Greenlawn Sprinkler Corporation v. Forsberg

461 P.2d 22, 170 Colo. 286, 1969 Colo. LEXIS 745
CourtSupreme Court of Colorado
DecidedNovember 10, 1969
Docket22405
StatusPublished
Cited by6 cases

This text of 461 P.2d 22 (Greenlawn Sprinkler Corporation v. Forsberg) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greenlawn Sprinkler Corporation v. Forsberg, 461 P.2d 22, 170 Colo. 286, 1969 Colo. LEXIS 745 (Colo. 1969).

Opinion

Opinion by

Mr. Chief Justice McWilliams.

This is a contract case and the parties to the controversy are as follows: (1) Greenlawn Sprinkling Corporation, a Colorado corporation engaged in the business of installing lawn sprinkling systems and which will hereinafter be referred to as the plaintiff; (2) The Reynolds Development Corporation, hereinafter referred to as the Corporation, now defunct but at one time engaged in the business of building apartment houses; and (3) Olle S. Forsberg, the president and owner of over 90% of the stock of the Corporation, who will hereinafter be referred to as the defendant. The main issue sought to be raised in this Court is whether the several contractual obligations owed the plaintiff are personal obligations of the defendant or are the obligations of the Corporation. The trial court found that the contractual obligations under consideration were those of the Corporation and were not obligations of the defendant. By writ of error, in which the Corporation is not a designated party on error, the plaintiff seeks reversal of the judgment dismissing his complaint as to the defendant.

In its amended complaint the plaintiff alleged that the defendant entered into three separate written agreements with the plaintiff whereby the plaintiff agreed to install three described lawn sprinkling systems and the defendant agreed to pay a sum certain for each installation. As concerns each of these three agreements, which were referred to in the complaint and throughout the trial as exhibits A, B and C, plaintiff alleged that it had performed its obligations but that the defendant had in each instance failed to pay as promised. Accordingly, in connection with these three agreements, plaintiff demanded judgment against the defendant in a total sum of $6,900.36.

As relates to a fourth written agreement between *289 plaintiff and defendant, which agreement was referred to upon trial as exhibit E, plaintiff alleged that in such agreement the plaintiff again agreed to install another sprinkling system for an agreed price, that the system had in fact been installed and that the defendant had failed to pay the agreed price. In connection with this particular agreement it was further alleged that the Corporation, as opposed to the defendant, had later executed a so-called lien note, referred to throughout the trial as exhibit D, which was claimed by the plaintiff to have been given only as additional security for the payment called for by exhibit E. As concerns the so-called fourth agreement and the lien note, plaintiff sought a joint and several judgment against both the defendant and the Corporation in the sum of $5,141.65.

By answer the defendant admitted the execution by him of the four agreements with the plaintiff but denied, however, executing the lien note. In this regard, the Corporation admitted that it had executed the lien note.

A written pretrial order, signed by the trial judge and approved as to both form and content by counsel, limited the “combined issues of fact and law” to be litigated upon trial to the following matters:

“1. Whether or not, and the extent to which, plaintiff performed its promises as set forth in exhibits A, B, C and E;
“2. Whether the defendants or either of them made payments on the aforesaid agreements in excess of those amounts alleged in the complaint, and if so, in what amounts; and
“3. Whether or not the lien note, hereinabove referred to as exhibit D, operated as a satisfaction in full of defendant Forsberg’s obligation as set forth in plaintiff’s exhibit E.”

Trial of this matter was to the court and upon trial it was stipulated that a total sum of $6,900.36 plus interest and attorney’s fees was unpaid on the first three agreements, namely, exhibit A, B and C, and that the unpaid *290 indebtedness on exhibits D and E was in the sum- of $5,141.65 plus interest and attorney’s fees. As concerns exhibits D and E, the trial court found that the lien note (exhibit D) had been given by the Corporation in full satisfaction for the indebtedness created by exhibit E. Accordingly, as concerns this phase of the case the trial court entered judgment for the plaintiff and against the Corporation only in the sum of $5,141.65, plus interest costs and attorney’s fees.

During the course of the trial it became evident that notwithstanding the admissions made by the defendant in his answer and the pretrial order limiting the issues to be tried, there was an attempted shifting of defense strategy as to exhibits A, B and C. As concerns exhibits A, B and C the only issues under the pretrial order which remained to be tried were the issues as to whether the plaintiff had performed its obligations under the three agreements and the extent of the payments, if any, made by either the defendant or the Corporation on said agreements.. As above indicated, the amount of the outstanding indebtedness was stipulated to by the parties. As relatés to the issue of performance by the plaintiff, the trial court found on disputed evidence that the plaintiff had performed its obligations under the several agreements and that the several installations were not defective'.'"

However, upon trial the defendant sought to show that though he signed exhibits A, B and C in an individual capacity with no reference whatsoever in any" of these three agreements to the Corporation of which- he was then the president and majority stockholder, thát nevertheless the obligations created by such agreements were really not his, but were those of the Corporation. However, when the defendant attempted to testify along the lines above indicated, timely objection was made :by plaintiff and after extensive argument the trial court sustained the objection and ruled that exhibits A, B and C were of “sufficient nature to be considered as contracts and could not be varied by parol.”

*291 At the conclusion of the trial the court took the entire matter under advisement. One week later — in its written findings and judgment, the trial court — in its own words — “reversed” itself and held that exhibits A, B and C were not contracts, but only “work orders.” The trial court then went on to find that the defendant under the circumstances should not be held personally liable, that he had in fact contracted on behalf of the Corporation and that the Corporation- — not the defendant — should be the only party liable on any of these three agreements with the plaintiff. Accordingly, as to these three claims the trial court entered judgment for the plaintiff against the Corporation (even though plaintiff had not requested judgment on these claims against the Corporation) in a total sum of $6,900.36 plus interest costs and attorney’s fees. As concerns the defendant, however, against whom the plaintiff had sought judgment on these claims, the trial court entéred a judgment in favor of the defendant and dismissed all of the plaintiff’s claims against him. This writ of error seeks reversal of the judgment dismissing plaintiff’s several claims against the defendant and, as indicated, the proceedings in this Court concern only the plaintiff and the defendant, and do not relate to the judgment entered in favor of the plaintiff and against the Corporation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Public Service Co. of Colorado v. Board of Water Works of Pueblo
831 P.2d 470 (Supreme Court of Colorado, 1992)
Stan Miller, Inc. v. Breckenridge Resort Associates, Inc.
779 P.2d 1365 (Colorado Court of Appeals, 1989)
Coffee v. Inman
728 P.2d 376 (Colorado Court of Appeals, 1986)
North York Land Associates v. Byron Oil Industries, Inc.
695 P.2d 1188 (Colorado Court of Appeals, 1984)
Beasley v. Mincomp Corp.
683 P.2d 370 (Colorado Court of Appeals, 1984)
Barbara's Lighting Center, Inc. v. Churchill
540 P.2d 1110 (Colorado Court of Appeals, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
461 P.2d 22, 170 Colo. 286, 1969 Colo. LEXIS 745, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greenlawn-sprinkler-corporation-v-forsberg-colo-1969.