Gregory v. Weber

626 P.2d 392, 51 Or. App. 547, 1981 Ore. App. LEXIS 2248
CourtCourt of Appeals of Oregon
DecidedApril 6, 1981
DocketA7809-15373 CA 15154
StatusPublished
Cited by3 cases

This text of 626 P.2d 392 (Gregory v. Weber) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gregory v. Weber, 626 P.2d 392, 51 Or. App. 547, 1981 Ore. App. LEXIS 2248 (Or. Ct. App. 1981).

Opinion

*549 WARREN, J.

Defendant appeals from a judgment for plaintiffs after trial to the court in an action for specific performance of certain terms a home construction contract and for damages. Plaintiffs sought a decree compelling defendant, a builder, to convey title to the property 1 and also prayed for damages for loss of use of the house and for the cost of having the house completed. The trial court awarded specific performance as requested and entered a judgment for the claimed damages. 2 Defendant assigns error to (1) the trial court’s decreeing specific performance but not ordering defendant to complete the building; (2) the finding that defendant was responsible for delays he claimed were beyond his control; (3) the improper use of rental value as a measure of loss of use; and (4) the court’s reliance on testimony by plaintiffs’ expert and the exclusion of testimony by defendant’s expert concerning costs of completion. We affirm.

The original contract to construct the home, executed in March, 1977, provided for plaintiffs to pay $65,000. Defendant’s position in a nutshell is that plaintiffs agreed in a telephone conversation in April, 1977, to pay him $20,000-30,000 for certain changes in the original plans, which consisted of switching the location of the *550 kitchen and living/dining rooms, and in the process deleting a patio and adding a pantry; adding a walk-in closet in the master bedroom; extending the garage two feet; and adding a fourth bedroom. Plaintiffs contend that most of these changes were agreed upon either in March, 1977, when the contract was signed, or in October, 1977, when a change order agreement for $945 was made covering finishing of a fourth bedroom and other work.

The trial judge stated his reasons for finding for plaintiffs:

"THE COURT: I may make some mistakes. I have done my best to try to figure out these various problems. First I’m going to grant the specific performance.
"I do it for about four different reasons, Mr. Weber. You may think that you are an experienced contractor, but I think you are extremely inexperienced in this job. I can’t accept the testimony that the Gregorys agreed to pay an additional 20- to $30,000. You had the second plans about April the 27th or 28th. It was obvious with 8- or 900 square feet in addition that you would have prepared a subsequent agreement for that sum of money, 20- to $30,000.
"I think you acquiesced in it. First if you’re going to need 20- or $30,000 more, certainly you would have borrowed that from Far West instead of leaving it at $52,000. I am sure you weren’t financially capable of picking up a 20- to $30,000 loss.
"Secondly, you indicated * * * that you just didn’t have time to prepare changes or addendums, but yet Exhibit 7 shows you wrote out an addendum for only $945, and yet you want the Court to believe that you — Gregorys had agreed to pay you 20-to $30,000. I can’t accept that.”

Defendant seeks to overturn the decree of specific performance for a number of reasons, none of which we find persuasive. Defendant contends that the usual weight should not be given to the trial court’s determination as to credibility, since one of the plaintiffs, Mr. Gregory, did not testify in person on the key issues. Not only did defendant have Mr. Gregory testify briefly at trial, but the trial judge stated for the record that there was an "understanding” that due to plaintiff’s bad health, his deposition would be used. Had defendant intended to challenge Mr. Gregory’s credibility, he need not have entered into the stipulation. *551 Additionally, as can be seen from the trial judge’s comments quoted above, the credibility question was resolved against defendant on his own testimony.

Defendant contends the evidence supports his position that the Gregorys had agreed to pay an additional $20,000-30,000 for the changes made in the original plans. Where the evidence is conflicting, this court will defer to the trial court’s findings unless the record gives a basis for weighing credibility differently than did the trial judge. Stoll v. Curl, 275 Or 487, 490, 551 P2d 1058 (1976). We agree with the trial court that it is highly unlikely that defendant would have memorialized in writing changes amounting to $945 and left unwritten a previous agreement for a change costing $20,000-30,000. We find no reason to disturb the trial court’s view of the evidence.

Defendant also contends that the contract was too vague and indefinite for specific performance since a sketch of the disputed remodelling changes was not produced by plaintiffs at trial. The sketch was not necessary to require defendant to convey title, the only act requested to be specifically performed. Defendant claims that specific performance is inequitable, because the original consideration for construction was grossly inadequate to cover the additional changes. Not only were the changes not quite as substantial as defendant would have us believe, 3 but defendant cannot prevail merely because he made a poor bargain. We agree with the trial court that defendant agreed to the modifications.

Finally, defendant seems to be requesting the court to allow or require him to complete the construction. Plaintiffs did not pray for that relief, and defendant did not, either in his pleadings or at trial, request to complete the house. The trial court remarked at the close of trial that he *552 gathered neither party wanted defendant to complete construction. There is no indication in the record that defendant then sought to be allowed to complete the construction himself. We do not interpret defendant’s estimate of costs of completion to be an offer to do the work. 4 We conclude the decree of specific performance was not in error.

With regard to delays in construction, we concur with the trial court’s conclusion that, even granting defendant four months’ credit for unavoidable delays, as the trial court did, the building should have been completed by January, 1978. Defendant asserts that plaintiffs limited their claim by their allegation in the complaint that the building was not completed by the agreed-upon time in August, 1977. But defendant never completed the building, and plaintiffs prayed for damages for loss of use up to the date of judgment. The only question is the proper measure of damages for plaintiffs’ loss of use of the residential building. Without citation of any authority, defendant contends that plaintiffs’ actual expenditure for alternative housing should be the measure of damages. Plaintiffs’ actual housing costs bear no logical relationship to the value of the premises had they been timely completed. They could have elected to live in a bungalow or a mansion, but that does not bear on the value of the lost use. The most convenient index of the value of loss of use in this situation is rental value, despite plaintiffs’ intention to reside in the house.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ambrose v. Biggs
509 N.E.2d 614 (Appellate Court of Illinois, 1987)
Marshall v. Karl F. Schultz, Inc.
438 So. 2d 533 (District Court of Appeal of Florida, 1983)
UNITED STATES NAT. BANK OF OR. v. Caldwell
655 P.2d 180 (Court of Appeals of Oregon, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
626 P.2d 392, 51 Or. App. 547, 1981 Ore. App. LEXIS 2248, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gregory-v-weber-orctapp-1981.