Green Mountain Power Corp. v. Sprint Communications

779 A.2d 687, 172 Vt. 416, 2001 Vt. LEXIS 262
CourtSupreme Court of Vermont
DecidedAugust 17, 2001
Docket00-155
StatusPublished
Cited by8 cases

This text of 779 A.2d 687 (Green Mountain Power Corp. v. Sprint Communications) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Green Mountain Power Corp. v. Sprint Communications, 779 A.2d 687, 172 Vt. 416, 2001 Vt. LEXIS 262 (Vt. 2001).

Opinion

*417 Amestoy, C.J.

This appeal arises from a determination made by the Vermont Public Service Board pursuant to an assertion of jurisdiction under 30 V.S.A. chapter 86, Underground Utility Damage Prevention System. Respondent Sprint appeals the summary judgment granted by the Board in favor of petitioner Green Mountain Power (GMP), relieving GMP of liability for causing damage to one of its fiber optic cables during an excavation. Because we find that the Legislature did not intend to confer authority on the Board to decide issues of common law negligence arising from excavation activities undertaken pursuant to 30 V.S.A. chapter 86, we reverse.

GMP intended to excavate a site located in White River Junction. Under 30 V.S.A. § 7004, GMP was required to notify the utility companies and allow them forty-eight hours, weekends and holidays excluded, to mark the presence of underground wiring at the site, if any. 1 As required by Public Service Board Rule 3.800, on Thursday, September 5, 1996, GMP notified Dig Safe System, Inc. of the proposed excavation. By Monday morning, September 9, all parties except Sprint had marked the site as required by 30 V.S.A. § 7006. 2 Shortly after 8:00 a.m., the supervisor of the excavation received a phone call that purported to be from a Sprint employee, authorizing GMP to excavate. Sometime between 8:15 and 8:25 a.m., the excavator for GMP struck and damaged a fiber optic cable owned by Sprint. When Saturday and Sunday, September 7 and 8 are excluded, less than 48 hours had elapsed between GMP’s notice and the damage to the cable.

GMP filed a petition with the Board requesting a declaratory ruling that it was not liable under 30 V.S.A. chapter 86 for damage to Sprint’s fiber optic cable caused by the excavation. GMP also requested that the Board declare that Sprint was subject to the civil penalty provided *418 in 30 V.S.A. §7008(b)-(c) for its failure to mark its underground facilities as required by 30 V.S.A. § 7006. 3

Sprint and GMP filed cross-motions for summary judgment. The Public Service Board issued its final order on February 23, 2000. The Board denied GMP’s motion that it impose a penalty on Sprint finding that there was not an actual failure to fulfill its statutory requirements. The Board reasoned that since the 48 hours had not yet run, Sprint did not violate § 7008(c), regardless of whether they would have been able to mark the site within that period. The Board also held that GMP had violated 30 V.S.A. § 7004 by initiating the excavation before the 48-hour waiting period required by the statute, and therefore, imposed a civil penalty of $1,000 on GMP, as provided for in 30 V.S.A. § 7008(a).

The Board also found that § 7008(a) did not create an independent basis of liability for damages, nor establish a per se rule of strict liability, and held that, under common law negligence, GMP was not liable for the damages. The Board found that GMP had successfully shown that the accident would have occurred even if the excavator had waited until the 48-hour period had run out, and that therefore GMP’s failure to wait was not the proximate cause of Sprint’s injury. The Board concluded that even if GMP’s failure was a proximate cause, Sprint’s failure was at least as great as GMP’s, which would preclude recovery by Sprint under Vermont’s comparative negligence law. Sprint appeals the Board’s decisions regarding GMP’s liability.

On appeal, Sprint contends that 30 V.S.A. § 7008(a) imposes strict liability for money damages where an excavator does not comply with the procedures set out in the statute. Sprint argues that GMP’s failure to comply with the 48-hour waiting period as required by § 7004 resulted in damages to Sprint’s fiber optic cable, and therefore GMP is strictly liable for those damages.

I

We begin by observing that both parties and the Board assumed that the statutory scheme pursuant to which GMP’s request for a *419 declaratory judgment was filed provides the Board with the jurisdiction to determine liability for damages based on common law theories of negligence. Sprint’s motion for summary judgment claimed 30 V.S.A. § 7008 was evidence of “an unambiguous legislative intent to vest all aspects of underground utility excavation regulation, including the award of damages, in the Public Service Board and not the courts.” GMP did not contest the Board’s jurisdiction to act on Sprint’s motion with respect to the issue of liability between Sprint and GMP, but argued that sufficient material facts were in dispute to make an award of summary judgment to Sprint inappropriate. The Board asserted that “[t]he statute that controls here, 30 V.S.A. § 7008, clearly vests the Board with jurisdiction to decide this matter, including the determination of liability for the damage to Sprint’s cable, determination of the amount of damages to be paid by the party found to be liable for that damage, and the imposition of civil penalties.” (Emphasis added.)

Ordinarily, public service boards and commissions do not have the authority to rule on claims for damages alleged to have been caused by negligence or breach of contractual obligations on the part of corporations subject to their supervision. See Trybulski v. Bellows Falls Hydro-Electric Corp., 112 Vt. 1, 9, 20 A.2d 117, 121 (1941). The Public Service Board “is a body exercising special and statutory powers not according to the course of the common law, as to which nothing will be presumed in favor of its jurisdiction.” Id. at 7, 20 A.2d at 120. The Board “has only such powers as are expressly conferred upon it by the Legislature, together with such incidental powers expressly granted or necessarily implied as are necessary to the full exercise of those granted.” Id.

The provision of the Underground Utility Damage Prevention System statute most directly relied upon by the parties and the Board to address the claim of negligence is 30 V.S.A § 7008(a):

Any person who violates any provisions of sections 7004, 7006a, 7006b or 7007 of this title shall be subject to a civil penalty of up to $1,000.00, in addition to any other remedies or penalties provided by law or any liability for actual damages.

Both parties agree that § 7008(a) authorizes the Board to impose a civil penalty of up to $1,000. The conflict in the interpretation of the statute arises from the phrase “in addition to any other remedies or penalties provided by law or any liability for actual damages.”

*420 Sprint argues that the phrase sets forth two additional consequences which the violator may face in addition to the civil penalty: 1) any other remedies or penalties provided by law; or 2) any liability for actual damages. For Sprint, the use of the word “or” signifies a legislative intention to create a separate category that imposes strict liability without regard to civil negligence standards.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

North Country Sportsman's Club v. Town of Williston
2017 VT 46 (Supreme Court of Vermont, 2017)
Petersen v. Magna Corp.
773 N.W.2d 564 (Michigan Supreme Court, 2009)
In Re Doolittle Mountain Lots, Inc.
2007 VT 104 (Supreme Court of Vermont, 2007)
State v. Anderson
2005 VT 80 (Supreme Court of Vermont, 2005)
In Re MacIntyre Fuels, Inc.
2003 VT 59 (Supreme Court of Vermont, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
779 A.2d 687, 172 Vt. 416, 2001 Vt. LEXIS 262, Counsel Stack Legal Research, https://law.counselstack.com/opinion/green-mountain-power-corp-v-sprint-communications-vt-2001.