Greenwell v. A. v. Wills & Sons

239 S.W. 578, 210 Mo. App. 651, 1922 Mo. App. LEXIS 240
CourtMissouri Court of Appeals
DecidedMarch 11, 1922
StatusPublished
Cited by8 cases

This text of 239 S.W. 578 (Greenwell v. A. v. Wills & Sons) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greenwell v. A. v. Wills & Sons, 239 S.W. 578, 210 Mo. App. 651, 1922 Mo. App. LEXIS 240 (Mo. Ct. App. 1922).

Opinion

*654 BRADLEY, J.

T. J. and Chas. A. G-reenwell sued to recover damages to their crops alleged to have been caused by water negligently held on their lands. The cause was tried to a jury and resulted in a judgment for plaintiffs in the sum of $710, from which judgment defendants appealed.

Plaintiffs allege two grounds of negligence: (1) Negligence in and about constructing a dam across the ditch; and (2) in so negligently operating the boat that it sank, and the dams necessary to raise it caused or contributed to the damage. Plaintiffs state these grounds in their petition substantially as follows: (1) That during the times mentioned defendant drainage district was enlarging drainage ditch No. 6 and defendants A. Y. Wills & Sons were drainage contractors and as such contractors entered into a contract for enlarging said drainage ditch No. 6; that said drainage ditch No. 6 had theretofore been constructed, and lateral ditches leading from the land adjacent thereto had been constructed so as to drain the water from the adjacent land into said drainage ditch No. 6; that the lands mentioned were drained prior to the time complained of; that defendants in doing the work of enlarging said drainage ditch No. 6 placed a dam across said ditch so as to completely prevent the water from flowing down said ditch as it had previously done without leaving any' outlet for the water which had previously flowed down said ditch, and negligently and carelessly kept said dam in said ditch for a great period of time until the land cultivated by plaintiffs for the season of 1919 was completely flooded; that after the lands were flooded defendants cut a passageway around the dam so as to let part of the water that continued to accumulate in said ditch pass around said dam, but there was not sufficient passageway to lower and take the. water off the land.

(2) That it was the duty of defendants in enlarging said dainage ditch to do the work in a reasonably expeditions manner, and at all times leave sufficient passageway for the water so as to prevent the water *655 from flowing out of tlie laterals and overflow the land cultivated by plaintiffs and others; that defendant while doing the work of enlarging said ditch so negligently and carelessly conducted the management of the dredge boat with which said drainage ditch was being dug as to let said dredge boat sink, and in order to raise and repair said dredge boat defendants constructed two more dams across said drainage ditch, one just behind the dredge boat that was sunk, and one just in front, and used a large pump for the purpose of pumping out the water between the two dams so that they could get to the sunken boat and repair it; that the last two dams completely cut off all flow of water down said drainage ditch, and caused the water that would otherwise have flowed around the first dam from flowing down said ditch, and caused all of the water thus accumulated to spread out over the land cultivated by plaintiffs; that defendants through the negligent manner in which they conducted the enlarging of said drainage ditch and. repair of said dredge boat permitted the last two mentioned dams to remain across said ditch for near two months, so that all drainage was closed for about that period of time; that the passageway left for the water around the original dam being small, when the last two dams were opened the water that had accumulated on the land cultivated by plaintiffs could not run through said opening sufficiently fast to lower the water and take it off of said land until plaintiffs ’ corn had been damaged.

Wills & Sons answered by general denial. The district answered by a general denial, and a defense that Wills & Sons were independent contractors, and that in no event was it liable. No reply seems to have been filed to the new matter in the district’s answer, but no point is made in that respect.

Defendants brief their case separately, and make separate assignments, but in the main to the same effect. These assignments may be stated thus: (1) That the court erred in failing to direct a verdict for defendants; *656 (2) that the court erred in admitting evidence; (3) that the court erred in giving and refusing'; certain instructions. The defendants are interested in common for the most part. Their interest do not run counter except on the issue of an independent contractor, but the view we take of this cause makes it unnecessary to consider any except the first assignment.

. Should the court have directed a verdict for both defendants? The ditch in the drainage district was being enlarged, cleaned, etc., under sections 4531 et seq., Revised Statutes 1919. "Wills & Sons were awarded the contract for a portion of this work. The district was several miles in length, and the original ditch had been dug for several years. The old ditch was twenty feet wide with a ten or twelve foot bottom, and the new ditch was forty feet wide with a twenty foot bottom.

The clauses and provisions of the contract under which Wills & Sons were working which we think are pertinent here are as follows: ‘ ‘ The ditches herein provided for shall be constructed with machinery suitable for the work, dug to the depth and bottom width as directed by the engineer, and have side slopes as near as may be of one horizontal to one vertical. The excavated material shall be deposited about equally on each side of the ditches, in even uniform spoilbanks, leaving berms of such width between the outer slopes of the ditches and the spoil-banks as shown on the plans; provided, that unequal distribution of spoil-banks may be made by the contractor upon the written consent of the engineer. In the reconstruction or deepening of ditches all excavated material shall be deposited so that none of the material shall fall or flow upon the berm space as required by the plans and specifications.

The contractor will be permitted to hold water in the ditches for the purpose of floating dredeges at such elevations as the engineer from time to time may direct.

Where ditches pass through caving ground the contractor will be required to continue work with the equipment in use thereon until such time as the engineer shall *657 conclude and advise the contractor that it is not practical to complete the work, as per plans, after which time the contractor may be relieved of further responsibility for such portion of the work, and he will be paid for the portion of the required section left available; the district will be free to arrange with another contractor, or to provide other means for the construction of said work, or the engineer may require the contractor under this contract to excavate and construct a detour ditch at the contract price, or, if directed so to do, the said contractor shall furnish the labor and equipment and do such work in connection with such caving ground as may be required by the engineer .to complete such portion of the work on the cost plus percentage basis, as herein provided for extra work.

Openings shall be left in the spoil-bank for admission of surface water on each side of the ditches at all depressions where water might accumulate and at such other places as the engineer may direct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wood v. South River Drainage District
422 S.W.2d 33 (Supreme Court of Missouri, 1967)
City of Hardin v. Norborne Land Drainage District
232 S.W.2d 921 (Supreme Court of Missouri, 1950)
Sigler v. Inter-River Drainage District
279 S.W. 50 (Supreme Court of Missouri, 1925)
Johnson v. Inter-River Drainage District
257 S.W. 492 (Missouri Court of Appeals, 1924)
State Ex Rel. Hausgen v. Allen
250 S.W. 905 (Supreme Court of Missouri, 1923)
Weller v. Mulgrew & Sons Co.
192 N.W. 969 (North Dakota Supreme Court, 1923)
Southwestern Bell Telephone Co. v. Drainage District No. 8
247 S.W. 494 (Missouri Court of Appeals, 1923)
D'Arcourt v. Little River Drainage District
245 S.W. 394 (Missouri Court of Appeals, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
239 S.W. 578, 210 Mo. App. 651, 1922 Mo. App. LEXIS 240, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greenwell-v-a-v-wills-sons-moctapp-1922.