Gridliance Heartland LLC v. The Illinois Commerce Commission

2023 IL App (5th) 230073-U
CourtAppellate Court of Illinois
DecidedDecember 26, 2023
Docket5-23-0073
StatusUnpublished

This text of 2023 IL App (5th) 230073-U (Gridliance Heartland LLC v. The Illinois Commerce Commission) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gridliance Heartland LLC v. The Illinois Commerce Commission, 2023 IL App (5th) 230073-U (Ill. Ct. App. 2023).

Opinion

NOTICE 2023 IL App (5th) 230073-U NOTICE Decision filed 12/26/23. The This order was filed under text of this decision may be NO. 5-23-0073 Supreme Court Rule 23 and is changed or corrected prior to the filing of a Petition for not precedent except in the

Rehearing or the disposition of IN THE limited circumstances allowed the same. under Rule 23(e)(1).

APPELLATE COURT OF ILLINOIS

FIFTH DISTRICT ________________________________________________________________________

GRIDLIANCE HEARTLAND LLC, ) Appeal from the ) Illinois Commerce Petitioner-Appellant, ) Commission ) ) v. ) ) THE ILLINOIS COMMERCE COMMISSION and ) No. 20-0263 AMEREN ILLINOIS COMPANY, d/b/a ) Ameren Illinois, ) ) Respondents-Appellees. ) ________________________________________________________________________

JUSTICE CATES delivered the judgment of the court. Justices Boie and McHaney concurred in the judgment.

ORDER

¶1 Held: The Illinois Commerce Commission properly found that GridLiance Heartland LLC was a public utility, and res judicata did not apply. The Illinois Commerce Commission’s interim order directing GridLiance to seek a certificate of public convenience and necessity and by reopening the proceeding after its determination was not in error.

¶2 The petitioner, GridLiance Heartland LLC (GridLiance), appeals directly from an

interim order of the Illinois Commerce Commission (Commission), dated November 17,

2022, and subsequent denial of rehearing, dated January 5, 2023. The Commission found

in its interim order that GridLiance met the definition of a public utility as defined in section 1 3-105 of the Illinois Public Utilities Act (220 ILCS 5/3-105 (West 2022)). Based on this

finding, the Commission directed GridLiance to apply for a certificate of public

convenience and necessity (CPCN) and the Commission reopened the proceeding. We

affirm the Commission’s order.

¶3 I. BACKGROUND

¶4 In August of 2018, GridLiance entered into a purchase agreement with Electric

Energy, Inc. (EEI) for transmission assets which consisted of two substations in Joppa,

Illinois, and six connecting 161 kilovolt transmission lines that extended into Kentucky.

The Illinois portion of the facilities were in Ameren Illinois Company d/b/a Ameren

Illinois’s (Ameren) authorized service territory and connected to Ameren’s electric

transmission and distribution facilities.

¶5 After entering into the purchase agreement and prior to acquiring the EEI facilities,

GridLiance petitioned the Commission in GridLiance Heartland LLC, Ill. Comm. Comm’n

No. 18-1617 (Oct. 12, 2018), for a certificate of public convenience and necessity (CPCN)

under section 8-406(a) of the Public Utilities Act. 220 ILCS 5/8-406(a) (West 2018). The

CPCN would authorize GridLiance to own, control, operate, and manage the EEI facilities

for public use, and to provide public utility electric transmission service over the facilities.

GridLiance had argued that it should qualify as a public utility because, unlike EEI,

GridLiance would offer non-discriminatory service on the EEI transmission facilities to

“eligible customers,” including entities that would supply power to “end users” in Illinois.

¶6 Ameren intervened in GridLiance, Ill. Comm. Comm’n No. 18-1617, and argued

that GridLiance was not a public utility or eligible for a CPCN. Ameren claimed that a 2 determination could not be made on whether GridLiance was a public utility prior to the

acquisition of the EEI facilities. On September 6, 2019, GridLiance withdrew its petition.

The Commission subsequently dismissed GridLiance, Ill. Comm. Comm’n No. 18-1617

(Sept. 18, 2019) without determining whether GridLiance was a public utility under section

3-105 of the Public Utilities Act (220 ILCS 5/3-105 (West 2018)).

¶7 GridLiance and EEI had also petitioned the Federal Energy Regulatory Commission

(FERC) for approval of the GridLiance acquisition of the EEI facilities. FERC issued an

order on August 28, 2019, denying, without prejudice, GridLiance’s application. FERC

found that GridLiance and EEI failed to demonstrate that the acquisition was consistent

with the public interest because it would adversely impact customers’ rates. GridLiance

filed a subsequent application. On January 31, 2020, FERC conditionally approved

GridLiance’s acquisition of the EEI facilities subject to rate mitigation measures.

GridLiance accepted the conditions.

¶8 GridLiance acquired the facilities from EEI on February 29, 2020. GridLiance

transferred functional control of four transmission lines and associated facilities to the

Midcontinent Independent System Operator, Inc. (MISO), a non-profit, non-stock

corporation that was a Regional Transmission Organization (RTO).

¶9 MISO managed the region’s power grid which was approximately 65,000 miles of

interconnected high-voltage transmission line. MISO additionally operated an energy and

ancillary service market for approximately 200,000 megawatts of power generating

resources. GridLiance, as an owner of transmission assets, continued to own and maintain

3 its assets while MISO coordinated the use of individual assets and offered transmission

services.

¶ 10 GridLiance’s assets were subject to MISO’s open access transmission tariff (MISO

Tariff) because of the transfer of GridLiance’s functional control to MISO. Illinois service

customers in a specified pricing zone paid the aggregate rate of the annual revenue

requirement for all transmission owners in the zone to recoup costs associated with owning

and operating transmission assets. Ameren and its customers pay approximately $6 million

in costs annually regarding GridLiance’s MISO assets.

¶ 11 After GridLiance acquired the facilities, Ameren filed a complaint with the

Commission against GridLiance, in Ameren Illinois Co. v. GridLiance Heartland LLC, Ill.

Comm. Comm’n No. 20-0263 (Mar. 9, 2020). Ameren alleged that GridLiance failed to

comply with multiple requirements under the Public Utilities Act (220 ILCS 5/1-101 et seq.

(West 2018)). Ameren’s claims included that GridLiance was in violation for not lawfully

operating as a public utility; transferring functional control of the EEI facilities to MISO

without Commission approval; not providing the least-cost service and plant to Illinois

customers; and for not possessing a CPCN.

¶ 12 On the same day that Ameren filed its complaint with the Commission, GridLiance

filed a verified petition for declaratory ruling in GridLiance Heartland LLC, Ill. Comm.

Comm’n No. 20-0264. GridLiance requested that the Commission determine whether it

qualified as an Illinois public utility under section 3-105 of the Public Utilities Act (220

ILCS 5/3-105 (West 2018)) based on its acquisition of the EEI facilities and the transfer of

their functional control to MISO. 4 ¶ 13 Ameren filed a motion to intervene in GridLiance, Ill. Comm. Comm’n No. 20-

0264, and requested to consolidate the two pending matters. GridLiance then filed a motion

to suspend Ameren, Ill. Comm. Comm’n No. 20-0263, until a determination was made by

the Commission on whether GridLiance was a public utility. The Commission denied

Ameren’s request to consolidate and granted GridLiance’s motion to suspend.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arvia v. Madigan
809 N.E.2d 88 (Illinois Supreme Court, 2004)
Downing v. Chicago Transit Authority
642 N.E.2d 456 (Illinois Supreme Court, 1994)
People Ex Rel. Burris v. Progressive Land Developers, Inc.
602 N.E.2d 820 (Illinois Supreme Court, 1992)
River Park, Inc. v. City of Highland Park
703 N.E.2d 883 (Illinois Supreme Court, 1998)
Mississippi River Fuel Corp. v. Illinois Commerce Commission
116 N.E.2d 394 (Illinois Supreme Court, 1953)
Commonwealth Edison Co. v. Illinois Commerce Commission
937 N.E.2d 685 (Appellate Court of Illinois, 2010)
Wilson v. Edward Hospital
2012 IL 112898 (Illinois Supreme Court, 2012)
Illinois Landowners Alliance, NFP v. Illinois Commerce Comm'n
2016 IL App (3d) 150099 (Appellate Court of Illinois, 2016)
Village of Bartonville v. Lopez
2017 IL 120643 (Illinois Supreme Court, 2017)
People ex rel. Madigan v. Wildermuth
2017 IL 120763 (Illinois Supreme Court, 2017)
Illinois Landowners Alliance, NFP v. Illinois Commerce Commission
2017 IL 121302 (Illinois Supreme Court, 2017)
Illinois Landowners Alliance, NFP v. Illinois Commerce Comm'n
2017 IL 121302 (Illinois Supreme Court, 2018)
Highland Dairy Farms Co. v. Helvetia Milk Condensing Co.
139 N.E. 418 (Illinois Supreme Court, 1923)
Iowa RCO Ass'n v. Illinois Commerce Commission
409 N.E.2d 77 (Appellate Court of Illinois, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
2023 IL App (5th) 230073-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gridliance-heartland-llc-v-the-illinois-commerce-commission-illappct-2023.