Gregory Supply Co. v. Calacci

CourtVermont Superior Court
DecidedAugust 11, 2004
DocketS0585
StatusPublished

This text of Gregory Supply Co. v. Calacci (Gregory Supply Co. v. Calacci) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gregory Supply Co. v. Calacci, (Vt. Ct. App. 2004).

Opinion

Gregory Supply Co. v. Calacci, No. 585-03 CnC (Katz, J., Aug. 11, 2004)

[The text of this Vermont trial court opinion is unofficial. It has been reformatted from the original. The accuracy of the text and the accompanying data included in the Vermont trial court opinion database is not guaranteed.]

STATE OF VERMONT SUPERIOR COURT Chittenden County, ss.: Docket No. 585-03 CnCiv

GREGORY SUPPLY CO.

v.

ERIC CALACCI and ANNIE CALACCI

FINDINGS OF FACT, CONCLUSIONS OF LAW AND NOTICE OF DECISION

On the basis of evidence presented at trial, the following decision is announced.

FINDINGS OF FACT 1. Plaintiff Gregory Supply operates a lumber yard and building supply operation in Bulrington. Eric Calacci has developed a business as a home builder, starting with renovations and additions, but more recently progressing to complete homes.

2. Calacci began purchasing more and more of his materials from Gregory Supply, and eventually opened an account there. The account agreement made him personally liable for materials purchased, including reasonable attorney fees and collection costs.

3. Calacci is now married to Annie Calacci. She helps him in the business, but never signed the account agreement with Gregory. The two began planning a new home in Williston. They perused magazines featuring drawings of different styles and sizes of houses, eventually selected one, and then ordered the plans for it.

4. Those house plans came with a “materials list,” which Calacci eventually submitted to Gregory Supply, together with the detailed drawings. He did so for the purpose of getting a dollar amount representing the required materials, which he could then take to his bank to obtain a mortgage. The process of estimating the amount of materials, and then their cost, is sometimes called “doing a take off.” Often, it is done from drawings, as they are the only documentary source. But here, there was no need for Gregory’s personnel to do a take off from drawings. The architects who had prepared the drawings had also prepared the materials list which Calacci submitted. It would be a useless expenditure of effort for Gregory or any other materials supplier to go through the arduous task of estimating requisite amounts of different materials, when the actual designer has already done that in the form of a materials list. Gregory’s list of required materials, and prices, is on a document featuring the word “quote.” PL EX 2. The prices there quoted are retail, although a homebuilder with an account and some credit history, such as Calacci, could probably expect somewhat better prices, at least some of the time on some of the items. However, quoting the prices retail is an advantage to someone in Calacci’s position, as it suggests to the bank formulating a mortgage offer, that the house may be worth somewhat more than Calacci might actually need to build it.

5. Calacci testified he was told by the Gregory estimator told him “Don’t worry about prices, they are all high.” He further testified that defendants’ “dispute is not with the unit pricing, but with the quantities.”

6. It is apparent from the Gregory pricing document that quantities were taken directly from the material list—they are all identical. Calacci, however, testified that he “flipped through the materials list, but that there was no reason for me to read it.”

7. At no time did Calacci ever actually order the list of materials, sufficient to build an entire house. Of course, Gregory never delivered an entire house worth of materials at one time. Instead, after the mortgage was approved, the site work completed, the foundation put in place, Calacci began to purchase what he needed, as he needed it.

8. The quantity of material necessary to complete the house is influenced by the experience, ability and motivation of the carpenter who is doing the actual construction. An inexperienced carpenter may well waste more than an experienced, but always cutting from large pieces, instead of keeping track of scraps that are available. The evidence does not permit the court to know if waste was an issue on this job.

9. During construction, Calacci departed from the original plans. Specifically, he abandoned the truss roof system they contain, and built his roof with lumber rafters. This obviously has an influence on quantity and price.

10. The actual quantity of material ordered by Calacci from Gregory and delivered by it to this personal home construction site differed very substantially from the architect’s material list, and therefore from the quantities on which Gregory gave its original price. This is tabulated on PL EX 4. Some of the larger examples include: C 131 sheets tongue and groove floor underlayment, instead of the 105 on the material list and “quote;” C 16 pieces of 2x12x18' spruce, instead of three; C 568 pieces of 2x6x 104-5/8 spruce instead of 250. There was no showing that any of the quantities claimed delivered by Gregory for this project are incorrect.

11. There was never any agreement, either express or implied, that Gregory would deliver strictly the materials quantities on the original list submitted by Calacci and quoted by it. Rather, it was always the understanding of these parties that Calacci would order what he needed and Gregory would deliver what he ordered.

12. The unfortunate reality of this construction project is that it ended up costing significantly more than defendant anticipated. The well cost more than expected. Of course the materials ordered from Gregory cost more than the original pricing document, although the actual prices were often lower. The problem surfaced when Annie Calacci went over monthly statements from Gregory and finally realized that they were running well beyond the price of the original pricing document.

13. Martha Phillips, bookkeeper for Gregory, dealt with Annie Calacci on accounting issues.

14. $40,532 is the present balance due.

CONCLUSIONS OF LAW

A. To hold Gregory to the total material price of its original document would be unfair, and stretching it beyond what the parties could have intended its meaning to be, or reasonably relied on at the time. Morrisseau v. Fayette, 164 Vt. 358, 366 (1995) (absent ambiguity, contract interpretation is a matter of law). Calacci never promised to buy every item from Gregory. There was no contract requiring him to do so. Material prices can be expected to fluctuate.

B. To hold Gregory to the total material quantity, or count, of its original document would be unfair. The original projection of amount of material comes directly from the document submitted by Calacci. Why should Gregory go through the uncompensated task of taking off quantities from the drawings, when it is given a materials list by the architect who made those drawings? If anything, one would expect the architect’s takeoff to be more accurate.

C. To hold Gregory to the material quantity, or count, or its original document would be unfair for the additional reason that the amounts ordered by Calacci and delivered by Gregory varied greatly from those on the architect’s material list and Gregory’s original pricing document.

D. From the starting point of delivering a “materials list” and asking for a price to bring to the bank, defendants’ position morphs into one of viewing the resulting price to constitute a promise and undertaking to deliver all the materials for that price, despite the fact that Mr. Calacci actually ordered a quite different quantity of those materials.

E. Defendants rest their case on the word “quote” in that original pricing document.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morrisseau v. Fayette
670 A.2d 820 (Supreme Court of Vermont, 1995)
Sargent v. Gagne
147 A.2d 892 (Supreme Court of Vermont, 1958)
Dj Painting, Inc. v. Baraw Enterprises, Inc.
776 A.2d 413 (Supreme Court of Vermont, 2001)
Wilson v. Alexander
428 A.2d 1089 (Supreme Court of Vermont, 1981)
Hedges v. Schinazi
481 A.2d 1046 (Supreme Court of Vermont, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
Gregory Supply Co. v. Calacci, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gregory-supply-co-v-calacci-vtsuperct-2004.