Greenwood v. Evergreen Mines Co.

19 N.W.2d 726, 220 Minn. 296, 1945 Minn. LEXIS 529
CourtSupreme Court of Minnesota
DecidedJune 29, 1945
DocketNos. 33,917, 34,075.
StatusPublished
Cited by15 cases

This text of 19 N.W.2d 726 (Greenwood v. Evergreen Mines Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greenwood v. Evergreen Mines Co., 19 N.W.2d 726, 220 Minn. 296, 1945 Minn. LEXIS 529 (Mich. 1945).

Opinion

Julius J. Olson, Justice.

Two cases founded upon identical facts were consolidated for trial in the court below and are so submitted here. We shall refer to the respective plaintiffs as Greenwood and Babbe, and to defendant village of Crosby as the village. Defendant Evergreen Mines Company is not involved here, since as to it both cases were dismissed.

Plaintiffs sought damages for blocking the outlet of Serpent Lake so as to raise the level thereof beyond high-water mark, thereby causing the flooding and damaging of their properties abutting on the lake.

Serpent Lake is a meandered and navigable body of water comprising approximately 1,300 acres. At the westerly end thereof it originally had its outlet in Serpent Creek within the area of the village. In 1917, the village closed the natural outlet and constructed in its place an open ditch some 250 to 300 feet downstream, thereby carrying the water westerly from the lake to the creek. A roadway there required the installation of a culvert to take the lake overflow to the creek, and a 42-inch culvert was installed. Some two or three years later, the village installed a 24-inch culvert in place of the open ditch which had formerly carried the water to the creek. Thus matters remained until 1927, *300 when the state highway department took over for state highway purposes the road under which the 42-inch culvert had been laid. The department filled in material along the lake shore, thereby widening the roadway to the east along the westerly shore of the lake. It installed a 36-inch intake culvert from the lake so as to connect with the village 42-inch intake culvert. From the time of the original construction of the new outlet and until 1938, no difficulty had been experienced in respect to the flow of water from the lake. These were normally rather dry years. But in the spring of 1938, the water of the lake gradually arose; and in 1942 and again in 1943, a substantial part of the Greenwood property was covered with water. During these dry years, with low outflow, property owners along the creek had appropriated the adjacent areas of the creek bed to various domestic uses. The village had installed culverts across at least five streets through which the creek flowed. These varied in size from one of only nine-inch diameter to ones as large as 18, 24, 30, and 36 inches in diameter.

After a thorough trial, the court submitted to the jury as questions of fact the issues of whether the village had filled in, obstructed, or dammed up the new culvert outlet and thereby raised the waters of the lake to a height in excess of its natural high-water mark. On that phase, the court said:

“The plaintiffs in these two cases are the owners of land bordering on Serpent Lake, and as owners of land abutting on Serpent Lake they were entitled to have the water of the lake maintained at the natural and ordinary level at all times.

“If the village of Crosby, acting through its officers or employes; caused the water to raise above its natural high-water mark to overflow and damage the property of plaintiffs, the village would be liable, and in that case your verdict should be for plaintiffs in some amount.

“It is the law that the natural high-water mark of Serpent Lake would extend to that part of the lake bed which the water has *301 occupied sufficiently long and continuously as to wrest it from vegetation and to destroy its value for other purposes.”

In the Greenwood case, the jury returned a verdict of $4,000 for the plaintiffs. In the Babbe case, the verdict read:

“We, the jury in the above entitled action, find for the Plaintiff [sic] and assess their damages in the sum of Nothing.”

When the jury reported its verdicts, the court asked the foreman, addressing the inquiry to each member of the jury; “* * * by that verdict do you mean that you found for the defendant?” There was some discussion, during which a member of the jury said:

“We found that there wasn’t any damage to speak of down there at Babbes’ place, and that’s the reason we didn’t allow anything for any damage. There wasn’t but a small amount there; it doesn’t amount to anything; it didn’t hurt his property; just a little lake shore washed out and away from there.

“The Clerk: Ladies and gentlemen of the jury, are these your verdicts ?

“Voices: Yes.

“The Clerk: And all of you?

“Voices: It is.”

In due season, the village moved for judgment notwithstanding or for a new trial in the Greenwood case. In the Babbe case, plaintiffs moved for a new trial. The village then moved for judgment notwithstanding also in the Babbe case. The court granted the motion of the village for judgment in each case, being 'of opinion, as expressed in its memorandum, that—

“From an examination of the entire record I am satisfied that the record fails to show that the village of Crosby failed to perform any legal duty imposed upon it by law or that it performed any affirmative act that constituted a material element or substantial factor in causing.the flooding of plaintiffs’ land.

“I am further satisfied that the proximate cause of the flooding of plaintiffs’ land was the negligence of the Minnesota State High *302 way Department in permitting an excessive stage of water to accumulate in Serpent Lake by its failure to keep its state highway culvert clear of obstructions.”

In the Greenwood case, plaintiffs have appealed from the judgment. In the Babbe case, plaintiffs appealed from the order denying their motion for new trial.

The decisive question here is whether the evidence, viewed in the light most favorable to plaintiffs Greenwood, is sufficient to present a jury issue. Since the court granted judgment non obstante, the rule to be applied is whether, as a matter of law, defendant was entitled to judgment on the merits. The question is not whether the trial court could or ought, in its discretion, to have granted a new trial, but whether, from the whole record, the evidence was such as to require a judgment for the moving party. Thom v. N. P. Ry. Co. 190 Minn. 622, 627, 252 N. W. 660, 662. Our cases are found in 3 Dunnell, Dig. & Supp. § 5085.

The fact issue upon which both causes depend is whether acts or omissions of the village were the proximate cause so as to constitute a material element in the rise of the water in the lake and as such were responsible for the resulting damage. On this phase the court charged (Record, p. 505, f. 1515) :

“These cases are based upon the claim the village was negligent in taking care of the water that flowed out of Serpent Lake, and obstructed the flow of such water. The village cannot be held liable in these cases unless the damage complained of was caused by the lack of reasonable care and skill on the part of the village in taking care of the water that flowed through this state culvert.”

And at p. 507, ff. 1519 and 1520:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Paynesville Farmers Union Cooperative Oil Co.
817 N.W.2d 693 (Supreme Court of Minnesota, 2012)
Witzman v. Lehrman, Lehrman & Flom
601 N.W.2d 179 (Supreme Court of Minnesota, 1999)
Joyce Witzman v. Bert M. Gross
Eighth Circuit, 1998
Chabot v. City of Sauk Rapids
422 N.W.2d 708 (Supreme Court of Minnesota, 1988)
Chabot v. City of Sauk Rapids
412 N.W.2d 371 (Court of Appeals of Minnesota, 1987)
Wilson v. Ramacher
352 N.W.2d 389 (Supreme Court of Minnesota, 1984)
Dunn v. County of Ramsey
184 N.W.2d 773 (Supreme Court of Minnesota, 1971)
F. Koehnen, Ltd. v. County of Hawaii
388 P.2d 214 (Hawaii Supreme Court, 1963)
Collins v. Wickland
88 N.W.2d 83 (Supreme Court of Minnesota, 1958)
McDonough v. Newmans Cloak & Suit Co.
77 N.W.2d 59 (Supreme Court of Minnesota, 1956)
Paul v. Faricy
37 N.W.2d 427 (Supreme Court of Minnesota, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
19 N.W.2d 726, 220 Minn. 296, 1945 Minn. LEXIS 529, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greenwood-v-evergreen-mines-co-minn-1945.