Gridliance Heartland LLC v. The Illinois Commerce Commission

2023 IL App (5th) 230073-U
Appellate Court of Illinois·Decided December 26, 2023·No. 5-23-0073·Unpublished

Opinion

NOTICE

2023 IL App (5th) 230073-U NOTICE

Decision filed 12/26/23. The This order was filed under text of this decision may be NO. 5-23-0073 Supreme Court Rule 23 and is changed or corrected prior to the filing of a Petition for not precedent except in the

Rehearing or the disposition of IN THE limited circumstances allowed the same. under Rule 23(e)(1).

APPELLATE COURT OF ILLINOIS

FIFTH DISTRICT

GRIDLIANCE HEARTLAND LLC, ) Appeal from the ) Illinois Commerce

Petitioner-Appellant, ) Commission )

)

v. )

)

THE ILLINOIS COMMERCE COMMISSION and ) No. 20-0263 AMEREN ILLINOIS COMPANY, d/b/a ) Ameren Illinois, )

)

Respondents-Appellees. )

JUSTICE CATES delivered the judgment of the court.

Justices Boie and McHaney concurred in the judgment.

ORDER

¶1 Held: The Illinois Commerce Commission properly found that GridLiance Heartland LLC was a public utility, and res judicata did not apply. The Illinois Commerce Commission’s interim order directing GridLiance to seek a certificate of public convenience and necessity and by reopening the proceeding after its determination was not in error.

¶2 The petitioner, GridLiance Heartland LLC (GridLiance), appeals directly from an interim order of the Illinois Commerce Commission (Commission), dated November 17, 2022, and subsequent denial of rehearing, dated January 5, 2023. The Commission found in its interim order that GridLiance met the definition of a public utility as defined in section

3-105 of the Illinois Public Utilities Act (220 ILCS 5/3-105 (West 2022)). Based on this finding, the Commission directed GridLiance to apply for a certificate of public convenience and necessity (CPCN) and the Commission reopened the proceeding. We affirm the Commission’s order.

¶3 I. BACKGROUND

¶4 In August of 2018, GridLiance entered into a purchase agreement with Electric Energy, Inc. (EEI) for transmission assets which consisted of two substations in Joppa, Illinois, and six connecting 161 kilovolt transmission lines that extended into Kentucky. The Illinois portion of the facilities were in Ameren Illinois Company d/b/a Ameren Illinois’s (Ameren) authorized service territory and connected to Ameren’s electric transmission and distribution facilities.

¶5 After entering into the purchase agreement and prior to acquiring the EEI facilities, GridLiance petitioned the Commission in GridLiance Heartland LLC, Ill. Comm. Comm’n No. 18-1617 (Oct. 12, 2018), for a certificate of public convenience and necessity (CPCN) under section 8-406(a) of the Public Utilities Act. 220 ILCS 5/8-406(a) (West 2018). The CPCN would authorize GridLiance to own, control, operate, and manage the EEI facilities for public use, and to provide public utility electric transmission service over the facilities. GridLiance had argued that it should qualify as a public utility because, unlike EEI, GridLiance would offer non-discriminatory service on the EEI transmission facilities to “eligible customers,” including entities that would supply power to “end users” in Illinois.

¶6 Ameren intervened in GridLiance, Ill. Comm. Comm’n No. 18-1617, and argued that GridLiance was not a public utility or eligible for a CPCN. Ameren claimed that a

determination could not be made on whether GridLiance was a public utility prior to the acquisition of the EEI facilities. On September 6, 2019, GridLiance withdrew its petition. The Commission subsequently dismissed GridLiance, Ill. Comm. Comm’n No. 18-1617 (Sept. 18, 2019) without determining whether GridLiance was a public utility under section 3-105 of the Public Utilities Act (220 ILCS 5/3-105 (West 2018)).

¶7 GridLiance and EEI had also petitioned the Federal Energy Regulatory Commission (FERC) for approval of the GridLiance acquisition of the EEI facilities. FERC issued an order on August 28, 2019, denying, without prejudice, GridLiance’s application. FERC found that GridLiance and EEI failed to demonstrate that the acquisition was consistent with the public interest because it would adversely impact customers’ rates. GridLiance filed a subsequent application. On January 31, 2020, FERC conditionally approved GridLiance’s acquisition of the EEI facilities subject to rate mitigation measures. GridLiance accepted the conditions.

¶8 GridLiance acquired the facilities from EEI on February 29, 2020. GridLiance transferred functional control of four transmission lines and associated facilities to the Midcontinent Independent System Operator, Inc. (MISO), a non-profit, non-stock corporation that was a Regional Transmission Organization (RTO).

¶9 MISO managed the region’s power grid which was approximately 65,000 miles of interconnected high-voltage transmission line. MISO additionally operated an energy and ancillary service market for approximately 200,000 megawatts of power generating resources. GridLiance, as an owner of transmission assets, continued to own and maintain

its assets while MISO coordinated the use of individual assets and offered transmission services.

¶ 10 GridLiance’s assets were subject to MISO’s open access transmission tariff (MISO Tariff) because of the transfer of GridLiance’s functional control to MISO. Illinois service customers in a specified pricing zone paid the aggregate rate of the annual revenue requirement for all transmission owners in the zone to recoup costs associated with owning and operating transmission assets. Ameren and its customers pay approximately $6 million in costs annually regarding GridLiance’s MISO assets.

¶ 11 After GridLiance acquired the facilities, Ameren filed a complaint with the Commission against GridLiance, in Ameren Illinois Co. v. GridLiance Heartland LLC, Ill. Comm. Comm’n No. 20-0263 (Mar. 9, 2020). Ameren alleged that GridLiance failed to comply with multiple requirements under the Public Utilities Act (220 ILCS 5/1-101 et seq. (West 2018)). Ameren’s claims included that GridLiance was in violation for not lawfully operating as a public utility; transferring functional control of the EEI facilities to MISO without Commission approval; not providing the least-cost service and plant to Illinois customers; and for not possessing a CPCN.

¶ 12 On the same day that Ameren filed its complaint with the Commission, GridLiance filed a verified petition for declaratory ruling in GridLiance Heartland LLC, Ill. Comm. Comm’n No. 20-0264. GridLiance requested that the Commission determine whether it qualified as an Illinois public utility under section 3-105 of the Public Utilities Act (220 ILCS 5/3-105 (West 2018)) based on its acquisition of the EEI facilities and the transfer of their functional control to MISO.

¶ 13 Ameren filed a motion to intervene in GridLiance, Ill. Comm. Comm’n No. 20- 0264, and requested to consolidate the two pending matters. GridLiance then filed a motion to suspend Ameren, Ill. Comm. Comm’n No. 20-0263, until a determination was made by the Commission on whether GridLiance was a public utility. The Commission denied Ameren’s request to consolidate and granted GridLiance’s motion to suspend.

¶ 14 GridLiance then filed a motion to dismiss Ameren’s complaint for want of jurisdiction. GridLiance argued that the Commission did not have jurisdiction to consider Ameren’s petition and GridLiance was not subject to the statutory obligations because GridLiance was not a “public utility” under the Public Utilities Act (220 ILCS 5/3-105 (West 2018)). GridLiance claimed that it did not sell electricity to end-use customers in Illinois nor did it offer transmission assets for public use in Illinois. GridLiance additionally argued that res judicata applied where the circuit court previously determined that EEI’s ownership and operation of the transmission assets did not make EEI a public utility. See Electric Energy, Inc. v. Illinois Commerce Comm’n, No. 91-MR-175 (Cir. Ct. Sangamon County, Aug. 28, 1991).

Free access — add to your briefcase to read the full text and ask questions with AI

Gridliance Heartland LLC v. The Illinois Commerce Commission, 2023 IL App (5th) 230073-U (Ill. Ct. App. 2023).

2023 IL App (5th) 230073-U (Gridliance Heartland LLC v. The Illinois Commerce Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Arvia v. Madigan
809 N.E.2d 88 (Illinois Supreme Court, 2004)
Downing v. Chicago Transit Authority
642 N.E.2d 456 (Illinois Supreme Court, 1994)
People Ex Rel. Burris v. Progressive Land Developers, Inc.
602 N.E.2d 820 (Illinois Supreme Court, 1992)
River Park, Inc. v. City of Highland Park
703 N.E.2d 883 (Illinois Supreme Court, 1998)
Mississippi River Fuel Corp. v. Illinois Commerce Commission
116 N.E.2d 394 (Illinois Supreme Court, 1953)
Commonwealth Edison Co. v. Illinois Commerce Commission
937 N.E.2d 685 (Appellate Court of Illinois, 2010)
Wilson v. Edward Hospital
2012 IL 112898 (Illinois Supreme Court, 2012)
Illinois Landowners Alliance, NFP v. Illinois Commerce Comm'n
2016 IL App (3d) 150099 (Appellate Court of Illinois, 2016)
Village of Bartonville v. Lopez
2017 IL 120643 (Illinois Supreme Court, 2017)
People ex rel. Madigan v. Wildermuth
2017 IL 120763 (Illinois Supreme Court, 2017)
Illinois Landowners Alliance, NFP v. Illinois Commerce Commission
2017 IL 121302 (Illinois Supreme Court, 2017)
Illinois Landowners Alliance, NFP v. Illinois Commerce Comm'n
2017 IL 121302 (Illinois Supreme Court, 2018)
Highland Dairy Farms Co. v. Helvetia Milk Condensing Co.
139 N.E. 418 (Illinois Supreme Court, 1923)
Iowa RCO Ass'n v. Illinois Commerce Commission
409 N.E.2d 77 (Appellate Court of Illinois, 1980)