Gregory v. Baer

149 F.2d 411, 1945 U.S. App. LEXIS 2607
CourtCourt of Appeals for the Fourth Circuit
DecidedMay 11, 1945
DocketNo. 5359
StatusPublished
Cited by1 cases

This text of 149 F.2d 411 (Gregory v. Baer) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gregory v. Baer, 149 F.2d 411, 1945 U.S. App. LEXIS 2607 (4th Cir. 1945).

Opinion

SOPER, Circuit Judge.

This is an appeal from a judgment for the defendants for breach of two contracts by the plaintiff. The controversy arose in a suit by the plaintiff to recover from the defendants for lumber sold to them, and for inspection fees advanced by him under the contracts. The plaintiff is a manufacturer of lumber with a saw mill in North Carolina; the defendants are dealers in hardwoods in Baltimore, who manufacture one-half the lumber they sell and buy the remainder in the open market, preferably under logging contracts. The defendants counterclaimed for failure of the plaintiff to deliver all the lumber called for by the contracts. The referee found that the defendants owed the plaintiff $2,352.39 for lumber delivered and $760 for inspection fees, with interest on both amounts, and also that the plaintiff had broken the contracts by insufficient deliveries, but that his breaches had been waived by the defendants. The District Judge affirmed the referee’s first conclusion but reversed the second, and finding no waiver by the defendants, rendered a judgment in their favor for $10,700 with interest less the amount of the defendant’s indebtedness to the plaintiff. No question is raised on this appeal in regard to the indebtedness due and owing by the defendants to the plaintiff. The controversy is confined to the breaches of the contracts by the plaintiff and to the contention that these breaches were waived by the defendants.

On October 4, 1935 the plaintiff entered into a contract with the owners of 400 acres of land known as the Skinner and Toxey tract, for the sale and logging of the growing timber thereon. The contract contained no express limitation on the time when the timber should be cut from this tract. On January 31, 1936 the plaintiff, acting through an agent, sold certain kinds of the timber to be cut from this tract to the defendants at certain prices. The aggregate estimated quantities thereof contemplated to be cut were stated to be from approximately 3,400,000 to approximately 4,500,000 feet. It was agreed that the title to the lumber when manufactured should pass to the defendants, subject to the plaintiff’s equity therein, and that it should be piled in a yard to be leased to the defendants who agreed to advance to the plaintiff $10 per thousand feet for the timber when it had been graded and inspected. Very little timber was cut under this contract because the plaintiff’s sawmill burned down in 1936.

On January 14, 1937 a new contract between the parties was entered into for the same timber on similar terms with revised prices, wherein the same estimated quantities were set out and it was stated that the plaintiff was “not bound to deliver more than all the timber produced” by him from the tract. Pursuant to this contract the plaintiff began operations in August, 1937 and delivered to the defendants all the lumber he cut from the tract, amounting to 2,217,839 feet. He ceased operations on August 31, 1938.

He was compelled to desist by reason of injunctions obtained by landowners who established title to some of the lands comprised within the outlines of the tract. He notified the defendants of the situation but said he would continue to cut the timber on the tract as soon as he could re-enter, and would notify defendants when the litigation ended. All of the injunctions, with the exception of one relating to one small tract, were dissolved prior to November 1, 1940. But the defendants had no knowledge of this fact, as the judge found, since [413]*413the plaintiff at various times between August 31, 1938 and November 1, 1940 told the defendants that the injunctions were still in effect and that he could not re-enter.

On June 27, 1939 the parties entered into another contract for the sale of all of certain kinds of lumber to be cut from a tract in North ' Carolina known as the Mitchell tract which was purchased by the plaintiff for $6,000 of which the defendants advanced $4,000. The quantities to be cut were estimated to be not less than 650,000 feet nor more than 1,000,000 feet of lumber. Provisions similar to those in the other contracts with reference to the manufacture of the lumber, the passage of the title and cash advances were inserted. The prices were specified and the defendants agreed to start immediately to manufacture the lumber and to continue as speedily as the weather would permit and to complete the manufacture within twelve months. In September, 1940 the plaintiff notified the defendants that he had sawn all the timber off the land and was going to sell it for pasture. At that time he had delivered 444,785 feet of lumber under the contract and there remained 245,000 feet of merchantable timber still uncut.

On November 1, 1940 during unsuccessful negotiations for a contract covering timber on a third tract, the plaintiff advised the defendants that he would saw no more lumber for them under any contract, and since that date,'the plaintiff has refused to saw any lumber of any kind for the defendant. The conclusion on this state of facts reached by the District Judge is contained in the following finding of the court: “That on or about November 1, 1940 the plaintiff breached his contract with the defendants, both with respect to the Skinner and Toxey tract and the Mitchell tract. That, at said time, and consistently thereafter, the plaintiff advised the defendants that he was through sawing any lumber for them, that he was absolutely finished and would saw no more lumber for defendants under any contract, and that he was not going to deliver another stick of timber to the defendants. That the plaintiff did not thereafter -saw any timbér or lumber for the defendants. That the difference at said time between the contract price and the market price of lumber of the kind and quality contemplated by said two contracts, at the place of contemplated delivery, was an average of $10 per M. feet —the market price being this average amount higher than the contract price.”

The court also found that there remained uncut and available to the plaintiff 825,000 feet of standing timber on the Skinner and Toxey tract and 245,000 feet on the Mitchell tract and that through the failure of the plaintiff to cut and deliver these amounts the defendants had suffered a loss of $10,700.

We consider first the objections raised by the plaintiff to the finding that he was short in his deliveries under both contracts. He contends that he was not obligated by his contract on the Skinner and Toxey tract to deliver more than the amount of timber, to wit, 2,217,839 feet, which he actually cut and delivered, although 825,000 feet remained uncut, because the contract provided that he was not bound to deliver more than all the lumber produced by him from the tract. In short, he contends that he was at liberty to discontinue the manufacture and delivery of lumber from the tract at any time no matter how small the amount already cut and delivered had been. We think that this interpretation of the contract is not reasonable. It was expressly stated in the document that it contemplated approximately from 3,400,000 to 4,500,000 feet of lumber and it is obvious from the surrounding circumstances that the amount of timber to be sawn and delivered was of material importance not only to the sawmill man, who was obliged to set up his equipment on the tract and to employ laborers at the. work, but also to the defendant lumber dealer who needed substantial quantities for its business. The qualification which limited the plaintiff’s obligation to deliver to the amount produced by him was obviously inserted to protect him against an overestimate of the quantity of timber on the land.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
149 F.2d 411, 1945 U.S. App. LEXIS 2607, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gregory-v-baer-ca4-1945.