Greenberry Industrial, LLC v. ESI, Inc. of Tennessee

CourtDistrict Court, N.D. Georgia
DecidedFebruary 28, 2023
Docket1:22-cv-00206
StatusUnknown

This text of Greenberry Industrial, LLC v. ESI, Inc. of Tennessee (Greenberry Industrial, LLC v. ESI, Inc. of Tennessee) is published on Counsel Stack Legal Research, covering District Court, N.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greenberry Industrial, LLC v. ESI, Inc. of Tennessee, (N.D. Ga. 2023).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF GEORGIA ATLANTA DIVISION

GREENBERRY INDUSTRIAL, LLC,

Plaintiff,

v. CIVIL ACTION FILE

NO. 1:22-CV-206-TWT ESI, INC. OF TENNESSEE,

Defendant.

OPINION AND ORDER This is a breach of contract action. It is before the Court on the Plaintiff’s Motion for Partial Summary Judgment for Prejudgment Interest [Doc. 43]. For the reasons set forth below, the Plaintiff’s Motion for Partial Summary Judgment for Prejudgment Interest [Doc. 43] is DENIED. I. Background1 The Plaintiff, Greenberry Industrial, LLC (“GBI”), is an industrial fabricator that offers a variety of processing piping services. (Am. Compl. ¶ 2). The Defendant, ESI, Inc. of Tennessee (“ESI”), is a general contractor that provides engineering, procurement, and construction services to support energy projects. ( ¶ 4). In the present case, ESI subcontracted GBI to provide certain services in support of a boiler replacement project in Port Hudson,

1 The operative facts on the Motion for Partial Summary Judgment are taken from the parties’ Statements of Undisputed Material Facts and the responses thereto. The Court will deem the parties’ factual assertions, where supported by evidentiary citations, admitted unless the respondent makes a proper objection under Local Rule 56.1(B). Louisiana (“the Project”), and the parties memorialized their agreement in a final purchase order (“the Subcontract”). (Pl.’s Statement of Undisputed Material Facts ¶ 1). The Subcontract specified that ESI would pay GBI

$4,118,209 for its mechanical work on the Project. ( ¶ 4). After entering into the Subcontract, GBI and ESI also executed six Change Orders that altered the scope of GBI’s work on the Project—though the parties dispute the validity of certain wording in the Change Orders. ( ¶¶ 5–8; Def.’s Resp. to Pl.’s Statement of Undisputed Material Facts ¶¶ 5–8). The six Change Orders increased the amount owed to GBI under the Subcontract to $5,026,253.06.

(Pl.’s Statement of Undisputed Material Facts ¶ 8). GBI completed its work on the Project on September 29, 2021. ( ¶ 17). Throughout the course of its work on the Project, GBI submitted several work invoices to ESI. ( ¶ 18). Prior to the filing of this lawsuit, ESI had paid GBI $2,783,803.98 for its work on the Project. ( ¶ 22). On January 18, 2022, GBI filed the present action, alleging that ESI failed to pay the full amount owed for the services it performed under the

Subcontract and the Change Orders. On July 27, 2022, ESI counterclaimed for damages, alleging that GBI failed to perform its duties under the Subcontract and the Change Orders, among other pleaded claims. Then on August 29, 2022, ESI made a payment to GBI totaling $1,376,635.70, which primarily applied to principal owed by ESI to GBI on the Project. ( ¶ 25). On September 20, 2022, ESI made another payment of $90,925.46 to GBI for principal retainage. 2 ( ¶ 33). GBI now moves for partial summary judgment to recover prejudgment interest on the principal payments made by ESI in August and September of 2022.

II. Legal Standard Summary judgment is appropriate only when the pleadings, depositions, and affidavits submitted by the parties show that no genuine issue of material fact exists, and that the movant is entitled to judgment as a matter of law. Fed. R. Civ. P. 56(a), (c). The court should view the evidence and draw any inferences in the light most favorable to the nonmovant.

, 398 U.S. 144, 158–59 (1970). The party seeking summary judgment must first identify grounds that show the absence of a genuine issue of material fact. , 477 U.S. 317, 323–24 (1986). The burden then shifts to the nonmovant, who must go beyond the pleadings and present affirmative evidence to show that a genuine issue of material fact exists. , 477 U.S. 242, 257 (1986). III. Discussion

GBI moves for partial summary judgment to recover prejudgment interest on principal payments that ESI made to GBI in August and September of 2022. GBI argues it is entitled to the prejudgment interest because ESI delayed ten months in making the payments despite having been compensated in full by the project owner on November 30, 2021. (Br. in Supp. of Pl.’s Mot. for Partial Summ. J., at 1–2). In total, GBI claims an interest award of 3 $252,213.17, calculated from a 1.5% monthly interest rate under O.C.G.A. § 7-4-16. ( at 2). In response, ESI argues that an award of prejudgment interest is inappropriate for several reasons. ESI argues that an interest award

under O.C.G.A. § 7-4-16 requires the pleading of a claim for an open or commercial account, and not a breach of contract claim as pleaded by GBI. (Def.’s Resp. Br. in Opp’n to Pl.’s Mot. for Partial Summ. J., at 2). ESI also contends that a 7% annual interest rate, not a 1.5% monthly rate, is the appropriate rate under O.C.G.A. § 7-4-2. ( ). Finally, ESI claims that genuine issues of material fact remain as to when interest on the principal began to

accrue. ( at 2–3). The Court first considers whether a genuine dispute of material fact exists as to the accrual and owing of GBI’s claimed interest and then considers the commercial account and interest rate issues. A. Accrual and Owing of Interest GBI claims that the Subcontract required ESI to pay GBI’s invoices within 30 days of their receipt and that its failure to do so resulted in the accruing of prejudgment interest on the outstanding principal amounts

beginning after the 30-day payment periods. (Br. in Supp. of Pl.’s Mot. for Partial Summ. J., at 22). In response, ESI claims that under the Subcontract, it was entitled to withhold payment on GBI’s invoices because GBI breached the Subcontract. (Def.’s Resp. Br. in Opp’n to Pl.’s Mot. for Partial Summ. J., at 19–20). ESI also claims that it was entitled to withhold payment under the Subcontract because GBI filed a lien on the Project’s premises. ( at 20). In 4 reply, GBI argues primarily that ESI’s justifications for nonpayment are “legally meritless” because they are conclusory allegations unsupported by specific facts and because they run contrary to the express terms of the

Subcontract. (Reply Br. in Supp. of Pl.’s Mot. for Partial Summ. J., at 11–15). Relevant to the parties’ arguments, the Subcontract’s General Terms and Conditions provide the following: Contractor [ESI] shall pay to Subcontractor [GBI], within 30 days of receipt of the approved invoice, an amount equal to the value of Subcontractor’s completed work, less all previous payments, and less the amount of current retainage. . . .

Contractor shall have the right to withhold payment to Subcontractor for defective work not remedied and for any other breach of this Subcontract by Subcontractor.

(Stark Decl., Ex. 1-B at 2–3, § 5). Several counterclaims by ESI for breach of contract against GBI remain pending before the Court, including allegations of GBI’s delayed performance and defaults, among other alleged breaches. ( Countercls. ¶¶ 31–51).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Adickes v. S. H. Kress & Co.
398 U.S. 144 (Supreme Court, 1970)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Martin v. Rollins, Inc.