Greenpeace, Inc. v. Environmental Protection Agency

43 F.3d 701, 310 U.S. App. D.C. 50, 39 ERC (BNA) 2116, 1995 U.S. App. LEXIS 545, 1995 WL 10369
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 13, 1995
Docket93-1458, 93-1682, 93-1683
StatusPublished

This text of 43 F.3d 701 (Greenpeace, Inc. v. Environmental Protection Agency) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greenpeace, Inc. v. Environmental Protection Agency, 43 F.3d 701, 310 U.S. App. D.C. 50, 39 ERC (BNA) 2116, 1995 U.S. App. LEXIS 545, 1995 WL 10369 (D.C. Cir. 1995).

Opinion

Opinion for the court filed by Circuit Judge ROGERS.

ROGERS, Circuit Judge:

These petitions present one of several challenges by petitioners to various stages of the construction and operation of a hazardous waste incinerator owned and operated by Waste Technologies Industries (‘WTI”) in East Liverpool, Ohio. Three actions by the Environmental Protection Agency are challenged. First, in Petition No. 93-1458, Greenpeace, Inc., Alonzo Spencer, and Teresa Swearingen (together “Greenpeace”), seek review of the Regional Administrator’s letter of April 6, 1993, confirming that WTI had satisfied permit conditions for commencement of post-trial bum operations. Second, in Petition No. 93-1682, the City of Pittsburgh seeks review of the Regional Administrator’s letter of April 12, 1993, notifying WTI that it must comply with two additional limitations in its post-trial burn operations. Third, in Petition No. 93-1683, the City of Pittsburgh seeks review of the June 21,1993, *703 decision of the agency’s Environmental Appeals Board (“Appeals Board”) denying administrative review of the April 12th letter for lack of jurisdiction. Because the Resource Conservation and Recovery Act of 1976 (“RCRA”), 42 U.S.C. § 6976(b) (1988), limits judicial review to the EPA Administrator’s issuance, denial, modification, or revocation of a permit, and we conclude that none of the challenged actions issued, denied, modified, or revoked WTI’s permit, the court lacks jurisdiction, and we dismiss the petitions. 1 Hazardous Waste Treatment Council v. EPA, 910 F.2d 974, 976 (D.C.Cir.1990).

I.

Under the RCRA, every owner and operator of a hazardous waste treatment, storage, or disposal facility must obtain a permit. 42 U.S.C. § 6925(a). Pursuant to regulations promulgated by the Agency under the RCRA, a final permit to operate a hazardous waste incinerator is the culmination of several phases of operation. Id. § 6924(a); 40 C.F.R. § 270.62. The first phase follows construction and authorizes limited “shakedown” operations. 40 C.F.R. § 264.344(c)(1). The second phase requires that a newly-constructed hazardous waste incinerator conduct a “trial burn” designed to test emissions and provide data from which the Agency sets final operating conditions. Id. §§ 264.344(c)(2) & (c)(4), 270.62(b). A permit may authorize a third phase allowing a new hazardous waste incinerator to engage in limited commercial operations, or “post-trial burn operations,” prior to the Agency’s final modification of the permit to reflect trial bum results. Id. § 270.62(c). 2 The final phase begins once the Agency sets the final operating conditions based on the trial burn results. See id. § 270.62(b)(10).

In 1983, the Agency issued a permit to WTI to construct a hazardous waste incinerator in East Liverpool, Ohio. The permit contained various conditions for operation and became effective in 1985. The Agency modified the permit in February 1992 to include additional pollution control equipment. 3 The incinerator has been in limited commercial operation since November 12, 1992, and it has been burning hazardous waste according to the RCRA permit limits since December 9, 1992. Greenpeace, Inc. v. Waste Technologies Indus., 9 F.3d 1174, 1177 (6th Cir.1993).

In order to receive approval for full-scale commercial operations, WTI’s permit required that the incinerator conduct an eight-day trial burn. WTI submitted a trial burn plan, which the Regional Administrator approved on January 8, 1993. At the time the Regional Administrator imposed additional restrictions regarding carbon monoxide and particulate emissions, which were incorporated into the original WTI permit. 40 C.F.R. § 270.62(c). 4 WTI conducted a trial bum *704 from March 10 to 18, 1993. Based on the initial results, the Regional Administrator notified WTI by letter of April 6, 1993, that emissions levels of carbon monoxide and particulate matter were within levels specified in the permit and that, as a result, WTI could engage in post-trial burn operations until the Agency set the final operating conditions.

Subsequent analysis, however, revealed that WTI failed to achieve the 99.99% destruction removal efficiency requirement (“DRE”), a regulatory performance standard incorporated as a condition in WTI’s permit that requires a hazardous waste incinerator to destroy 99.99% of the principal organic hazardous constituents fed into the facility. See 40 C.F.R. § 264.343(a). As a result, by letter of April 12, 1993, the Regional Administrator imposed additional restrictions on post-trial burn operations by prohibiting WTI from burning aqueous wastes and limiting the total waste feed rate into the incinerator. 5

Greenpeace filed a petition with the Appeals Board for review of the April 6th letter confirming the incinerator’s compliance with the emission limits set in the permit and, thereby, authorizing post-trial burn operations. The City of Pittsburgh, along with the State of West Virginia, petitioned the Appeals Board for review of the April 12th letter prohibiting the burning of aqueous waste and limiting the total waste-feed rate. The Appeals Board dismissed the petitions on the ground that it lacked subject matter jurisdiction because the letters arose from implementation of the WTI permit and thus were not “final permit decisions” subject to Appeals Board review pursuant to 40 C.F.R. § 124.19. In the Matter of: Waste Technolo gies Industries Hazardous Waste Incinerator Commercial Operation Permit, RCRA Appeal Nos. 93-7 & 93-9, 1993 RCRA LEXIS 105 (Jun. 21, 1993) (“Appeals Board Decision”). Greenpeace and the City of Pittsburgh now petition for review of the letters and the Appeals Board Decision. The Agency has moved to dismiss the petitions for a lack of jurisdiction.

II.

Section 7006(b) of the RCRA authorizes judicial review by federal appellate courts of the “Administrator’s action ... in issuing, denying, modifying, or revoking any permit.” 42 U.S.C. § 6976(b). Greenpeace contends that the Regional Administrator’s April 6th letter either issued WTI a permit or modified its existing permit within the meaning of § 7006(b).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
43 F.3d 701, 310 U.S. App. D.C. 50, 39 ERC (BNA) 2116, 1995 U.S. App. LEXIS 545, 1995 WL 10369, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greenpeace-inc-v-environmental-protection-agency-cadc-1995.