Green & Sons Co. v. State

9 Ill. Ct. Cl. 218, 1936 Ill. Ct. Cl. LEXIS 53
CourtCourt of Claims of Illinois
DecidedApril 29, 1936
DocketNo. 2038
StatusPublished
Cited by2 cases

This text of 9 Ill. Ct. Cl. 218 (Green & Sons Co. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Green & Sons Co. v. State, 9 Ill. Ct. Cl. 218, 1936 Ill. Ct. Cl. LEXIS 53 (Ill. Super. Ct. 1936).

Opinions

Per Curiam:

Claimant filed its complaint herein on December 31st, 1932 and seeks to recover the sum of $75,000.00 as the reasonable value of certain services rendered during the period from November 1st, 1927 to September 1st, 1928, as superintendent of construction on contracts Nos. 5 and 6 of the Illinois Waterway, otherwise known as the retaining wall, lock and dam for the Brandon Road Pool.

Claimant had previously filed its claim herein, to wit, on July 12th, 1928 (Case No. 1339 reported 6 C. C. R. 373) seeking to recover for the services involved in the present claim, but based upon a contract in writing made and entered into by and between said claimant and the respondent, through its Department of Purchases and Construction, which said contract was approved and accepted by said respondent on October 27th, 1927. In its original claim filed on July 12th, 1928 as aforesaid, claimant sought to recover the sum of $50,692.49 for services rendered during the months of November and December, 1927 and from January to July, 1928. Thereafter, pursuant to leave of court, claimant increased the amount of its original claim from $50,692.49 to $78,095.90, the additional sum of $27,403.41 being for similar services claimed to have been rendered during the months of July and August, 1928.

Previous to November, 1927 claimants had entered into a contract with the respondent for the construction of a portion of the Illinois Waterway. About November 1st, 1927 the Department itself took over the construction of the work on such Waterway, pursuant to the provisions of the Illinois Waterway Act hereinafter referred to.

The provisions of the Illinois Waterway Act particularly involved in the claim now under consideration (as well as in the previous claim) are sections 12 and 13 of the Illinois Waterway Act — State Bar Association Revised Statutes 1935 — Chapter 19, Paragraphs 102 and 103, which are as follows, to-wit:

“Sec. 12. In the construction of such waterway, its appurtenances and appliances, the Department of Public Works and Buildings may, in its judgment and discretion, proceed in either of the following ways:
(1) It may let the same or any part or portion thereof to the lowest responsible bidder; or
(2) It may do the same or any part or portion thereof, by the direct employment of services, labor, materials and equipment, and may procure and employ for such purpose the necessary superintendents, agents, office force, laborers, workmen, implements, tools, machinery and all other employees, equipment and services necessary or incidental to such construction.
Sec. 13. Before any contract entailing the expenditure of five thousand dollars or more is entered into, public notice shall be given of the time and place at which proposals shall be received for entering into contracts, which notices shall be previously published for at least once a week for four weeks in two daily newspapers printed in the city of Chicago, in two engineering and contracting journals of general circulation in the United States, and in such other publication as may be deemed proper.”

When the work was taken over by the Department of Purchases and Construction as aforesaid, such Department entered into the aforementioned contract of October 27th, 1927 with the claimant, for the superintendence of the work and the use of its machinery and its equipment in the doing of such work. Such contract provided that the claimant should receive ten per cent (10%) of the “Fee Cost” as therein defined, as compensation for its services as superintendent, and was made without any compliance with the aforementioned provisions of the Illinois Waterway Act with reference to advertising for competitive bids where the amount of the contract is in excess of $5,000.00.

Thereafter a question as to the validity of the contract was raised by the Auditor of Public Accounts, and the matter was submitted to Oscar Carlstrom, then Attorney General, for an opinion thereon. He advised (Attorney General’s Report 1929, p. 227) that the contract was invalid.

Thereafter a public letting was held, and claimant was awarded the contract for the completion of the work on substantially the same terms as the previous contract which had been declared invalid.

The claim originally filed by the claimant on July 12th, 1928 as aforesaid, was for the recovery of the amount claimed to be due it under its aforementioned contract of October 27th, 1927.

The then Attorney General contested the allowance of the claim upon the hearing thereof, this court held — 6 C. C. R. 373 — that the contract in question was in violation of the aforementioned sections of the Waterway Act, and therefore invalid, and refused to allow an award. Petition for rehearing was filed and denied.

Thereafter, to-wit, on December 31st, 1932, claimant filed its aforementioned complaint in this cause to recover the reasonable value of the services rendered by it pursuant to the aforementioned contract of October 27th, 1927.

The present complaint, however, is not based upon the contract, but is based upon the quantum meruit; for the recovery of the reasonable value of the services rendered.

The Attorney General makes the following contentions in this case, to-wit:

1. That the former decision of this court, reported in 6 C. C. R. 373, in which the contract of October 27th, 1927 was held invalid, is res adjudicata and constitutes an absolute bar to the present claim.

2. That even though the former decision of this court is not a bar to the present claim, claimant is not entitled to recover on the quantum meruit for the services rendered.

3. That in any event, this court has no jurisdiction in this case.

We will consider the questions raised by the Attorney General in the order above stated.

I.

The question as to when the doctrine of res adjudicata may be applied has been considered by the courts of this State in many, many cases. The general principles of law with reference thereto seem to be well established, but the application of such principles is not always free from difficulty.

We will refer only to a few of the more recent decisions, as we feel that such decisions set forth the principles of law which must govern us in the determination of the question here involved.

In the case of Hoffmam vs. Hoffman, 330 Ill. 413, the facts were entirely different from the case at bar, but the court had occasion to consider the general principles of law which must govern in cases where a previous adjudication is relied upon as an absolute bar to a subsequent claim. In that case the court, on pages 417 and 418, said:

“Where a former adjudication is relied upon as an absolute bar, there must be, as between the actions, identity of parties, of subject matter and of cause of action. When the second action between the same parties is upon a different claim or demand, the judgment in the prior action operates as an estoppel only as to those matters in issue or points controverted upon the determination of which the finding or verdict was rendered.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wulf v. State
51 Ill. Ct. Cl. 383 (Court of Claims of Illinois, 1999)
Wilder Mobile Homes, Inc. v. State
33 Ill. Ct. Cl. 227 (Court of Claims of Illinois, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
9 Ill. Ct. Cl. 218, 1936 Ill. Ct. Cl. LEXIS 53, Counsel Stack Legal Research, https://law.counselstack.com/opinion/green-sons-co-v-state-ilclaimsct-1936.