Greenfield v. Peay

209 S.W. 730, 137 Ark. 552, 1919 Ark. LEXIS 482
CourtSupreme Court of Arkansas
DecidedMarch 10, 1919
StatusPublished
Cited by1 cases

This text of 209 S.W. 730 (Greenfield v. Peay) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greenfield v. Peay, 209 S.W. 730, 137 Ark. 552, 1919 Ark. LEXIS 482 (Ark. 1919).

Opinion

HUMPHREYS, J.

This suit was instituted by appellants against appellees in the second division of the Pulaski Circuit Court on the 18th day of June, 1912, to recover $3,109 on a bond executed by appellees in that sum as sureties for the faithful performace of a contract entered into by and between appellants and the Nick Peay Construction Company, under which contract the said Nick Peay Construction Company undertook to build and furnish all material for the construction of nine vitrified pipe culverts and a concrete floodgate or dam across Pennington Bayou, near Woodson, Arkansas. The material allegations in the complaint were that the Nick Peay Construction Company signed a contract on February 25, 1910, to build the aforesaid culverts and dam or floodgate, furnishing all material and labor under a “unit bid,” meaning a fixed price for the several classes of work entering into the construction, which bid was as follows:

“Excavation, 40 cents per cu. yd.
Driving round or pin piling, 50 cents per lin. ft.
Wakefield sheet piling, $45 per 1,000 F. B. M.
Concrete, $12 per cu. yd.
Gates, complete, $2,600.
24" culverts, $2.25 per lin. ft.
18" culverts, $1.75 per lin. ft.
15" culverts, $1.50 per lin. ft.
12" culverts, $1.25 per lin. ft.
Concrete base, 40c. per lin. ft.
Cast-iron gates, $70 each.”

That said construction company was to begin work within twenty days after signing the contract and to continue and complete it on or before June 1, 1910; that appellee began the work within the time and continued it in a slow and unsatisfactory manner until after the construction company received pay on the last estimate rendered on its work by the engineer on July 8, 1910, at which time, or soon thereafter, it abandoned the work; that, at the-time of abandonment, said construction company had received a total of $5,564.50 on estimates, which included items of labor and material for construction done and materials on the ground ready to be placed in the construction; that on August 3, pursuant, to notice to appellees and the construction company, and to a letter of authorization signed by appellees, appellant took charge of the work under abandonment provisions in the contract and completed it in accordance with the terms of said abandonment provisions; that, including the amount paid said construction company on estimates, which amounts were paid with the knowledge and consent of appellees, it cost $17,394.36 to complete said contract, being $5,876.44 in excess of the sum which the work would have cost appellants if said construction company had duly performed the contract according to its bid; that it kept an account of all outlays made in the construction of the work, a copy of which account and bill of particulars, showing pay rolls, etc., was attached to the complaint and marked “Exhibit 6.”

Appellees filed answer denying all the material allegations in the complaint and counterclaim for credits on account of extra concrete, extra lumber, piling and other materials, extra labor for placing concrete and driving piling not provided for or contemplated by the contract, for which appellants had paid out large sums and not given the construction company credits in the account attached as “Exhibit 6” to the complaint; that, had proper credits been given, it would have been entitled to a judgment of $2,000 over against appellants.

Appellees answered, denying all material allegations in the counterclaim and cross-bill.

It seems that no formal motion or order was made transferring the cause to the chancery court, but, without objection by the parties, the cause was tried in the Pulaski Chancery Court. After the pleadings and depositions in the case had been read and arguments made, the chancellor, on his own motion, appointed W. D. Dickinson special master, over the protest of all the parties, authorizing him to take additional evidence, to read the evidence already taken, hear arguments and make findings on the points: “ (1) Whether the construction company had done work at too low a figure; (2) whether there was any pin-piling used in completing the work not contemplated in the original contract, and what was the value of this additional work; (3) whether there was any unreasonable delay on the part of the district in completing the work; (4) whether there was any delay on the part of the district in completing the work which involved any additional expense; (5) what additional expense was incurred by negligence or delay, if any, of the district in completing the work; and (6) what should it have cost to have finished the contract.” Without hearing further evidence or argument of council, the special master filed a report on the several points, or response to the several questions, on the 13th day of February, 1918. Exceptions to the report, attacking every part of it, were filed by appellants on the same day. Nick Peay then intervened and filed a cross-bill alleging that, according to the master’s report, appellant was indebted to him in the sum of $3,000. Appellant filed motion to dismiss- the intervention and answer denying the allegations set up in the cross-bill. On June 13, 1918, the court rendered the following decree: “Now on this day come the complainants by Messrs. Morris M. and Louis M. Cohn, their solicitors, and come the defendants, by Messrs. Cockrill & Armistead, their solicitors, and this cause having.been submitted to the court upon the pleadings and upon the depositions of Gordon E. Greefield, P. B. Hill, W. G. Stahl and Mike Kelly, and the exhibits to the said depositions, in behalf of the complainants, and upon the depositions of Nick Peay, Julius Mons, P. B. Hill, recalled, D. A. McCrea, Henry Hamilton and Gordon N. Peay, and the exhibits thereto, in behalf of the defendants, and the depositions of P. B. Hill and Gordon E. Greenfield and the exhibits thereto, in behalf of the complainants on rebuttal, and upon the report of W. D. Dickinson, special master, and the exceptions and amended exceptions filed in behalf of the complainants, and the court having heard arguments of counsel, and being well and sufficiently advised in the premises, and being of the opinion that said exceptions should be overruled, doth find that the complainants are not entitled to recover anything from the defendants herein.

“It is therefore ordered, adjudged and decreed that the said exceptions be and the same are hereby overruled, and that the complaint of the plaintiffs herein be, and the same is hereby dismissed for want of equity.”

From the findings and decree of the court, an appeal has been prosecuted to this court.

The record in this case is voluminous, but, after a careful reading and consideration of the evidence, our conclusions from it obviate the necessity of making a detailed and lengthy statement of the facts. A very general statement of the facts is sufficient upon which to base and announce our conclusions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arkansas State Game & Fish Commission v. Kizer
262 S.W.2d 265 (Supreme Court of Arkansas, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
209 S.W. 730, 137 Ark. 552, 1919 Ark. LEXIS 482, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greenfield-v-peay-ark-1919.