Greer v. Town Construction Co.

92 So. 3d 360, 2011 La.App. 1 Cir. 1360, 2012 WL 982414, 2012 La. App. LEXIS 387
CourtLouisiana Court of Appeal
DecidedMarch 23, 2012
DocketNo. 2011 CA 1360
StatusPublished

This text of 92 So. 3d 360 (Greer v. Town Construction Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greer v. Town Construction Co., 92 So. 3d 360, 2011 La.App. 1 Cir. 1360, 2012 WL 982414, 2012 La. App. LEXIS 387 (La. Ct. App. 2012).

Opinion

HIGGINBOTHAM, J.

1 Jonathan K. and Rene P. Greer (“the Greers”) brought suit for damages arising out of an allegedly defective foundation in their home that had been built pursuant to a construction contract between them and Town Construction Company, Inc. (“Town Construction”).1 The Greers appeal a district court judgment sustaining Town Construction’s peremptory exception on the basis of res judicata due to a prior arbitration proceeding. For the reasons set forth below, we reverse and remand.

BACKGROUND

In April 2004, the Greers entered into a contract with Town Construction for the construction of their residence at 6929 Woodstock in Baton Rouge, Louisiana. At some point, a dispute arose between the Greers and Town Construction concerning costs, change orders, workmanship, and timeliness issues. In March 2006, pursuant to the construction contract, Town Construction filed a demand for the unpaid contract balance by arbitration through the American Arbitration Association (“AAA”). The Greers filed a counterclaim for damages in the arbitration proceeding, asking for reimbursement, repairs, and diminution in the value of their home due to alleged construction defects and pursuant to the Louisiana New Home Warranty Act (“LNHWA”).2 In their counterclaim, the Greers specifically alleged that their home had mold/mildew problems and cracks in the walls that were “growing at an alarming rate” and were allegedly “due to a structural defect in the foundation” or “faulty construction of the home[’]s foundation.”

|sThe arbitration proceeding took place in two phases, the first in November 2006 and the second in March 2007. Prior to each phase, the parties submitted their claims to the arbitrator. The arbitrator heard and considered evidence regarding the Greers’ various claims, including the alleged damage to the foundation of the Greer home, cracks in the walls, structural deficiencies in the roof framing system, and mold/mildew problems. On April 30, 2007, the arbitrator issued an arbitration award to Town Construction that amounted to the full contract balance plus extra costs and interest. The arbitrator also issued a damage award to the Greers on their counterclaim for reimbursement, repair, or replacement for “Structural Claims (including] foundation)” damages. The arbitrator specifically denied all other claims and counterclaims made by the parties in both phases of the arbitration. Rather than seeking a modification in the district court, the Greers filed a request with the AAA arbitrator for modification of the assessment of costs and fees that had been rendered solely against them. The Greers did not, however, seek any modification or correction regarding the actual merits of the arbitration award. The rec[362]*362ord does not reflect the outcome of the Greers’ costs/fees modification request with the AAA, and the record is void, as well, of any confirmation of the arbitration award by the district court.

Three years after the arbitration award was issued, the Greers discovered additional cracks in the floors and walls of their home. They filed this lawsuit against Town Construction in the district court on May 27, 2010. The Greers sought damages in the form of repair costs and diminution in the value of their home as a result of an alleged “defective foundation” in their home. Town Construction responded to the Greers’ lawsuit by filing a peremptory exception raising the objection of res judicata, maintaining that the Greers’ petition should be dismissed because the claims between the parties had already been litigated through an arbitration process. After a hearing, the district court sustained the 1 ¿exception and dismissed Town Construction from the Greers’ lawsuit on December 15, 2010. The Greers appealed. The only issue on appeal is whether the district court erred in sustaining Town Construction’s exception of res judicata.

DISCUSSION

The doctrine of res judicata is codified in La. R.S. 13:4231, which provides as follows:

Except as otherwise provided by law, a valid and final judgment is conclusive between the same parties, except on appeal or other direct review, to the following extent:
(1) If the judgment is in favor of the plaintiff, all causes of action existing at the time of final judgment arising out of the transaction or occurrence that is the subject matter of the litigation are extinguished and merged in the judgment.
(2) If the judgment is in favor of the defendant, all causes of action existing at the time of final judgment arising out of the transaction or occurrence that is the subject matter of the litigation are extinguished and the judgment bars a subsequent action on those causes of action.
(3) A judgment in favor of either the plaintiff or the defendant is conclusive, in any subsequent action between them, with respect to any issue actually litigated and determined if its determination was essential to that judgment. (Emphasis added.)

This statute explicitly applies only when there is a “valid and final judgment” between the parties. Official Comment (d) (1990) to La. R.S. 13:4231 further explains the requirement of a “valid and final judgment,” stating:

To have any preclusive effect a judgment must be valid, that is, it must have been rendered by a court with jurisdiction over subject matter and over parties, and proper notice must have been given.... The use of the phrase “final judgment” also means that the preclusive effect of a judgment attaches once a final judgment has been signed by the trial court. (Emphasis added.)

In a recent opinion with three dissenting views, the Louisiana Supreme Court considered the requirement of a “valid and final judgment” in the context of an unconfirmed arbitration award, holding that an unconfirmed arbitration award is not a “valid and final judgment,” because it was not “rendered by the court” and as |ssuch, the unconfirmed award has no res judicata effect. Interdiction of Wright, 2010-1826 (La.10/25/11), 75 So.3d 893, 897.3 In Wright, the supreme court illustrated the [363]*363distinction between an unconfirmed “arbitration award” and a “judgment” by examining the language of the Louisiana Binding Arbitration Law found in La. R.S. 9:4209, et. seq,,4 and concluding that the legislature intended for parties to seek judicial confirmation before an arbitration award would become a legally enforceable judgment. Id, 75 So.3d at 897. The supreme court further held that the power to issue a legally binding judgment cannot be delegated to nonjudicial personnel such as an arbitrator, because the Louisiana Constitution mandates independent judicial review before an arbitrator’s award can serve as the ground for a judgment that has res judicata effect. Id, 75 So.3d at 898; see La. Const. Art. V, § 1.

The record in this case reflects that both parties consented to the arbitration, that neither party objected to or questioned the merits of the arbitration award or the finality of the award, and that the parties apparently honored the arbitrator’s decision. As previously noted, the Greers filed a motion with the AAA arbitrator, | fiseeking to modify the arbitration award as to the assessment of costs and fees only, not as to the merits of the awards.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Craig v. Adams Interiors, Inc.
785 So. 2d 997 (Louisiana Court of Appeal, 2001)
Farmers Cotton Co., Inc. v. Savage
714 So. 2d 926 (Louisiana Court of Appeal, 1998)
Aucoin v. Gauthier
35 So. 3d 326 (Louisiana Court of Appeal, 2010)
National Tea Co. v. Richmond
548 So. 2d 930 (Supreme Court of Louisiana, 1989)
Glod v. Baker
755 So. 2d 910 (Louisiana Court of Appeal, 1999)
HOLLY & SMITH ARC., INC. v. St. Helena Congregate Facility
872 So. 2d 1147 (Louisiana Court of Appeal, 2004)
Hurley v. Fox
587 So. 2d 1 (Louisiana Court of Appeal, 1991)
Peter Vicari General Contractor, Inc. v. St. Pierre
831 So. 2d 296 (Louisiana Court of Appeal, 2002)
Kleinschmidt v. Lanza
45 So. 3d 1165 (Louisiana Court of Appeal, 2010)
Interdiction of Wright
75 So. 3d 893 (Supreme Court of Louisiana, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
92 So. 3d 360, 2011 La.App. 1 Cir. 1360, 2012 WL 982414, 2012 La. App. LEXIS 387, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greer-v-town-construction-co-lactapp-2012.