Greg Bondy, V. Dana Kuchan

Court of Appeals of Washington·Decided November 9, 2021·No. 54616-7·Unpublished

Opinion

Filed

Washington State

Court of Appeals

Division Two

November 9, 2021

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II

GREG BONDY, and KANDU ENTERPRISE, No. 54616-7-II LLC, a Washington limited liability company,

Respondents,

v. UNPUBLISHED OPINION

DANA RAY KUCHAN, and ‘JANE DOE’ KUCHAN, a married couple, and KUCHAN CONSTRUCTION COMPANY, INC., a Washington Corporation,

Appellants.

MAXA, J. – Dana Kuchan and Kuchan Construction Co. (hereinafter Kuchan) appeal the trial court’s judgment in favor of Greg Bondy and Kandu Enterprise, LLC (hereinafter Bondy) following a bench trial in which Kuchan was found liable for breach of contract arising from a construction project.

Bondy, a general contractor, hired Kuchan as a subcontractor to demolish a garage that Bondy had contracted to rebuild. Bondy specifically instructed Kuchan to remove the garage walls without disturbing the garage’s foundation. However, Kuchan removed the garage’s stem wall and the slab, eliminating any use of the existing foundation. Bondy then had to install a new foundation, which required him to obtain a new building permit for work on the garage. Bondy claimed that he incurred over $20,000 in expenses that would not have been incurred but

for Kuchan’s removal of the slab. The trial court found Kuchan liable for breach of contract and awarded Bondy the full amount of his claimed damages.

Kuchan does not challenge the trial court’s finding that he breached his contract with Bondy. However, he argues that the trial court erred in concluding that his breach caused Bondy’s claimed damages. He asserts that Bondy would have incurred the additional expenses even if Kuchan had not removed the stem wall and slab. We hold that substantial evidence supports the trial court’s finding regarding the amount of Bondy’s damages. Accordingly, we affirm the trial court’s judgment.

FACTS

Background In 2015, Bondy was hired as a general contractor to perform work on a house in Port Angeles. A prior contractor had obtained a building permit for the work in 2013, which was based on the use of the existing foundation slab for the garage. Bondy hired Kuchan as a subcontractor to remove the garage and perform other work.

Bondy told Kuchan to remove the garage walls without disturbing the stem wall or the garage slab because the homeowners planned to rebuild the garage on the existing concrete footprint. Despite this direction, Kuchan tore out the stem wall and the slab, thereby eliminating any use of the existing foundation. Because Bondy’s work on the garage now included constructing a new foundation, he had to obtain a new building permit for the work.

Bondy filed a lawsuit against Kuchan for breach of contract. Bondy alleged that he suffered damages because he had to replace the garage foundation, incurring additional architectural, engineering, permitting, and labor costs to complete the work.

The case went to mandatory arbitration, where the arbitrator awarded Bondy $9,030 in damages. Kuchan requested a trial de novo. Trial and Judgment The case proceeded to a bench trial. Bondy testified that he planned to remove the roof and framing of the old garage so he could rebuild a new garage using the existing foundation. He hired Kuchan to remove the roof and framing. Although he directed Kuchan not to remove the stem wall and the slab, Kuchan removed them. The removal of the foundation eliminated any “grandfather” privileges related to the 2013 permit. Before Kuchan removed the foundation, it was intact without any cracks or defects.

Bondy testified that he had to incur additional expenses to complete his work on the garage because the foundation had to be replaced, and he produced invoices to support his claim. The expenses related to (1) architectural and engineering costs for the new design and the cost of the new building permit, (2) an electrical panel that had to be installed in the garage, (3) materials and labor to construct the new foundation, (4) replacement of a sidewalk that was removed along with the foundation, and (5) the hours of Bondy and a bookkeeper relating to the additional work. At least some of the additional expenses were incurred because of the loss of the grandfather privileges.

The total additional expenses Bondy claimed were over $21,000, although Bondy agreed that some of his claimed time was litigation related and should not have been included. Bondy stated that none of these expenses would have been incurred if the foundation had been left in place. The costs did not include any work that was planned before removal of the slab.

On cross-examination, Bondy confirmed that the 2013 building permit application described the work to be performed on the garage as “rebuild roof structure.” Ex. 12. The

permit did not describe demolishing and replacing the garage. On the other hand, the 2015 permit application described the work as “[g]arage reconstruction.” Ex.13.

Kuchan testified that he removed the slab because there was a void underneath and there was no steel rebar in the slab. He did not think that the slab was adequate for a new garage.

Don Schuba, the project designer, testified that the stem wall and the slab seemed to be in good shape. The plans Schuba prepared to obtain the 2013 building permit included using the existing foundation. The foundation was adequate for the project and had no defects or sign of failure. The 2013 building permit allowed the use of the existing foundation.

On cross-examination, Schuba confirmed that the 2013 building permit application only referenced rebuilding the garage roof, not demolishing the entire structure. He also stated that his plans called for use of the existing walls, but with modifications. Later, he testified that the 2013 permit contemplated rebuilding the walls to accommodate the new roof structure. Although the permit application did not mention the walls, the drawings he submitted showed what he intended when seeking the permit.

Jim Lierly, the building official for the City of Port Angeles, testified that the 2013 building permit was for rebuilding the garage roof structure and would not include demolition and reconstruction of the garage. However, he then admitted that without looking at the actual plans, he would have to speculate about what was allowed by the 2013 permit.

In closing argument, Kuchan argued that the 2013 permit did not allow Bondy to remove the walls of the garage as he planned. Kuchan asserted that as a result, Bondy would have been required to obtain a new permit and incur the additional expenses he claimed to perform the planned work even if Kuchan had not removed the stem wall and slab. Therefore, Kuchan argued that any breach of contract did not cause Bondy any damages.

Following trial, the trial court filed a memorandum opinion ruling in Bondy’s favor. The court concluded that Kuchan was liable for breach of contract and Bondy was entitled to damages in the amount of $20,609.72.

The trial court subsequently entered findings of fact, including the following:

16. Plaintiff Bondy had been a contractor for approximately 20 years and had done a lot of concrete work and inspections of concrete, and he determined that the existing stem wall and slab were intact, not cracked and appeared adequate for future use.

17. The foundation was in good shape, adequate, and the right size.

18. The City of Port Angeles granted a permit based upon using the [foundation]

in the plans.

....

22. As a result of Defendant’s removal of the slab and stem foundation for the garage, Plaintiff dedicated $20,609.72 to consequential cost to complete the project.

23. Defendant Dana Kuchan and Kuchan Construction Company, Inc. are liable for the breach.

....

26. None of [the] costs claimed by Plaintiff would have been incurred if the slab and stem wall were left in place (Bondy). Plaintiff would not have incurred these costs claimed for damages but for Defendant’s removal of the stem wall and slab (Bondy).

Free access — add to your briefcase to read the full text and ask questions with AI

Greg Bondy, V. Dana Kuchan, (Wash. Ct. App. 2021).

Greg Bondy, V. Dana Kuchan (Greg Bondy, V. Dana Kuchan) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Floor Exp., Inc. v. Daly
158 P.3d 619 (Court of Appeals of Washington, 2007)
Bearden v. McGill
415 P.3d 100 (Washington Supreme Court, 2018)
Floor Express, Inc. v. Daly
138 Wash. App. 750 (Court of Appeals of Washington, 2007)
Columbia Park Golf Course, Inc. v. City of Kennewick
160 Wash. App. 66 (Court of Appeals of Washington, 2011)