at the unit prices specified in the contract.

[459]*459The work under the contract included furnishing all labor ¡and materials for clearing the site of the work of trees, •buildings, underground water pipes, conduits and other obstructions ; digging trenches along the parkway and at the site of the Watergate; digging and cribbing 82 pits or wells, into which reinforced concrete for cylinders and foundation piers was to be placed; constructing cofferdams around areas where work was to be carried on within or near the limits of the river bed, where seepage of water might be expected; building wooden forms for and casting and driving 576 reinforced concrete piles; driving several thousand feet of sheet piling, both wood and steel; and tearing out and reconstructing a large sewer which intersected the site of the work.

The contract price was $328,700, and the work was to be ■completed within 180 days after receipt of notice to proceed, which made the original completion date November 21,1929. The contract provided that liquidated damages in the amount of $100 per day might be assessed against plaintiff for lateness in completing the contract work. It also provided that the time for completion would be equitably extended on account, inter alia, of changes or additions directed by the contracting officer which delayed completion. On account of changes directed by the contracting officer during the course of the contract plaintiff received $70,192.28 additional compensation and 62 days’ additional time for performance. The work was completed June 21, 1930,. 212 days after the original completion date and 150 days after the completion date as extended.

Plaintiff sues for $133,000 under a special act of Congress approved May 6, 1937 (50 Stat. 955). That act reads as follows:

That the claim of Grier-Lowrance Construction Company, Incorporated, for losses and damages under contract numbered AMB 28, dated May 18, 1929, for the construction of the foundation for the several structures of the Arlington Memorial Bridge project be, and the same is hereby, referred to the United States Court of Claims with jurisdiction to hear the same to judgment, said claim to be adjudicated upon the basis of all losses or damages suffered by the said company duly found to [460]*460be due to acts of the Government or delays caused by the Government or subsurface conditions unknown to the contractor and not disclosed by the Government before contract was entered into, notwithstanding any lapse of time or any provisions of the statute of limitations: Provided, That suit hereunder is instituted within four months from the approval of this Act.

Plaintiff contends that the court’s function under this act is limited to the ascertainment of the amount of losses suffered by plainiff due to “acts of the Government or delays caused by the Government or sub-surface conditions unknown to the contractor and not disclosed by the Government before contract was entered into”, and that, this amount having been found, judgment for plaintiff should follow as a matter of course. This contention would seem to mean that Congress intended that it should be immaterial whether the “acts of the Government” or “delaj^s caused by the Government” were rightful or wrongful, and that the absence of disclosure by the Government of “sub-surface conditions unknown to the contractor” should be a ground of recovery even though the Government did not know and had no duty to know the conditions, and even though plaintiff could, by the exercise of prudence, have known them itself, or had, by the terms of the contract, assumed the risk of such variations in the conditions of the work as actually were encountered. We think that Congress had no intention to imposed upon us the duty to discard all legal and equitable bases of liability and merely trace the relation of cause and effect between rightful and proper conduct on the part of the Government, or risks contracted for by plaintiff and paid for by the Government and “losses” suffered by plaintiff as a consequence thereof. We think that Congress would hardly have described as “losses or damages suffered by the said company duly found to be due” to acts of the Government, the mere financial consequences to plaintiff of the Government doing what it had a right to do, or its insisting on plaintiff’s doing what it had contracted to do. In our consideration of the case, therefore, we shall examine into the consequences only of wrongful acts or nondisclosures of the Government, or breaches of contract on its part, or refusals to compensate plaintiff as provided in the contract.

[461]*461A question arises as to whether plaintiff’s failure to make timely written protests concerning the subjects of its claims, and its failure to appeal from adverse decisions of administrative officials, prevents our consideration of those claims on their merits, or whether the special jurisdictional act relieves plaintiff of these impediments. A consideration of the legislative history of the special act persuades us that Congress did not intend to give plaintiff any special relief in that direction. In view however, of what we say hereinafter about the contracting officer’s waiver of the lateness of plaintiff’s claims, and of the impracticability of any appeal in the peculiar circumstances of the case, the question becomes immaterial, and we do not discuss the legislative history.

Plaintiff claims that a considerable number of items of work which it did, and which, it alleges, it was required to do, were made necessary by some fault of the defendant, or by some unforeseen condition which developed on the job, or were, under the terms of the contract, such items as entitled plaintiff to greater compensation than plaintiff has been paid, or were wholly outside the requirements of the contract.

Paragraph 20 of the specifications was as follows:

Protects. — If the Contractor considers any work demanded of him to be outside the requirements of the contract, or considers any record or ruling of the Contracting Officer or of the inspectors to be unfair, he shall immediately ask for written instructions or decision, and, within ten days after receipt of the same, he shall file a written protest with the Contracting Officer, stating clearly the basis of his objections. Unless the Contractor files protest as thus provided, he will be considered to have accepted the record or ruling.

In no instance did plaintiff ask for a written instruction or decision, or file a written protest with the contracting officer within the specified ten days. However, the contracting officer disregarded this provision of the specifications just as completely as plaintiff did, by accepting plaintiff’s claims after the work was completed, and considering them on their merits. To be sure, in his communications to the Comptroller General, the contracting [462]*462officer mentioned that the plaintiff had not protested the various matters at the time they arose.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
98 Ct. Cl. 434, 1943 U.S. Ct. Cl. LEXIS 99, 1943 WL 4201, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grier-lowrance-construction-co-v-united-states-cc-1943.